Skip to main content

Full text of "Nkandla Report Thuli Madonsela Jacob Zuma"

See other formats


Report on an investigation into allegations of impropriety and 
unethical conduct relating to the installation and implementation of 
security measures by the Department of Public Works at and in respect of 
the private residence of President Jacob Zuma at Nkandla in the 

KwaZulu-Natal province 

Report No: 25 of 2013/14 • ISBN: 978-1-920692-15-5 



PUbLIC PPOTFCTOP. 
SOUTH AFRICA 

Accountability • Integrity • Responsiveness 




Website: www.publicp 



Follow us: 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



Executive Summary 4 

1. INTRODUCTION 78 

2. THE COMPLAINTS 80 

3. THE POWERS AND JURISDICTION OF THE PUBLIC PROTECTOR 86 

3.1 . Mandate of the Public Protector 86 

3.2. The legal framework of the investigation 88 

3.3. Balancing State Security Considerations with Open Democracy Requirements 92 

3.4. Security Cluster objections to the investigation and preference for 
investigations by the SIU and Auditor General 96 

3.5. The Alleged Leaking of Information from the Provisional Report: 103 

4. THE ISSUES CONSIDERED AND INVESTIGATED 106 

5. THE INVESTIGATION 108 

6. THE EVIDENCE AND INFORMATION OBTAINED DURING THE 
INVESTIGATION 127 

PART A: EVIDENCE ON THE SEQUENCE OF EVENTS 127 

PART B: THE EVIDENCE ON THE GOODS AND SERVICES 

PROCURED BY THE DPW 183 

PART C: THE SUPPLY CHAIN MANAGEMENT PROCESS 192 

PART D: EVIDENCE ON SPECIFIC ISSUES CONSIDERED 

DURING THE INVESTIGATION 200 

PART E: EVIDENCE ON THE INVOLVEMENT OF THE INDUSTRIAL 
DEVELOPMENT CORPORATION AND ALLEGATIONS OF IMPROPER 

BENEFITS AFFORDED TO THE PRESIDENT'S BROTHERS 253 

PART F: THE INTERNAL TASK TEAM REPORT 263 



2 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC F>EO>TE<:.TOk 
SC^UTH flfPKU 



PART G: THE RESPONSES SUBMITTED BY THE PRESIDENT IN 

REPLY TO QUESTIONS PUT TO HIM DURING THE INVESTIGATION 269 

7. EVALUATION OF THE EVIDENCE AND INFORMATION OBTAINED 
DURING THE INVESTIGATION 284 

PART A: SEQUENCE OF EVENTS 284 

PART B: THE GOODS AND SERVICES PROCURED BY THE DPW 292 

PART C: THE SUPPLY CHAIN MANAGEMENT PROCESS 293 

PART D: SPECIFIC ISSUES CONSIDERED DURING THE 

INVESTIGATION 301 

PART E: THE INVOLVEMENT OF THE IDC AND ALLEGATIONS OF 
IMPROPER BENEFITS AFFORDED TO THE PRESIDENT'S BROTHERS 336 

8. THE LEGAL AND REGULATORY FRAMEWORK 350 

9. ANALYSIS AND CONCLUSION 387 

10. FINDINGS 427 

11. REMEDIAL ACTION 442 

12. MONITORING 446 



3 



Secure In Comfort A Report of the March 2014 



Public Protector 



Executive Summary 

"Given the very humble beginnings of this project, nothing short of a full township 

establishment is now required. .." 

(Comment of the Director: Architectural Service of the Department of Public Works addressed to 
the Acting Director-General of the Department on the Nkandla Project at the end of August 201 0) 



"Our government is the potent, the omnipresent teacher. For good or for ill, it 
teaches people by example. . . If the government becomes a law breaker, it 
breeds contempt for law; it invites every man [person] to become a law; unto 

himself..." 

Justice Louis D Brandeis, US Supreme Court Justice. 



(i) "Secure in Comfort' is my report as the Public Protector of the Republic of 
South Africa on an investigation conducted into allegations of impropriety and 
unethical conduct relating to the installation and implementation of security 
and related measures at the private residence of the President of the 
Republic of South Africa, His Excellency J G Zuma, at Nkandla in the 
KwaZulu-Natal Province. 

(ii) At the time the remark of the Director: Architectural Services of the 
Department of Public Works (DPW) is made, the cost estimation for the 
project was R145 million. By the time I concluded this investigation R215 
million had been spent while the total cost to conclude the project was 
conservatively estimated at R246 million. 

(iii) The investigation was conducted in terms of section 182 of the Constitution, 
1996, which gives the Public Protector the power to investigate alleged or 



4 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC PISOTCCTOf? 
SOUTH flfPICfl 

suspected improper or prejudicial conduct in state affairs, to report on that 
conduct and to take appropriate remedial action; and in terms of section 6 
and 7 of the Public Protector Act, 23 of 1994, which regulate the manner in 
which the power conferred by section 182 of the Constitution may be 
exercised. Part of the investigation was also conducted in terms of the 
Executive Members' Ethics Act, 82 of 1998, which confers on the Public 
Protector the power to investigate alleged violations of the Executive Ethics 
Code, at the request of Members of National and Provincial Legislatures, the 
President and Premiers. 



(iv) The investigation was carried out in response to seven complaints lodged 

between 13 December 201 1 and November 2012. The first complaint, from a 
member of the public was lodged in terms of the Public Protector Act on 13 
December 201 1 . Other complaints followed thereafter, also lodged under the 
Public Protector Act. Further complaints were received from ordinary 
members of the public and a year after the first complaint, a Member of 
Parliament lodged a complaint under the Executive Members' Ethics Act. 

(a) The first complainant requested an investigation into the veracity of 
allegations published by the Mail and Guardian newspaper on 1 1 November 
2011, under the heading: "Bunker, bunker time: Zuma's lavish Nkandla 
upgrade". According to this media report the President's private residence 
was being improved and upgraded at enormous expense to the state, 
estimated at about R65 million. The impugned improvements allegedly 
included a network of air conditioned living quarters, a clinic, gymnasium, 
numerous houses for security guards, underground parking, a helicopter pad, 
a playground and a Visitors' Centre. 

(b) The earliest concerns regarding opulent or excessive expenditure at the 
private residence of President Zuma were expressed on 04 December 2009 



5 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

by the Mail and Guardian in an article titled "Zuma's R 65 million Nkandla 
Splurge". Apart from the release of a statement by the Presidency on 03 
December 2009, denying that government was footing the bill, nothing seems 
to have been done by government to verify the 2009 allegations or attempt to 
arrest the costs which the article predicted would continue to rise. Three 
years later and a year after a complaint was lodged with my office, the 
Minister of Public Works appointed a Task Team of officials from the 
departments involved in the impugned upgrades at the President's private 
residence, to investigate specified matters in relation therewith. The Task 
Team's report was released to the public on 19 December 2013. 

(c) More items were added to the project after the concerns were raised in 2009, 
bringing the cost from the initialR65 million, which was the subject of 
complaint in 2009, to R215 million, which has since been spent, while 
outstanding work is currently estimated at R36 million bringing the envisaged 
total cost to R246 million. 

(d) Some of the key questions in the written complaints were the following: 

(1 ) "Where is the money coming from and how has it been approved?" 

(2) "Whether any undue political influence was placed on the Department of 
Public Works to allocate these funds."; 

(3) "Who issued the instruction for the allocation of these funds;" 

(4) "Whether these funds have been properly budgeted for;" 

(5) "Whether any funds have been transferred from other much needed 
projects for this revamp to take place;" 



6 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




JCjLIC F>EO>TE<:.TOk 



(6) "Whether the allocation of funds for what is essentially a private home- 
which will not remain within the state's ownership-represents irregular 
expenditure. " 

(7) "How can this amount of money be spent on a private residence of any 
government employee" 

(8) The additional complaints raised issues regarding the possible abuse of 
Executive privileges, impropriety, extending benefits to relatives and 
misleading Parliament. 

(9) Included in the complaints were the following significant statements: 

"I do not understand how this money can be spent on a private 
residence of any government employee, especially when that employee 
has two residences at his disposal in Cape Town and Pretoria. " 

"Whether this construction is being performed for President Zuma as 
President of SA or as a favour as ANC President, I would suggest it is 
misuse of state funds to the benefit of a private individual, possibly to 
curry political favour for the Minister of Public Works or a DG. When the 
President is no longer the incumbent he is not entitled to state housing 
but he will enjoy the benefits of the modifications to his private estate in 
perpetuity . " 

" While the majority of people in this country still struggle and fight for 
survival it is deeply disturbing to discover that the President and some 
of his close senior supporters feel that it is all right to abuse their 
positions to benefit themselves and each other at the expense of the 

7 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

nation and all her citizens. These individuals, in their capacities as 
servants of the people, should be held to task if they are in any way 
guilty of wrongdoing, abuse of power or corruption. If the allegations in 
the press on what is happening with the President's private homestead 
in Nkandla are true then the President and those involved in facilitating 
these massive renovations are possibly guilty of a number of 
transgressions and should be held accountable. At the least these 
allegations should be grounds for you and your team to conduct some 
sort of investigation. " (emphases added) 



(e) In essence the complainants alleged that: 



(1) There was no legal authority for the expenditure that was allegedly 
incurred by the state in respect of upgrades made at the President's 
private residence in the name of security. Even if there was authority, 
the upgrades were excessive or "opulent" and transcended such 
authority. 

(2) The procurement process was improper, in violation of the prescribed 
Supply Chain Management policy framework and resulted in unduly 
excessive amounts of public money being spent unnecessarily. 

(3) The conduct of the President in relation to the implementation of the 
impugned upgrades at his private residence may have been unethical 
and in violation of the Executive Ethics Code. 



(v) Based on an analysis of the complaints, the following issues were identified 

and investigated: 



8 



A Report of the 
Public Protector 



March 2014 




(1) 

(2) 

(3) 

(4) 
(5) 

(6) 
(7) 
(8) 
(9) 



Was there any legal authority for the installation and implementation of 
security measures and the construction of buildings and other items by 
the state at the President's private residence and was such authority 
violated or exceeded? 

Was the conduct of relevant authorities in respect of the procurement of 
goods and services relating to the upgrades, improper and in violation 
of relevant Supply Chain Management prescripts? 

Did the measures taken by the Department of Public Works (DPW) at 
the President's private residence, go beyond what was required for his 
security? 

Was the expenditure incurred by the state in this regard excessive or 
amount to opulence at a grand scale, as alleged? 

Did the President's family and/or relatives improperly benefit from the 
measures taken, buildings and other items constructed and installed at 
the President's private residence? 

Was there any maladministration by the public office bearers, officials 
and other parties involved in this project? 

Was there any political interference in the implementation of this 
project? 

Were funds transferred from other much needed DPW projects to fund 
this project? 

Is the President liable for some of the cost incurred? 



9 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC F>EO>TE<:.TOk 
SOUTH flfPKU 



(10) Were there ethical violations on the part of the President in respect of 
this project? 



(11) Are there other maladministration issues that arose from the complaints 
and the investigation process? 

(12) Are there systemic deficiencies regarding the administration of benefits 
of Presidents, Deputy Presidents, former Presidents and former Deputy 
Presidents? 



(vi) The investigation focused on security installations at the President Zuma's 

private residence situated at a village known as Nkandla in Kwa-Zulu Natal 
where he was born and spent most of his life, save for the years when he 
was in prison and later exiled. President Zuma is the fourth President of 
democratic South Africa. The security installations commenced shortly after 
he was elected and sworn in during May 2009. 



(a) The period covered by the investigation runs from the date of first 
assessment of the requirements to upgrade the security at the President's 
private residence on 19 May 2009 to the end of January 2014. 

(b) The substantive scope focused on compliance with applicable laws and 
policies in relation to security privileges accorded to Presidents, Deputy 
Presidents, former Presidents and former Deputy Presidents; compliance 
with Supply Chain Management prescripts; and the propriety of the conduct 
of the President and others allegedly involved in the implementation of the 
impugned upgrades. 



10 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



(c) The laws and policies that informed the investigations were principally those 

relating to the authority to implement the upgrades being the Cabinet Policy 
of 2003 and the National Key Points Act, 102 of 1980 and those relating to 
procurement, being section 217 of the Constitution, the Preferential 
Procurement Policy Framework Act, 5 of 2000, the Public Finance 
Management Act, 1 of 1999 and Treasury Regulations. In relation to the role 
of the Department of Defence (DOD), the provisions of the South African 
Defence Review of 1 998, and the Defence Act, 42 of 2002 were considered 
together with institutional policies regulating the provision of medical support 
and securing the President and others while in transit. With regard to 
procurement, section 217 of the Constitution was applied. 



(d) I was particularly mindful of the fact that the current regulatory framework 

does not distinguish between permissible measures for securing the private 
residences of Presidents, Deputy Presidents, former Presidents and Deputy 
Presidents. In respect of the DOD I was further mindful of the fact that the 
regime relied on for the provision of health care, being paragraph 22 of 
Chapter 7 of the Defence Review, covers the President, Deputy President, 
Minister and Deputy Minister of Defence and foreign dignitaries visiting South 
Africa. In other words, if I were to reach a conclusion that what was done at 
Nkandla was permissible for a sitting President, I would be saying that the 
same measures are permissible for the others. This would inevitably lead to 
questions of affordability and sustainability, not only in the context of the 
current fiscal climate, but also in terms of balancing competing needs of 
South Africa as a developmental state against the backdrop of section 237 of 
the Constitution, which directs that "All constitutional obligations must be 
performed diligently and without delay" and the Batho Pele, White Paper on 
Transforming Public Service Delivery (1997) which undertakes to transform 
an inherited insular state to one that puts people first as the true targeted 
beneficiaries of public resources and services. 



11 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



JCjLIC F>EO>TE<:.TOk 



(e) The conduct of the President was primarily assessed against the pursuit of 

ethical standards imposed on members of the executive by section 96 of the 
Constitution and the Executive Ethics Code issued under the Executive 
Members' Ethics Act. To unpack the provisions of the Constitution and the 
code, I took into account previous investigations of the Public Protector on 
executive privileges notably the investigations that had scrutinized the 
conduct of the Minister of Police in relation to accommodation privileges, the 
then Minister of Cooperative Governance and Traditional Affairs on 
accommodation and travelling privileges and the Minister of Agriculture, 
Forestryand Fisheries on the same issues. With regard to the Minister of 
Police, the findings of the Auditor General regarding alleged excesses in 
relation to the construction of a security wall at his private homestead, were 
also taken into account in compliance with laws and related standards 
regulating the provision of medical support and securing Presidents and the 
others while in transit, were also considered count. 



(f) Consideration was also given to global benchmarks, principally on the role of 

those entrusted with public power and resources regarding the exercise of 
such power and balancing people's rights to resources and self-maintenance 
privileges for 'trustees'. 



(g) My approach to the investigation included the following measures: 



(1) Correspondence, which commenced with alerting the Presidency to 
the allegations in January 2012 and a letter of acknowledgement on the 
same day. Further correspondence was entered with the Presidency, 
the Ministers of Defence and Military Veterans, Police and Public 
Works; the Deputy Minister of Women, Children and Persons with 
Disabilities; Departments of Defence, Police and Public Works; 



12 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




Complainants and various parties involved in the project, including 
contractors; and the Acting State Attorney. The latter wrote to me on 24 
April 2013, advising on a suspension of my investigation, responded to 
by the head of my private office on 10 May 2013, clarifying the legal and 
constitutional position regarding Public Protector investigations and the 
status of the current investigation at the time. 

(2) Interviews conducted with Ms G Mahlangu-Nkabinde, the former 
Minister of Public Works (telephonically) on 23 August 2013; Deputy 
Minister H Bogopane-Zulu, who was the Deputy Minister of Public 
Works at times material to the investigation on 14 May 2013; Officials of 
the DPW, the South African Police Service (SAPS) and DOD, selected 
contractors that were involved in the Nkandla Project. Meetings were 
also held with President Zuma on 11 August 2013; Dr C R Lubisi, the 
Director-General in the Presidency, in January 2012; The Ministers of 
Police, Mr N Mthethwa, Public Works, Mr T W Nxesi and State Security, 
Dr S Cwele on 22 April 2013, 31 May 2013, and 8 August 2013 
respectively. The meeting of 31 May 2013 was also attended by the 
Chief State Law Adviser, Mr E Daniels, and other high ranking officials 
of the Departments involved; the Minister of Justice and Constitutional 
Development, Mr J Radebe, who also attended the meeting of 31 May 
2013; The Minister of Public Works on 2 July 2013; The Minister of 
Defence and Military Veterans, Ms N Mapisa-Nqakula, who also 
attended the meetings of 31 May and 8 August 2013; The former 
Surgeon-General, Lt Gen V Ramlakan; and the Acting Chief of Staff of 
the Ministry of Police, Ms J Irish-Qhobosheane. 

(3) Analysis of voluminous documents such as correspondence; 
applicable laws incorporating legislation and case law; relevant policies 
regulating security upgrades at private residences; supply chain policies 



13 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

and supplementary prescripts and touch stones or established 
principles from previous Public Protector Reports; 

(4) An inspection in loco on 12 August 2013, aimed at verifying and 
assessing the works implemented by the DPW at the President's private 
residence, accompanied by the Minister of Defence, a member of the 
investigation team and officials from the DPW and the security cluster; 
and 

(5) Submissions in terms of section 7(9) of the Public Protector Act by 

parties that appeared to be implicated during the investigation. 

(h) Limitations of the investigation: 

(1) The investigation took approximately two years, which exceeds the one 
year target the Public Protector South Africa team has set for complex 
investigations. The delays can be attributed to: 

1 . Internal capacity constraints; 

2. Access to classified information; 

3. Access to the report of the internal Task Team appointed by the 
Minister of Public Works; 

4. Objection lodged by the Minister of Police on 22 March 2013, later 
supported by the Ministers of Public Works and State Security with the 
assistance of the Acting State Attorney and the Chief State Law Advisor 
to the investigation; 



14 



Secure In Comfort 



A Report of the 
Public Protector 




(vii) 
(a) 

(b) 
(c) 



5. General delays in access to information held by some departments 
involved in the Nkandla Project; and 

6. Requests for extensions to submit responses to notices issued in terms 
of section 7(9) of the Public Protector Act. 

(2) When the Executive Members' Ethics Act dimension was added in 
December 2012, the 30 day period stipulated in this Act could not be 
met, primarily because this was an addition to an existing extensive 
investigation in terms of the Public Protector Act. Furthermore, the 
abovementioned delays exacerbated the situation; 

(3) Some of the parties that appeared to have been implicated by the 
investigation were assisted by attorneys and advocates in their 
responses and a total of seven attorneys and five advocates were 
involved, some of whom tried to turn the investigation into adversarial 
proceedings. Threats of interdicts were frequently made. 

The following jurisdictional and process issues were raised by respondent 
organs of state and implicated persons: 

The authority of the Public Protector to conduct the investigation at the same 
time while the Executive had decided on the agencies it wanted to conduct 
the investigation; 

The authority to investigate the conduct of a private consultant contracted by 
the state; 

The access to, scrutiny and review of the evidence and information obtained 
during the investigation; and 



15 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




(d) 

(viii) 
(a) 

(b) 

(c) 
(d) 



The process followed during the investigation. In some cases there was a 
lack of proper understanding of the provisions of the Public Protector Act. 

Security concerns and litigation by the security cluster 

The security nature of the project in question required an extensive 
consideration of the legislation and other prescripts that regulate the security 
classified information. In terms of the provisions of the Minimum Information 
Security Standards Policy (MISS), this means that the information is 
regarded as being of such a nature that its unauthorized disclosure/exposure 
can be used by malicious/opposing/hostile elements to neutralize the 
objectives and functions of institutions and/or the state 

In essence I had to strike a balance between security on the one hand and 
accountability and openness on the other. I took into account the provisions 
of section 1(d) of the Constitution, entrenching accountability, 
responsiveness and openness among other founding values of our 
democracy. 

My office took drastic measures to ensure that information that is sensitive 
and classified was secured throughout the investigation. 

I was further guided by what government had already made available in the 
public domain. In June 2013 the Minister of Public Works in response to an 
application in terms of the Promotion of Access to Information Act, 2000 
provided the M & G Centre for Investigative Journalism with 1 2 000 pages of 
documents from the DPW records relating to the Nkandla Project. All these 
documents, including several that are classified, were published on the 
Internet and are available at www.amabhungane.co.za. 



16 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



JCjLIC F>EO>TE<:.TOk 



(e) In relation to the ethical considerations, I was faced with asking the President 

the same questions that I had to ask of the former Minister of Cooperative 
Governance and Traditional Affairs, the late Mr S Sicheka, and the Minister 
of Police, Mr N Mthethwa, when I investigated allegations of unethical 
conduct against them, i.e. did he raise any concerns about obvious 
extravagant and expensive measures that were being implemented by the 
state at his private residence? In Mr Mthethwa's case he questioned obvious 
excessive expenditure and took steps to remedy the impropriety. 

(ix) My approach to the investigation was to consider and evaluate what 

happened, what should have happened and whether there was a 
discrepancy between the two that constituted improper conduct and 
maladministration, to rectify or remedy the impact. 



(x) I now turn to the general conclusions I have reached on the 12 issues before 

I proceed to my specific findings on each of them: 

(a) Regarding the issue of legal authority to install security features at a 

private residence at state expense and the allegation that such 
authority may have been exceeded, the investigation revealed that: 

(1) Security upgrades at private residences are allowed as privileges 
accorded to members of the executive and other parties whose security 
is essential to the functioning of the state, at the owner's request. In the 
case of the President and Deputy President, the Presidency is also 
authorized to make the request. 

(2) The Ministerial Handbook regulates security installations for members 
of the executive except for the President, Deputy President, former 



17 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

Presidents and former Deputy Presidents. The Cabinet Policy of 2003 is 
the key policy instrument that has regulated security installations at the 
private residences of Presidents, Deputy Presidents, former Presidents 
and former Deputy Presidents during the period under scrutiny. 



(3) Installations implemented in connection with health care services to the 
President and transport, are regulated by prescripts guiding the DOD 
Doctrines relating to transporting and providing medical services to the 
President, Deputy President, former Presidents and former Deputy 
Presidents. 



(4) It was these two sets of regulatory frameworks that authorized the 
installations undertaken in the name of security at the private residence 
of President Zuma on assumption of office in May 2009. 

(5) According to a Declaration Certificate issued by the Minister of Police, 
the Nkandla private residence of President Zuma was a declared 
National Key Point on 08 April 2010. Despite the Minister of Police and 
the Presidency's denial in their submissions during the final phases of 
the investigation, this added the National Key Points Act, 1980 into the 
legal framework permitting and regulating security measures at his 
residences. The specific compliance requirements with regard to the 
National Key Points Act are stipulated in the Declaration Certificate 
issued by Minister Mthethwa on 08 April 2010, declaring the Nkandla 
residence a National Key Point and the receipt of which was confirmed 
by the Presidency, a year later, on 07 April 201 1 . 

(6) As indicated earlier, security measures at private residences under any 
of the regulatory instruments are not automatic. In the case in point, we 
have established that the measures implemented from May 2009 to 



18 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




April 2010 could have only been authorized by the Cabinet Policy as the 
DOD prescripts do not cover any permanent security installations. 
Paragraph 8.1 .2(b)(i) of the Cabinet Policy directs that such installations 
be implemented "at the request of the President or the Presidency" (if 
the residence belongs to the President) following a security evaluation 
by the SAPS together with the National Intelligence Agency (NIA, now 
SSA) advising that the security of the President is compromised as a 
direct result of his or her public position. 

(7) A Security Evaluation Report duly compiled by the Security Advisory 
Service of the SAPS in May 2009 did conclude that the security 
measures at the President's private residence were inadequate at the 
time when he assumed office as President. The evidence of officials 
from the DPW, SAPS and the DOD and our inspection in loco in August 
2013 confirmed the need. This was despite the fact that Mr Zuma had 
been the Deputy President between 1 999 and 2005. The situation was 
said to be compounded by the fact that Nkandla is a deep rural area 
with a rather unfriendly terrain. 

(8) Looking broadly into the issue of compliance with the law and other 
prescripts, no evidence has been presented or found indicating that the 
trigger mechanism for the state to get involved financially, in respect of 
any law, was complied with. We have already established that the 
process started in 2009 and the President's private residence was only 
declared a National Key Point in April 2010. Accordingly, the only basis 
on which any state funds could have been used for security installations 
at the President's private residence is the Cabinet Memorandum of 
2003. 



19 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

(9) However, no evidence has been submitted or found indicating that the 
Presidency requested the SAPS and State Security Services to 
consider securing the private residence of the President, yet this is the 
trigger mechanism stipulated in paragraph 8.1.2(b)(i) of the Cabinet 
Policy of 2003. 

(10) However, I was persuaded by the submissions by various 
representatives of the organs of state involved in the security value 
chain that the normative process is not to wait for a request from the 
Presidency. I was advised that that action is taken to provide immediate 
basic security while commencing a process of conducting a 
comprehensive security evaluation as soon as a President is elected. 



(11) The documentary evidence, which shows that the measures identified 
as needing to be taken in response to the security evaluation at that 
point were consistent with security measures identified in the standard 
setting documents, among which are the Cabinet Policy of 2003 and the 
Minimum Physical Security Standards. The procurement of such 
measures were also costed as required, although not by the SAPS but 
by the DPW and amounted to R27 million at the time. 



(12) The evaluation above, herein after referred to as the first security 
evaluation, had apparently not taken into account the fact that President 
Zuma was in the process of constructing three new dwellings, which 
required the broadening of the scope of the security measures. A 
second and last security evaluation by the security experts within the 
SAPS was also conducted and this still did not include the construction, 
in the name of security, of buildings and other architectural items not 
listed in the standard setting instruments for the provision of security in 
identified private residences. 



20 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




(13) It would appear that the course of events changed significantly around 
August 2009, when Mr Makhanya, the President's private architect who 
had been involved in the President's non-security construction works, 
was brought in, without going on tender, to act as the DPW's Principal 
Agent in respect of the entire Nkandla Project, while retaining his 
position as the President's Principal Agent and architect. This is the 
period when the scale of work increased exponentially, leading to 
installations that were not recommended in any of the authorizing 
instruments or Security Evaluation Reports and the cost of works 
escalating to over R215 million. It is also the point at which the Director: 
Architectural Services at the DPW expressed concerns about moving 
from "humble beginnings" to establishing a full township. 

(14) By installing measures that were not based on the outcome of any of 
the two security evaluations carried out using the Minimum Physical 
Security Standards as requires and not quantifying and approving the 
scope of measures before approaching service providers, the process 
that ensued from August 2009 did not fully comply with the Cabinet 
Policy of 2003, from which the authority to install security measures was 
derived. 

(15) The Cabinet Policy of 2003 requires: 

(a) Request by the President or Presidency for security measures; 

(b) Security evaluation by the SAPS and State Security Agency; 

(c) A proposal to the Inter-Departmental Security Co-ordinating 
Committee for technical evaluation; 

(d) A cost estimate prepares by DPW; 



21 



Secure In Comfort A Report of the March 2014 

Public Protector 



SO-UTI1 111 l.'K.II 



(e) The SAPS to advise the Minister of Police on the proposed 
security measures including the cost; 

(f) Communication to the President on the approved security 
measures for his or consent ; and 

(g) Implementation by the DPW 

(16) If the Cabinet Policy of 2003 was not complied with, how about the 
National Key Points Act? The Presidency and SAPS have since argued 
that there was no need to comply with the National Key Points Act. This 
is despite the fact that in submissions to Parliament and media 
statements, the National Key Points Act was used, primarily by the 
current Minister of Public Works, to justify the installations and related 
expenditure at President Zuma's private residence. 



(17) According to the Declaration Certificate issued by the Minister of Police, 
Mr Nathi Mthethwa, on 08 April 2010, the security installations at the 
President's residence were supposed to be handled in terms of the 
National Key Points Act. Since work was already in progress, the 
directive in the declaration was to presumably apply from that date 
onwards. Unfortunately the organs of state involved have failed to 
address me on what was intended arguing, in a very strange way that 
that the act of bringing in the National Key Points Act was to secure 
what had already been built in the name of security. 



(18) Nonetheless, if I am right in arriving at the logical conclusion that the 
instruction in the declaration was meant to regulate installations and 
responsibility for payment thereof from April 2010, then everything that 
was done from that point onwards was in terms of the Declaration 
signed by the Minister of Police, not meant to be funded by the state but 
paid for by the owner, President Zuma. This conclusion is arrived at on 



22 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

the basis of the contents of the Declaration Certificate in question, 
which includes the following: 

"The total safeguarding of a National Key Point comprises not only the 
measures which you as owner are obliged to implement in terms of 
section 3(1) of the National Key Points Act , but also the effective 
protection which must be implemented by the protection unit. It is 
therefore of the utmost importance that either you or a person appointed 
by you, liaise with the protecting unit of this National Key Point and the 
Provincial NKP Officer to activate a Joint Planning Committee(JPC) for 
this National Key Point in order to draw up a joint plan to counter an 
incident . 

In terms of Section 24D of the Income Tax Act, you can submit a claim 
for tax deduction in respect of expenditure incurred on security 
measures implemented at your National Key Point. . . 

It is trusted that you will implement your security obligations as defined 
in section 3(1) of the National Key Point Acts, Act 102 of 1980, at your 
National Key Point." (emphases added) 

(19) The Minister of Police's declaration proceeds to advise the owner, who 
in this case is President Zuma, that: "This directive contains all the 
information you will need in reference to the administration and 
safeguarding of your NKP. Please study it carefully." It concludes with 
advice that "If the circumstances of your NKP should change to such a 
degree that its status as a NKP is affected, you must inform the NKP 
Section so that a re-evaluation can be carried out. " 

(20) No evidence documentary or otherwise indicates that the Minister of 
Police's decision to have the owner fund the security measures was 



23 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



revoked or the NKP's situation was reported as significantly changed or 
re-evaluated. 



(21) The respondent parties' response to the question regarding how and 
why the post April 2010 security measures were funded by the state, 
was simply that, the declaration was never meant to affect the regime 
that ordinarily applies to the security of Presidents and the other 
selected dignitaries. I had to consider the possibility that the National 
Key Points Declaration could have been meant to cover some of the 
items that were neither mentioned in any of the standard setting 
instruments nor included in the lists made by the security experts 
following the two security assessments. 



(22) The possibility that sections 3(2) or 3A of the National Key Points Act, 
which gives the Minister of Police the power to pay with state funds in 
the event an owner is unwilling or unable to pay, was eventually used 
as the basis for tapping into state funds and, was also explored despite 
protests from all affected organs of state. Despite not denying that he 
signed the National Key Point Declaration dated 8 April 2010, asking 
the President to pay for his own security upgrades, Minister Mthethwa 
said, in his response to the provisional findings: 

"Any contention that the President was required to implement security 
measures at his private residence at his own expense for his own safety 
and security is misguided and incorrect" 

(23) Incidentally, the same difficult-to-fathom view was taken in the 
Presidency's response to the provisional report. When I asked the 
President's legal advisers, what the declaration was asking the 
President to pay for and if he paid for same, I was advised that he had 



24 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

not paid for anything and should never have been asked to pay for 
anything. Perhaps that is true but the reality is that he was asked to pay. 

(24) From the investigation's point of view, the apportionment of costs path 
was explored primarily because there was evidence of a draft 
apportionment letter prepared at the request of Ms. Hendrietta 
Bogopane-Zulu, the Deputy Minister of Public Works at the time. 
Unfortunately although the Deputy Minister confirms requesting the 
letter and the evidence shows that it was duly prepared she could not 
confirm that it was sent to the President. Neither could Ms. Gwen 
Mahlangu-Nkabinde who was the DPW Minister at the material time. 

(25) There is clearly no evidence of a decision made by the Minister of 
Police as required by law to act in terms of the apportionment regime. It 
must also be indicated, as pointed out by the Presidency that, 
apportionment is an option. Otherwise, the state may under the National 
Key Points Act still pay for everything. This takes me back to the view 
that the owner's contribution may have to address the matters that were 
added to the security menu after the security evaluations were done 
and a final list prepared on what was absolutely needed for security 
purposes and the DOD related needs. The minutes of the meeting held 
on 1 1 May 201 1 where it was said a decision on the swimming pool is 
outstanding pending consultation with the owner as it has cost 
implications for him provide one of the pieces of evidence that gives us 
a glimpse of the thinking behind apportioning some of the costs to the 
owner. In the minutes of various progress meetings of the Project Team 
there is consistent reference to non-security items for the owner's 
account, as the elephant in the room. 



25 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

(26) Another piece of the puzzle that points us in the direction of the owner 
footing an undetermined part of the bill is minutes of meetings held by 
the Project Team. The minutes of the Project Team meeting dated 1 
April 201 1 , where the question of apportioning of costs was discussed, 
reveal an agreement reached for a document outlining such 
apportionment to be prepared for submission to President Zuma. The 
evidence of the former Deputy Minister of Public Works, Ms. Bogopane- 
Zulu, alluded to earlier, buttresses the existence of such an agreement. 
In the body of the report I deal extensively with her lamentation that she 
was unceremoniously removed from the project, an allegation not 
denied by the Minister at the time, Ms. Mahlangu-Nkabinde, whilst still 
wearing travelling clothes upon landing, from an overseas trip, Ms. 
Bogopane-Zulu indicated that she never saw or heard about the 
apportionment document she had requested upon departure following 
her discussion on the same with President Zuma. 

(27) Although the minutes of a progress meeting confirm its existence and 
the investigation did unearth a copy of a document that purports to be 
the apportionment document and with items for the President's bill 
allegedly ticked by Mr Makhanya, the fate of the original remains a 
mystery as Ms. Mahlangu-Nkabinde submitted that she had never seen 
it despite admitting to taking over the prestige portfolio, which included 
the Nkandla Project, after her abrupt removal of her deputy from same. 

(28) However, I must say that the disappearance of the document amid a 
situation where virtually all the members of the executive involved 
appeared conversant with its contents is a source of grave concern. It 
is clear that at the level of the Project Team the document was 
produced and delivered but at a political level, it seems to have been 



26 



Secure In Comfort A Report of the March 2014 

Public Protector 



111 l.'K.II 



managed in a manner that removed it from the normal administrative 
decision-making process or track. 

(29) What is clear though is that there is no document through which the 
Minister of Police revoked his decision. Furthermore his submission and 
that of the Presidency did not argue that such revocation occurred. 

(30) The procedural question that arose during a consideration of the 
apportionment of costs issue was whether or not the owner was 
consulted as required by the law. What we know, according to the 
Declaration is that President Zuma was informed that he was to pay for 
everything. Curiously though, the President appears to have been 
informed of such National Key Point Declaration, a year after it was 
made, on 07 April 201 1 . At what point was he told he would have to pay 
for some of the items, and for which of those, is not clear. 



(31) The only evidence uncovered that suggests the owner was informed or 
attempts were made to inform him of his partial payment obligations is 
the document purporting to be an apportionment of costs document and 
the testimonies of Deputy Minister Bogopane-Zulu and the former 
Regional Manager of the Durban DPW Regional Office, Mr Khanyile. 
However, that document was only prepared around the beginning of 
2011 and there is inconclusive evidence regarding its delivery to 
President Zuma. 



(32) The body of the report also deals with purported security installations on 
state land near the President's homestead, implemented by the DOD at 
the expense of the DPW. I must indicate upfront that these have 
emerged as extraneous to the regime for providing security to the 
President and selected dignitaries. They belong to a DOD-regime 



27 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



regulating medical services and transport services to the President and 
specified dignitaries. 



(33) This is the murkiest of all areas. The first thing to note is that no policy 
instrument that clearly stipulates in exact items which can be funded at 
state expense in the name of providing mobile security to the President 
was provided by government during the investigation. Precedent also 
does not help as all predecessors mainly got security assistance at 
private residences that is mostly limited to the items listed in the security 
guides. The only difference is former President Mandela whom around 
2010, long after retirement and about 3 years before his passing on, got 
a mobile ICU unit, which will now revert to the state. 



(34) At the Nkandla residence, the items attributable to the SAPS include 
the relocation of households of neighbours at state expense, apparently 
because Mr Makhanya's advice was that a straight fence would provide 
better security than one that goes around these homes. Here it must be 
borne in mind that the security evaluations did not recommend this. 
Furthermore Mr Makhanya is an ordinary architect and not a security 
expert or advisor. His ticket to the project was on account of non- 
security related architectural work he was performing for his client, the 
President, shortly before the Nkandla Project commenced. It must also 
be noted that the meandering fence and proximity of these households 
was never identified as a security threat in the two security evaluations 
conducted by security experts in accordance with the rules and which 
are the only security assessments ever conducted in respect of the 
Nkandla Project. 

(35) It is particularly worth noting that if the National Key Points Act were to 
be viewed as the key authority instrument authorizing the impugned 



28 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




security measures, these households could have simply been included 
inside the secured area as part of a National Key Point Precinct, as 
envisaged in section 2A of the Act. This would have meant a straight 
fence with these homesteads inside the enclosure. There is no 
evidence that this option was ever considered. 

(36) It is further worth noting that the organs of state involved did not invoke 
any law, including the Expropriation Act, 1975, as the basis for moving 
the households at state expense. The argument that this was a security 
requirement is not borne by the documents prepared by security experts 
following the two security evaluations. The fact that the families did not 
want to move on account of, among others, their family gravesite, does 
not negate the fact that they benefited from better buildings at state 
expense. 

(37) I have noted with concern the submission by Deputy Minister 
Bogopane-Zulu during her interview that she had advised that the 
Minister of Human Settlements be approached with a request to build 
RDP houses for the affected households. This would have cost between 
R100 000 and R120 000 per house, which would have been less than 
R2 million for the four households instead of the R8 million that has 
since been paid for the 15 rondavels that have been built for them. This 
cheaper option was not explored by the DPW. Regarding maintaining 
the rondavel style of the original homes, RDP houses can be adapted to 
any low cost architectural design. 



29 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



(b) Regarding the alleged flaunting of Supply Chain Management 

procedures stipulated in the relevant regulatory framework, the 
investigation revealed that: 

(1 ) It is common cause that despite the expenditure of an amount in excess 
of R215 million that was spent by the DPW on the Nkandla Project, the 
prescribed open tender process was not utilized for the procurement of 
the goods and services required at any stage of the project. Treasury 
requirements require that all goods and services between R10 000 and 
R500 000 be subjected to three quotations and above R500 000, to an 
open tender process. Most of the deviations from the prescribed open 
tender process were justified in internal memoranda and minutes of 
meetings citing: 

1. The fact that a particular service provider was appointed by the 
President and that there was a need to integrate the project with the 
President's private works; 

2. Security; 

3. Instructions from the Minister of Public Works; 

4. Urgency; and 

5. Indications that the service/product required was only available from 
one supplier. 

(2) Only nominated and negotiated procurement strategies were utilized, 
and in some cases there were direct contractual appointments of 
service providers. 



30 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



(3) According to the DPW records, the procurement without tender 
processes also covered works referred to as "general site works", 
amounting to more than R67 million and which included the installation 
of lighting, data and CCTV networks, access control facilities, bulk earth 
works and landscaping. Mobile accommodation for the SAPS staff and 
mobile generators were also procured without a tender process. 

(4) I have had great difficulty understanding why Mr Makhanya and the 
other consultants and contractors brought in on account of prior 
involvement in President Zuma's private renovations, were considered 
key to the work relating to the helipads, the clinic, homes for SAPS 
members, the relocation of households and most of the general site 
works. Most of these measures were unrelated to the private 
renovations by the President and were executed outside his private 
property. 

(5) According to his written statement presented to me dated 30 
September 2013, the President was present when Mr Makhanya, was 
introduced to the DPW team at his house in Nkandla in August 2009. 
The President has since submitted that he never insisted that 
Makhanya and others he had already engaged privately had to be 
engaged for the Nkandla Project. He explained that he simply 
participated in a meeting the purpose of which was: 

"Only to introduce my architect to senior government officials and to 
appraise each other of their respective plans" 

(6) It is common cause that Mr Makhanya not only served as principal 
agent for both the President's private work and the state funded the 



31 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

Nkandla Project. It is also common cause that he served as overall 
architect, providing subcontractors to the Nkandla Project while serving 
the President as his private architect. Also not denied is the fact that Mr 
Makhanya throughout the Nkandla Project served as the go-between 
between the government officials and the President, leaving it to him to 
discuss designs with and explain the President's preferences. What is 
particularly disturbing in this regard, is that the minutes show that Mr 
Makhanya was often asked to design something more economic and he 
would come back with something more expensive or even luxurious and 
then make a submission regarding why the 'security' need had to be 
met through the more costly design. An example in this regard is his 
decision to change the design and move the location of the safe haven 
at a significant increase to the cost. No explanation was given regarding 
why the government had to consult the President through Mr 
Makhanya, a consultant. 

(7) Despite denials by the Presidency, the appointment to design and 
implement security features at the President's residence placed the 
service providers who were also appointed by the President in a 
position of dual responsibility to the President and to the DPW. Although 
denied by the Presidency, I am unable not to conclude that this 
presented a risk of conflict of interest. This was particularly the case 
with regard to Mr Makhanya, whose new role as Principal Agent for the 
entire Nkandla Project meant that he became the state's main advisor 
on what it would take to cost effectively meet identified security 
requirements while maintaining his status as the President's architect 
and advisor. In fact the DPW never explained why Mr Makhanya had to 
be the Principal Agent for the entire project other than to indicate that he 
was already involved in the President's private works. 



32 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




(8) Mr Makhanya's third role as the main go-between between the 
President as owner and the Project Team also placed him in a position 
of serving the interests of two masters. The Presidency has argued that 
there is no evidence that the interests of the two masters were 
conflicting. That may be so. What we do know though is that many of 
the modest measures originally recommended by the security 
evaluation or agreed to at project meetings, ended up being replaced 
through the designs of Mr Makhanya and team under him, by more 
expensive measures. 

(9) The placing of Mr Makhanya between the Project Team and President 
Zuma evidently shifted power from state officials to Mr Makhanya. In his 
written submission, one of the "officiaf project managers stated that Mr 
Makhanya became the de facto project manager and that it was difficult 
to exercise control over him leading to a case of "the tail wagging the 
dog". It is not difficult to comprehend why government officials, 
particularly at a fairly low level of the food chain, would have difficulty 
controlling a consultant who was presented by and claims to speak with 
the President's concurrence or authority. My opinion is that even a 
Minister could have had difficulty countermanding Mr Makhanya. 

(10) Both minutes of the project and interviews reveal a picture of knee jerk 
reactions during which team members would come up with an idea at 
any time, thereafter Mr Makhanya was asked to design a feature that 
could capture that idea and between him and his quantity surveyor have 
it costed, the subsequent meeting would then simply adopt it. During the 
inspection in loco, the team deferred to Mr Makhanya, who battled to 
explain items such as the amphitheatre, the kraal, which includes a 
chicken run and cattle culvert, the Visitors' Centre, the swimming pool, 



33 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



extensive paving and the relocation, at state expense, of the President's 
neighbours. 



(11) Having a contract that paid him on the percentage of the cost of the 
measures installed also presented a risk of conflict of interest for Mr 
Makhanya as choosing the most expensive option meant more money 
as did expanding the scope of the work involved. Mr Makhanya had 
made R16,5 million from the Nkandla Project by the time of conclusion 
of the investigation. 

(12) Coming back to the issue of procurement, I have indicated that the 
minutes of meetings and interviews with the parties, clearly show that 
many of the procurement procedures were skipped, ostensibly on 
account of urgency. I am not convinced that urgency prevented the 
procurement of services on the basis of shortened tender turnaround 
times as provided for in Treasury Regulation 16A6.4. 



(13) Mr Khanyile, the former Regional Manager of the Durban Regional 
Office of the DPW, conceded during in his evidence, that from the time 
the project commenced, the procurement procedures followed were 
different from the norm usually applied by the SAPS, the DOD and the 
DPW. He conceded that these organs of state failed to comply with the 
prescribed standards of proper demand management and budgeting. 
The Minister of Public Works has, in his official statements, also 
conceded this point. The Task Team of officials from DPW, SAPS and 
the Security Ministry also confirmed the same, in its findings. 

(14) The evidence of the officials involved in the Nkandla Project indicated 
that they erroneously accepted that due to the fact that the project 
related to the security of the President, which was urgently needed, and 



34 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



because it was driven from the DPW Head Office and the Ministry of 
Public Works, the deviation from the norms was justified and not to be 
questioned. 



(15) The evidence of the officials was corroborated by the Acting Director- 
General of the DPW, Mr Malebye, who took responsibility for the short 
cuts. Furthermore, his involvement at trench level, when the project 
commenced, and later that of a Deputy Director-General, the Deputy 
Minister and the Minister, the officials at the Durban Regional Office that 
were mainly responsible for the implementation of the project, did create 
confusion regarding roles and accountabilities for procurement 
decisions. 



(16) In approving a request from Mr Khanyile submitted in an internal 
memorandum dated 9 October 2009, Mr Malebye even went so far as 
to allow a deviation from the internal DPW directive that all 
procurements above R20 million had to be approved by the DPW 
Special National Bid Adjudication Committee (SNBAC), and delegated 
unlimited and unconditional authority in respect of the Nkandla Project 
to the Regional Bid Adjudication Committee (RBAC) based at the 
Durban Regional Office. 

(17) In his capacity as the accounting officer, he also approved the 
appointment of consultants and contractors for millions of Rand by 
means of nominated and negotiated procurement strategies. This does 
not cater for proper competition and selection, on the basis that the 
Nkandla Project had to be fast tracked. 



35 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



(18) Despite all the deviations justified on urgency, the project started off 
quite slowly and, according to the evidence of the Project Manager, by 
January 201 0, not much had been done. 



(19) According to the SAPS, the President started complaining by March 
2010, about the slow progress. The President did the same from May 
2010. By then, little had been achieved despite the fact that the project 
was already a year old and procurement requirements had been 
flaunted ostensibly on the basis of urgency. 

(20) The evidence further shows that financial planning for the Nkandla 
Project was also not attended to by the SAPS, DOD and DPW. 
Furthermore, by June 2010, no funding had been allocated to the 
Nkandla Project for the applicable financial year, resulting in the 
reallocation of the DPW Capital Works budget. 



(21) The scale of the project increased exponentially in terms of number of 
items, size of measures and the size of President Zuma's homestead. 
In the construction industry a runaway project scale is referred to as 
"scope creep". Scope creep is primarily attributed to lack of or poor 
demand management and failure to manage service providers, who are 
known to find ways to expand their brief leading to greater cost and 
extended periods of engagement. Some of the dimensions of the scope 
creep were consequential to the constant add-ons to the original list of 
security measures. For example, one of the consequences of the 
measures constructed beyond the list compiled on the basis of the two 
security evaluations was that the soil was disturbed significantly leading 
to a decision by the Project Team in August to employ the services of a 
Landscape Architect to advise on the rehabilitation of the land. This was 
not part of the original idea. No wonder the Director: Architectural 



36 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

Services at DPW advised the Acting Director General, at that point, 
that: 

"Given the very humble beginnings of this project, nothing short 
of a full township establishment is now required..." (emphasis 
added) 



(22) Failure to ensure demand management as an essential part of Supply 
Chain Management is one of the factors behind the runaway costs of 
the Nkandla Project. Due to the fact that no proper initial planning of 
and budgeting for the project were done by the departments involved, 
the scale and cost of the project were clearly without boundaries. As 
more requirements were raised by the departments and other role 
players involved, more designs by the professional consultants were 
added, cost estimates prepared accordingly and funds within the DPW 
budget reallocated without independent evaluation from persons outside 
the project. The minutes show that Deputy Minister Bogopane-Zulu, 
tried to contain both scope creep and price escalation, during her short 
stint although she too was, by her own admission, responsible for small 
dimensions of the scope creep and cost escalation. She admitted to 
having supported the idea of turning the fire pool into a swimming pool 
on being assured the cost difference would be nominal and to ordering 
permanent brick and mortar quarters for SAPS personnel near the 
premises instead of the accommodation they then occupied. 

(23) Ms G Pasley, Chief Quantity Surveyor of the DPW, raised her 
concerns about the escalation of the costs of the Nkandla Project in an 
email message sent to Mr Rindel, on 3 December 2010. She stated, 
inter alia, that: 



37 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

"The scope of work and estimated costs have increased considerably over 
the past four months and continue to change which has given rise to further 
cost increases as can be seen from the budget reports already submitted 
by the consultant team and which are currently in the process of being 
revised again. The estimated costs have almost doubled over this period 
and it is essential that the parameters in respect of the scope of work and 
the budget are established and confirmed. Information pertaining to the 
exact apportionment of work and costs is critical in order that a detailed 
cost analysis can be done by the consultant Quantity Surveyors within the 
confines of the budget." (emphasis added) 



(24) The records of the DPW and the evidence of the officials that were 
involved in the implementation of the Nkandla Project show that the 
SAPS Security Advisory Service did not play a significant role in the 
design of the project. It submitted certain proposals, but the ultimate 
design details were left in the hands of especially Mr M Makhanya, the 
architect and Principal Agent, irrespective of the costs involved. 

(25) The evidence suggests that the focus of the Project Team from the start 
of the project was on creating an ideal situation, rather than a 
reasonably safe and affordable one. An example of no attention to cost 
effectiveness is the cattle kraal with a culvert and chicken run. When 
asked, during the inspection in loco, why a cattle culvert and chicken 
run, Mr Makhanya said "this is how they do it in England'. Moving the 
kraal, if it had to be moved, to the outer perimeter as is the case in the 
owner built kraal at the late President Mandela's homestead in rural 
Qunu, appears not to have been considered. Similar questions arise 
with the safe haven, which based on initial cost estimates, was originally 
conceived as a simple safety measure that would have cost under R1 
million. 



38 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC F>EO>TE<:.TOk 
SOUTH flfPKU 



(26) Brigadier Adendorff, the Head of the Security Advisory Service of the 
SAPS and SAPS' principal representative in the Nkandla Project, 
confirmed during her evidence that in her view, the SAPS did not pay 
attention to cost, understanding itself as having no role in such costing. 
She submitted that she understood this to be the responsibility of the 
DPW. She also confirmed that she had not operated according to the 
Cabinet Memorandum or the National Key Points Act. Had she been 
aware of the law, she would have known that both the costing and 
financing are the responsibility of the SAPS, except for the DOD related 
measures. 

(27) Lt General Ramlakan, who was the head of the South African Medical 
Services in the Department of Defence, also made a similar submission. 
With the support of two counsels, he contended strongly that he 
understood his role as having been confined to making a wish list and 
for DPW to adjudicate on that list, procure and provide what it chooses 
to provide and pay for such from its own budget. Despite presenting 
himself as the expert even questioning my own competency to question 
what he requested, he maintained that it was not his place to ensure 
that the needs identified in relation to military health services in support 
of the President, his family and military staff deployed in Nkandla, were 
addressed through the most cost effective measures. 

(28) It is difficult not to reach the conclusion that a license to loot situation 
was created by government due to a lack of demand management by 
the organs of state involved as provided for in the Cabinet 
Memorandum, the National Key Points Act, relevant health care and 
transport regulations as well as National Treasury Guides and directives 
on procurement. Treasury prescripts clearly require government not to 



39 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

go to the market with a blank cheque licensing service providers to 
simply fill the blanks relating to scope of work and amount to be paid. In 
the words of the Project Manager, Mr Rindel: "It was like building a 
puzzle without a picture" and the Project Team "wrote the rules as they 
went along". 



(c) Regarding the allegation that the measures taken at state expense at 

the President's residence transcended what was required for his 
security: 

(1 ) The evidence gathered focused on the standard setting instruments and 
their provisions regarding the minimum security requirements. The lists 
of security measures compiled at the conclusion of security evaluations 
were also taken as standard setting. The President's lawyers conceded 
during the meeting on 21 February 2014 that the deciding factor or what 
had to be implemented in the name of security were the lists prepared 
by security experts following the security evaluations. 

(2) However, even where measures were neither mentioned in the 
standard setting instruments nor in the lists compiled by the security 
experts, I still gave consideration to the judicious exercise of discretion 
by relevant state actors to address incidental needs. 

(3) With regard to security measures inside the residence and relating to 
fencing, the security verification was made easier by the existence of 
the Cabinet Policy of 2003, the Minimum Physical Security Standards 
and the SAPS Security Evaluation Reports compiled in conformity with 
the Minimum Physical Security Standards. 



40 



Secure In Comfort A Report of the March 2014 

Public Protector 

POJfcJJS F>EO>TECTOf? 
SOUTH flfPICfl 

(4) Based on the items listed in the Minimum Physical Security Standards 
and the lists compiled in pursuit of the security, evaluations left with no 
basis for accepting as security measures items such as the kraal, 
chicken run, Visitors' Centre, amphitheatre, swimming pool and 
extensive paving as these were not among the listed items. 

(5) While conceding the point made by the President in his written 
submission of 14 February 2014, his lawyers during our meeting, DPW 
and the security cluster, that I am not a security expert and accordingly 
cannot second guess security experts, the evidence shows that these 
items did not come from security experts. As indicated, they were 
neither on the list in the Minimum Physical Security Standards 
Instrument nor the list developed by the security experts in pursuit of the 
security evaluations. Furthermore, the minutes of the Project Team 
meetings show that their inclusion was principally in the advice of 
civilians in the Project Team. 

(6) My understanding is that my role is not that of a security expert but that 
of public scrutiny to ensure that those entrusted with public power do 
not exceed the bounds of their authority. In other words I'm exercising 
administrative scrutiny in the exercise of state power much the same 
way as judicial scrutiny. Do I need an expert to help me understand the 
decisions made and justifications given by actors such as Mr Makhanya 
and General Ramlakan (who presented themselves as experts in their 
respective fields) for recommending measures beyond what were in the 
Minimum Physical Security Standards Instrument and the lists from the 
security evaluations? Not in the case of the items in question, as there 
are precedents from previous Presidents. 



41 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

(7) Having accepted that for incidental measures, discretion, although not 
expressly authorized, had to be exercised, I had to determine how I was 
to adjudicate the judiciousness of the exercise of such discretion. In this 
regard, I found myself relying on the quality measures at residences of 
President Zuma's predecessors and the submissions made by the 
Project Team, which for whatever reasons, primarily deferred to Mr 
Makhanya for internal perimeter installations and Lt Gen Ramlakan for 
the works outside the land leased by the Zuma family. 



(8) Let us take the cattle kraal. President Mandela's is an ordinary kraal 
built by himself far from the main yard thus not interfering with motion 
detectors in the inner perimeter. No swimming pool was built for him. I 
am also not aware of any Visitors' Centre. In any event, the minutes of 
the Project Team meeting dated 1 1 May 201 1 show that the thinking at 
the time was that the swimming pool would have cost implications for 
the owner hence Mr Makhanya was assigned the task of consulting 
President Zuma in this regard. 



(9) Having listened to the submissions and measured these against 
measures in the private homes of previous Presidents and in the 
absence of any security evaluation report listing such measures, I had 
serious difficulty understanding the basis for classifying the following 
items as security measures: 



1. Inside the private residence: The Visitors' Centre, Cattle Kraal, 
Chicken Run, Amphitheatre, Marquee Area and the Swimming Pool. All 
I did here was to ascertain from the relevant state actors what the 
proximity of such non listed measures to the list in the Minimum 
Security Measures Instrument and the lists prepared in pursuit of the 
security evaluations were. I also engaged them on whether or not 



42 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

cheaper but equally effective measures had been considered. The 
arguments made were simply not convincing as the discretional security 
concerns sought to be addressed could have been addressed through 
much cheaper options. Furthermore, the minutes of progress meetings 
show that there was some debate on the inclusion of these. Some 
minutes specifically state that some of these fall outside the mandate of 
the DPW. The report captures an example of discussions at project 
progress meetings indicating that these items were not regarded as 
security items, stating that: "Mr Makhanya was also requested to 
discuss the issue of the fire-pool with the President " (emphasis added,). 
It was recorded in the minutes of the meeting that: "Mr Makhanya said 
that the pool has been placed on hold because of the pool bearing a 
private costing which the principal (the President) did not accommodate 
for. " (emphasis added) 

2. Regarding the Visitors' Centre: There is currently an empty building 
belonging to the Zuma family that was used by the SAPS at the 
beginning, which could have been used for the purpose. The media 
made an issue of a tuck shop, but as the original tuck shop building 
exists, and the new one is part of a building housing a legitimate and 
listed security measure, I found no basis for rejecting the arguments for 
the tuck shop as a discretional security measure. 

3. On the state leased land outside the private residence: The private 
health clinic, helipads and staff homes address a real need. However I 
found no reason why these were located near the private residence 
rather than at a central place that could benefit the entire impoverished 
Nkandla community. The government submission makes a point of 
highlighting the inhospitable terrain of Nkandla coupled with, at the time, 
a lack of infrastructure such as roads, and properly resourced health 



43 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

facilities and police stations. General Ramlakan's submission that there 
were no such central places is contradicted by evidence. For example, 
a helipad near a rural hospital or police station could offer enormous 
relief to this remote community. The building of the police staff quarters 
at a local police station would have left a legacy for the community. 
General Ramlakan alluded to the George airport as having been built 
within a stone's throw of the then President Botha's private residence in 
Wilderness. Firstly that airport is 23km from the said private residence, 
and secondly, it supports the point about catering for the needs of the 
caretakers in a manner that takes into account that public resources 
should be primarily deployed to meet public needs. Also of concern is 
the fact that the amounts involved in implementing these measures, 
particularly the SAPS ones, is obscenely excessive. I could not find any 
authority or legitimate reason for classifying the relocation of the 
households at state expense, as a security measure as envisaged in 
any of the authorizing security instruments. Apart from this not 
appearing in the Minimum Physical Security Standards, such relocation 
was not recommended in the Security Evaluation Reports. Furthermore, 
no evidence was provided indicating that such relocation at state 
expense was the only option for addressing the meandering fence. 

(10) The Ministers of Public Works' communication with Parliament, the 
nation and, possibly, the President was riddled with inaccuracies and 
inconsistencies, particularly regarding the regulatory framework 
employed to justify state expenditure on the upgrades at the President's 
private residence, the nature of the upgrades and the extent to which 
the President and his family benefited from relevant installations. This 
has grossly undermined trust in government. 



44 



Secure In Comfort A Report of the March 2014 

Public Protector 



111 l.'K.II 



(d) Regarding the allegation that the expenditure incurred by the state was 

excessive or amounted to opulence at a grand scale: 



(1) The cost analysis shows that the Nkandla Project started from humble 
beginnings, but soon escalated by more than two hundred per cent 
(200%) within a year. It is also clear that the uncontrollable escalation 
took place once the decision-making powers shifted towards Mr 
Makhanya as the Principal Agent. 



(2) Minutes of project progress meetings ascribe the uncontrolled 
escalation that occurred principally to the fact that there never was 
demand management or a point at which the process owners 
determined and capped the project scope and price. 

(3) Mr Rindel's evidence indicates that a decision was made by the 
Nkandla Project Team and the DPW to divide the project into three 
phases and the documents show that the entire project was not costed 
up front as required under both the Cabinet Policy and the National Key 
Points Act. The evidence also shows that the cost ballooned 
exponentially over time and so did the scale of the Nkandla Project. 



(4) I could find no indication from the evidence that the ever escalating cost 
and lack of planning of the project were ever attended to as serious 
issues during the implementation thereof. Ms Pasely's evidence 
confirms this. 



(5) As the designs of Phases 1 and 2 continued, based on the 
requirements of the SAPS and the DOD and the inputs of the Project 
Team and professional consultants, the estimated cost of the project 
increased, exponentially. 



45 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



(6) From the moment the professional quantity surveyors appointed for the 
Nkandla Project by the DPW, (the same consultants as appointed by 
the President) concluded from their initial assessment that the full scope 
of the security requirements of the SAPS and the DOD was not properly 
considered by the DPW and that the cost estimate of R27 million, as 
determined by the Department, was very conservative, there were new 
items and instant price escalation at virtually every project progress 
meeting. The industry term for this phenomenon is "scope creep". 



(7) As shown earlier, there, was massive scope creep. An example in this 
regard is the Safe Haven which was initially conceived with a specific 
location at the estimated cost of about half a million (R0.5 million). As 
soon as Mr Makhanya got involved and convinced Brigadier Adendorff 
the location was changed resulting in an initial estimate of R8 million 
and the subsequent guzzling of about R19 million at the time of 
concluding the investigation. 

(8) By the time of finalizing the investigation, the total actual expenditure 
had increased from the initially estimated R27 million to R215 million 
despite the fact that the project remains incomplete, with the current 
conservative estimation of the final cost being R246 million, excluding 
lifetime maintenance costs. 



(9) Worth noting is the fact that the money guzzlers are not items listed in 
the standard setting instruments for security. The measures inside the 
patch of land belonging to the Zuma family that seem to have escalated 
the costs include the relocated safe haven, security fencing covering a 
broader perimeter than President Zuma's original patch of land, the 
swimming pool, amphitheatre, sophisticated cattle kraal boasting a 



46 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

culvert and chicken run, and the Visitors' Centre. Measures located 
outside the Zuma patch of land and within land leased by the state for 
additional infrastructures and support staff as part of the President's 
security, health services inclusive of a clinic, helipads, paved streets, 
bachelor rondavels for staff and rondavels for the relocated neighbours. 

(10) All measures, whether in the inner perimeter fence (land leased by the 
Zuma family from the Ingonyama Trust) or in the outer perimeter (state 
occupied land) have been implemented principally for the purpose of 
providing security for the President. I was not convinced by General 
Ramlakan's argument that this is not the case. If it wasn't for the 
decision to extend privileges to cover the President when at his private 
residence, none of the costs incurred in respect of the infrastructure at 
his door step, would have been incurred by the state. The only 
difference between the inner and outer perimeter is the fact that 
measures in the inner perimeter become the President's property 
whereas those on state land remain public property when no longer 
needed for the President's security. 

(11) The contention by the representatives of organs of state involved that 
the bulk of the money went towards measures in the outer perimeter, 
accordingly, does not mitigate or change the fact that all expenditure 
was incurred in the name of security, providing health services and 
related privileges to the President in relation to his private residence. It 
must be borne in mind that no clinic would have been built at a private 
homestead if it was not passed as a security feature for the President. 
The same applies to the helipads, massive paving, houses for members 
of SAPS and others as well as the payment of relocation costs for the 
moved households. 



47 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




(12) With all the above in mind, coupled with the fact that no evidence was 
provided or found indicating that any effort was made to find more 
economic alternatives, how do we answer the questions raised by the 
first complainant regarding extreme opulence in the face of a state that 
is struggling to meet the basic needs of people, including those in the 
backyard of the homestead in question? 

(13) The investigation revealed that seven teams of professional consultants 
were involved in the Nkandla Project and were paid a total of R50 352 
842 for Phases 1 and 2 alone. It is worth noting that the relocation of 
two households cost R4.2 million whilst the relocation of 1.5 households 
cost R3.7 million. 

(14) The records of the DPW indicate that by the time that the investigation 
was concluded the total expenditure of the project for the DPW 
amounted to R 215 444 415. The estimated cost of Phase 3 of the 
project that has not been implemented is R 31 186 887, which would 
bring the total estimated cost of the project to R 246 631 303. 

(15) Some of the actual expenditure at the conclusion of the investigation on 
the Nkandla Project can be broken down as follows: 



48 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC F>EO>TE<:.TOk 











1 


Safe Haven, Corridor Link, Walkway Above & Exit Portion 


R 19,598,804.10 


2 


20 Residential Staff Houses (40 units) and Laundry Facility 


R 17,466,309.67 


3 


Relocation of 1,5 Households - Moneymine 310 CC* 


R 4,223,506.68 


4 


Relocation of 2 Households - Bonelena Construction 


R 3,698,010.76 


5 


Clinic and SAPS Garage 


R 11,900,233.76 


6 


Visitors Centre & Control Room # 


R 6,720,852.95 


7 


Tuck-shop, Transformer & LV Room, Genset Room & Refuse Area 


R 956,381.16 


8 


Guard House 1 


R 1,205,827.49 


9 


Guard House 2 & 3 


R 1,367,770.87 


10 


Crew Pavilion 


R 997,831.00 


11 


Sewer Pump Station 


R 807,782.16 


12 


Fire Pool and Parking 


R 2,819,051.66 


13 


Sewer Treatment Plant 


R 1,030,673.68 


14 


Booster Pump Station and Steel Reservoir Tank 


R 571,278.25 


15 


New Residences: Security Measures & Air-conditioning 


R 5,038,036.33 


16 


General SiteworksfWote 1) 


R 67,964,858.55 




SUB-TOTAL CONSTRUCTION COST 


R 146,367,209.07 




ADD: CONTRACT PRICE ADJUSTMENT PROVISION 


R 1,231,109.08 




LESS: PENALTIES IMPOSED FOR LATE COMPLETION OF THE CONTRACT 


-R 2,781,149.08 




SUB-TOTAL NET ESCALATED CONSTRUCTION COST 


R 144,817,169.07 




VAT (14%) 


R 20,274,403.67 




R 165,091,572.74 



Figure A: Summary of the works implemented by the DPW 



* The reference to 1.5 households here relates to the fact that not all of the buildings of the one 
household were replaced as it already had an existing building at the place of relocation. 

# The control room referred to here is the lower part of the building. The lounge is on the first floor of the 
Visitors' Centre. 



49 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



v. - - ' J I ii III :.■!'. II 









twiiA'j TET3 





1 


CA du Toit 


Security Consultants 


R 2,691,231.49 


2 


Ibhongo Consulting CC 


Civil & Structural Engineers 


R 6,006,457.36 


3 


Igoda Projects (Pty) Ltd 


Electrical Engineers 


R 2,503,732.89 


4 


R&G Consultants 


Quantity Surveyors 


R 13,794,957.70 


5 


Minenhle Makhanya Architects 


Architects, Principal Agent 


R 16,587,537.71 


6 


Mustapha & Cachalia CC 


Mechanical Engineers 


R 3,676,448.05 


7 


Ramcon 


Project Management 
Project Managers 


R 5,092,477.73 









Figure B: List of Consultants and total payments made to each 



(16) The security installations and amounts involved in security measures 
previously implemented at private residences of Presidents, Deputy 
Presidents, former Presidents and former Deputy Presidents appear to 
back the conclusion that the intention of the crafters of the authorizing 
instruments for security measures envisaged items that fall in the 
ordinary definition of security installations and did not anticipate grand 
scale constructions. 



(17) In this regard, it is worth noting that at R215 million and still rising, the 
cost of security installations at President Zuma's private residence far 
exceeds similar expenditure in respect of all his recent predecessors. 
The difference is acute, even if an allowance is made for the rural 
nature of the Nkandla area and the size of President Zuma's household. 



(18) According to information submitted by the DPW and DOD: 



1. R20 101 (equating to an estimated R173 338 in 2013 financial terms) 
was spent on former President Botha's private residence; 



50 



Secure In Comfort 



A Report of the 
Public Protector 




2. R42 196 (R236 484) was spent on former President De Klerk's private 
residence; 

3. Less than R32 million was spent at former President Mandela's two 
private residences, one of which is located in a rural area in the Eastern 
Cape. I was referred to the fact that the DOD had placed a field hospital 
at his rural home, at the cost of about R17 million. However, this is a 
mobile structure that will revert back to the state and not a permanent 
fixture, as is the case of the Military Clinic constructed at President 
Zuma's private residence; and 

4. R8 113 703 (R12 483 938) in the case of former President Mbeki's 
private residence. 

(19) Judging by these amounts, it is clear that the installations envisaged in 
the name of security are items you are likely to find at a security shop or 
company regulated by the security industry regulator, PRISA and not 
the kind of constructions done work done under the rubric of human 
settlements or the built industry. 



office bearers, public officials and other actors: 

(1) This part is specifically dealt with under findings of maladministration. 
What needs to be said here is that various state actors had different 
roles they were required to play, as stipulated by law. 

(2) Most of the roles are prescribed under the Cabinet Policy of 2003, the 
National Key Points Act 102 of 1980 and procurement prescripts, which 
primarily comprise the Public Finance Management Act 1 of 1999, 



(e) 



Regarding conduct allegedly amounting to maladministration by public 



51 



Secure In Comfort A Report of the March 2014 

Public Protector 



Preferential Procurement Policy Framework Act 5 of 2000, Treasury 
Regulations, Treasury Directives and Practice Notes and related 
prescripts and departmental policies and guidelines. 



(3) The actors in question were also required to refrain from prohibited 
practices, such as acts prohibited under the Executive Ethics Code, the 
Public Service Code and sections 96 and 195 of the Constitution. 

(4) The documents elicited, particularly in the form of memoranda, letters 
and minutes show that virtually all the parties involved either failed to do 
what they were required to do or did what they were not supposed to 
do. I deal with the accountability of relevant state actors in the findings. 

(5) Worth noting is the fact that no evidence indicates that any of the state 
actors took prudent action when the Mail & Guardian Newspaper blew 
the whistle on the runaway cost of the Nkandla Project in 2009, alleging 
then that an exorbitant amount of R65 million had been spent. It is my 
considered view that the President, Minister and Deputy Minister of 
Public Works and senior officials in the SAPS, DPW and DOD involved 
should have immediately assessed the project with a view to verifying 
the veracity of the allegations and if confirmed, arrest the escalating 
costs. I am also quite certain that had such prudent action been taken, 
we would not be speaking of R215 million while still counting today. 



(6) Considering that the Principal Agent, Mr Makhanya and one of the 
contractors, Moneymine, billed the President or his private works and 
the state for the Nkandla Project, it is difficult to understand how they 
could have charged the amounts in respect if the latter when some of 
the works are fairly similar or substantially less involved than the 
President's dwellings. More perplexing is the fact that many of the 



52 



Secure In Comfort 



A Report of the 
Public Protector 




measures funded by the state were less extensive than the President's 
private works. An example in this regard is the relocation of two families 
at R2.1 million each. 



security measures and the construction of buildings and other items at 
the President's private residence and was such authority violated or 
exceeded? 

(1) The authority for implementing security measures at the private 
residence of the President is primarily conferred by the Cabinet Policy 
of 2003. In view of the Declaration of the residence as a National Key 
Point during the implementation of the security measures, the National 
Key Points Act, constitutes part of the legal framework conferring 
authority to upgrade security at a private residence. However, the 
implementation of the security measures failed to comply with the 
parameters set out in the laws in question for the proper exercise of 
such authority. 

(2) The key violation in this regard is the failure to follow the processes 
outlined in the Cabinet Policy and the deviation from the 16 security 
measures that were recommended in the Second Security Evaluation 
by SAPS. This constitutes improper conduct and maladministration. 

(3) With the National Key Points Act having been inexplicably dragged in 
halfway through the implementation of the Nkandla Project, its 
provisions had to be complied with. This did not happen. Neither was 
there compliance with the contents of the declaration of the Nkandla 



(xi) 



I make the following findings: 



(a) 



Was there any legal authority for the installation and implementation of 



53 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

Residence as a National Key Point, as signed by the Minister of Police 
on 08 April 2010. 

(4) In relation to installations at the request of the Surgeon General on 
behalf of the DOD and SAMHS, there appears to be no instrument 
specifically authorizing the construction of brick and mortar installations 
at or for a private household. The installations were justified on generic 
military doctrines aimed at installations built in pursuit of public 
services and the general power given to the SAMHS to provide health 
services to the President Deputy President, Minister and Deputy 
Minister of Defence and, at the request of the Minister of International 
Relations and Cooperation, to foreign dignitaries. 

(b) Was the conduct of relevant authorities in respect of the procurement 
of goods services relating to the Nkandla Project improper and in 
violation of relevant prescripts? 

(1) The organs of state involved in the Nkandla Project failed dismally to 
follow Supply Chain Management prescripts, such as section 217 of the 
Constitution, PFMA, Treasury Regulations the DPW Supply Chain 
Management policy, key omissions including: the absence of demand 
management; improper delegations; failure to procure services and 
goods costing above R500 000 through a competitive tender process; 
failure to conduct due diligence leading to the engagement of service 
providers such as the Principal Agent without the necessary 
qualifications or capacity for security measures; failure to ensure 
security clearance for service providers, and allowing "scope creep" 
leading to exponential scope and cost escalations. 



54 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



(2) In addition, the DPW failed to comply with the provisions of GIAMA, 
which specifically require a proper asset management plan in respect of 
the immovable assets of the state. 



(3) The conduct of all organs of state involved in managing the Nkandla 
Project, particularly officials from the DPW, who unduly failed to comply 
with Supply Chain Management prescripts was unlawful and constitutes 
improper conduct and maladministration. The DOD and SAPS officials 
failed to comply with Treasury Regulation 16A.3.2 imposing the 
responsibility for demand management on client departments, which 
include ensuring cost effective measures and budgeting, appropriately 
for such. 



(c) Did the measures taken by the DPW at the President's private 

residence, go beyond what was required for his security? 

(1) A number of the measures, including buildings and other items 
constructed and installed by the DPW at the President's private 
residence went beyond what was reasonably required for his security. 
Some of these measures can be legitimately classified as unlawful and 
the acts involved constitute improper conduct and maladministration. 

(2) Measures that should never have been implemented as they are neither 
provided for in the regulatory instruments, particularly the Cabinet Policy 
of 2003, the Minimum Physical Security Standards and the SAPS 
Security Evaluation Reports, nor reasonable, as the most cost effective 
to meet incidental security needs, include the construction inside the 
President's residence of a Visitors' Centre, an expensive cattle kraal 
with a culvert and chicken run, a swimming pool, an amphitheatre, 
marquee area, some of the extensive paving and the relocation of 



55 



Secure In Comfort 



A Report of the 
Public Protector 




neighbours who used to form part of the original homestead, at an 
enormous cost to the state. The relocation was unlawful as it did not 
comply with section 237 of the Constitution. The implementation of 
these installations involved unlawful action and constitutes improper 
conduct and maladministration. 

(3) Measures that are not expressly provided for, but could have been 
discretionally implemented in a manner that benefits the broader 
community, include helipads and a private clinic, whose role could have 
been fulfilled by a mobile clinic and/or beefed up capacity at the local 
medical facilities. The measures also include the construction, within the 
state occupied land, of permanent, expensive but one roomed SAPS 
staff quarters, which could have been located at a centralized police 
station. The failure to explore more economic and community inclusive 
options to accommodate the discretional security related needs, 
constitutes improper conduct and maladministration. 



amount to opulence at a grand scale, as alleged? 

(1 ) The expenditure incurred by the state in respect of the measures taken, 
including buildings and other items constructed or installed by the DPW 
at the request of the SAPS and DOD, many of which went beyond what 
was reasonably required for the President's security, was 
unconscionable, excessive, and caused a misappropriation of public 
funds. The failure to spend state funds prudently is a contravention of 
section 195 (1)(b) of the Constitution and section of the Public Finance 
Management Act. The acts and omissions involved are, accordingly, 
unlawful and constitute improper conduct and maladministration. 



(d) 



Was the expenditure incurred by the state in this regard excessive or 



56 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC PEOTECTOf? 
SOUTH flfPICfl 

(2) The first Complainant's allegation that the expenditure constitutes 
opulence at a grand scale is substantiated. The acts and omissions that 
allowed the excessive expenditure due to non-security items and failure 
to arrest the wild cost escalation, especially after the story broke in the 
media in December 2009, constitute improper conduct and 
maladministration. 



(e) Did the President's family and/or relatives improperly benefit from 

installations implemented by the state at his private residence? 

(1) The allegation that President Zuma's brothers improperly benefitted 
from the measures implemented is not substantiated. I could find no 
evidence supporting the allegations that the President's brothers 
benefitted from the procurement of electrical items for the 
implementation of the Nkandla Project. 



(2) The allegation that the excessive expenditure added substantial value 
to the President's private property at the expense of the state is 
substantiated. The excessive and improper manner in which the 
Nkandla Project was implemented resulted in substantial value being 
unduly added to the President's private property. The acts and 
omissions that allowed this to happen constitute unlawful and conduct 
improper conduct and maladministration. 



(3) The original allegation that President Zuma's immediate family 
members also improperly benefitted from the measures implemented is 
substantiated. President Zuma improperly benefited from the measures 
implemented in the name of security which include none security 
comforts the Visitors' Centre, such as the swimming pool, amphitheatre, 
and the cattle kraal with culvert and chicken run. The private medical 



57 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



clinic at the family's doorstep will also benefit the family forever. The 
acts and omissions that allowed this to happen constitute unlawful and 
improper conduct and maladministration. 

(4) I do not find the relocation of the tuck shop as a benefit as the business 
was moved at the instance of the state to a building that might even be 
inconvenient to the owner. 

(5) The conduct of the DPW leading to the failure to resolve the issue of 
items earmarked for the owner's cost transparently, including the failure 
to report back on the swimming pool question after the 1 1 May 201 1 
meeting and the disappearance of the letter proposing an 
apportionment of costs, constitutes improper conduct and 
maladministration 

(f) Was there any maladministration by public office bearers, officials and 

other actors involved in the project? 

(1) Public Office Bearers: 

1 . All the Ministers of Public Works provided incorrect information on the 
legal authority for and the extent of the works at the President's private 
residence. 

2. The Minister of Police failed to properly apply his mind when signing the 
Declaration of President Zuma's private residence as a National Key 
Point directing the President to implement security measures at own 
cost or to properly modify the Declaration. This failure constitutes 
improper conduct and maladministration. 



58 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



3. The former Minister of Public Works, Mr G Doidge and the Minister of 
Police could have provided better executive leadership, especially with 
regard to speedily accessing the extent and cost of the Nkandla Project, 
particularly when the media broke the story in 2009 and taking decisive 
measures to curb excessive expenditure. Their failure in this regard 
constitutes improper conduct and maladministration 



(2) Officials of the DPW: 

1. The DPW officials failed to acquaint themselves with the authorizing 
instruments relating to the implementation of the Nkandla Project. They 
failed to apply their minds and adhere to the supply chain management 
policy framework in respect of the procurement of goods and services 
for the Nkandla Project. These failures constitute improper conduct and 
maladministration. 



2. Messrs Malebye and Vukela, the Acting Directors-General of the DPW 
failed as the accounting officers of the Department at the material times 
to comply with and/or ensure compliance with the provisions of sections 
195(1)(b) and 217 of the Constitution, the PFMA, Treasury Regulations 
and prescripts and the DPW Supply Chain Management Policy in 
respect of the Nkandla Project was improper and constitutes 
maladministration. 

3. Ms G Pasely, the Chief Quantity Surveyor showed exemplary conduct 
by raising her concerns about the excessive escalation in the cost of the 
Project. It is unfortunate that her concerns in this regard were not taken 
seriously. 



(3) Officials of the SAPS: 



59 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



JCjLIC F>EO>TE<:.TOk 



1. The SAPS officials failed to acquaint themselves with the authorizing 
instruments relating to the implementation of the Nkandla Project. They 
failed to apply their minds and adhere to the supply chain management 
policy framework in respect of the procurement of goods and services 
for the Nkandla Project. These failures constitute improper conduct and 
maladministration. 

2. Brigadier Adendorff, the Head of Security Advisory Service failed to 
comply with and or ensure compliance with the provisions of sections 
195(1)(b) and 217 of the Constitution, the PFMA, Treasury Regulations 
and prescripts in respect of the area of her responsibility relating to the 
Nkandla Project was improper and constitutes maladministration 

(4) Officials of the POD 

1. The DOD officials failed to acquaint themselves with the authorizing 
instruments relating to the implementation of the Nkandla Project. They 
failed to apply their minds and adhere to the supply chain management 
policy framework in respect of the procurement of goods and services 
for the Nkandla Project. These failures constitute improper conduct and 
maladministration. 

2. Lt Gen Ramlakan, the former Surgeon-General, failed to comply with 
and or ensure compliance with the provisions of sections 1 95(1 )(b) and 
217 of the Constitution, the PFMA, Treasury Regulations and prescripts 
in respect of his area of responsibility relating to the Nkandla Project 
was improper and constitutes maladministration. 



60 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

(5) The Contractors 

1. Mr Makhanya's assumed of multiple and conflicting roles as Principal 
Agent, the President's architect and procurer of some of the 
subcontractors which placed him in a position where the advice he gave 
was tainted by conflict of interest and not in the public interest, which 
led to uncontrolled scope creep, cost escalation and poor performance 
by some of the contractors. 

(g) Was there any political interference in the implementation of this 
project? 

(1) The former Minister of Public Works, Mr G Doidge, and Deputy Minister 
Bogopane-Zulu were at some stage involved in the implementation of 
the Nkandla Project. Their involvement, albeit for a short period of time, 
appears to have created an atmosphere that was perceived as political 
interference or pressure, although the evidence does not show any 
such intent on their part. 

(2) The Task Team Report also indicated that officials were uneasy with the 
operational involvement of politicians in the Nkandla Project. 

(3) Their involvement at trench level, including the Deputy Minister making 
suggestions on how to meet perceived security needs, was ill advised 
although well intended in the light of failures in meeting the project 
timelines. While I would discourage such acts in similar future 
circumstances, I am unable to find their attempts at problem solving as 
constituting improper conduct or maladministration. 



61 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



(h) Were funds transferred from other much needed DPW projects to fund 

this project? 



(1) Funds were reallocated from the Inner City Regeneration and the 
Dolomite Risk Management Programmes of the DPW. Due to a lack of 
proper demand management and planning service delivery 
programmes of the DPW were negatively affected. This was in violation 
of section 237 of the Constitution and the Batho Pele White Paper and 
accordingly constitutes improper conduct and maladministration. 



(i) Is the President liable for some of the cost incurred? 



(1) If a strict legal approach were to be adopted and the National Key 
Points Act was complied with, President Zuma would be held to the 
provisions of the Declaration of the Minister of Police issued on 08 April 
2010, which informs him of the decision to declare his private Nkandla 
residence a National Key Points and directs him to secure the National 
Key Point at his own cost. 



(2) However, that approach would not meet the dictates of fairness as the 
Presidents, Deputy Presidents, former Presidents and former Deputy 
Presidents are entitled, under the Cabinet Policy of 2003, to reasonable 
security upgrades, at their request or that of their office at state 
expense. Even on the understanding that some of the measures were 
unauthorized and transcended security measures as envisaged in the 
regulatory instruments and security evaluation findings, the 
questionable measures implemented exceed the financial means of an 
ordinary person. It is further clear from all communication by President 
Zuma that he was never familiarized with the provisions of the National 
Key Points Act and, specifically, the import of the declaration. The 

62 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



declaration itself was apparently delivered to his office in April 2011, a 
year after it was made and more than two years after the security 
installations had commenced. 



(3) The DPW mismanaged the process initiated with a view to determining 
the cost to be paid by President Zuma in respect of security measures 
installed at and in support of his private residence at Nkandla and which 
was initially estimated at more than R10 million, leading to a situation 
where to date, there is no clarity on that matter. This constitutes 
improper conduct and maladministration. 



(4) It is my considered view that as the President tacitly accepted the 
implementation of all measures at his residence and has unduly 
benefited from the enormous capital investment from the non-security 
installations at his private residence, a reasonable part of the 
expenditure towards the installations that were not identified as security 
measures in the list compiled by security experts in pursuit of the 
security evaluation, should be borne by him and his family. 

(5) It is also my considered view that the amount in question should be 
based on the cost of the installation of some or all the items that can't 
be conscionably accepted as security measures. These include the 
Visitors' Centre, cattle kraal and chicken run, swimming pool and 
amphitheatre. The President and his legal advisers, did not dispute this 
in their response to the Provisional Report. The President did not 
dispute during the investigation that he told me on 1 1 August 2013 that 
he requested the building of a larger kraal, and that he was willing to 
reimburse the state for the cost thereof. 



63 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



(j) Were there ethical violations on the part of the President in respect of 

the project? 



(1) President Zuma told Parliament that his family had built its own houses 
and the state had not built any for them or benefited them. This was not 
true. It is common cause that in the name of security, government built 
for the President and his family in his private a Visitors' Centre, cattle 
kraal and chicken run, swimming pool and amphitheatre among others. 
The President and his family clearly benefitted from this. 

(2) I have accepted the evidence that he addressed Parliament in good 
faith and was not thinking about the Visitors' Centre, but his family 
dwellings when he made the statement. While his conduct could 
accordingly be legitimately construed as misleading Parliament, it 
appears to have been a bona fide mistake and I am accordingly unable 
to find that his conduct was in violation of paragraph 2 of the Executive 
Ethics Code. His statement is also consistent with those made by the 
Ministers of Public Works throughout the public outcry over the Nkandla 
expenditure. I am accordingly unable to find that his conduct was in 
violation of paragraph 2 of the Executive Ethics Code. 



(3) Regarding President Zuma's conduct in respect of the use of state 
funds in the Nkandla Project, on the only evidence currently available, 
the President failed to apply his mind to the contents of the Declaration 
of his private residence as a National Key Point and specifically failed to 
implement security measures at own cost as directed by it or to 
approach the Minister of Police for a variation of the Declaration. 

(4) It is my considered view that the President, as the head of South Africa 
Incorporated, was wearing two hats, that of the ultimate guardian of the 



64 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




resources of the people of South Africa and that of being a beneficiary 
of public privileges of some of the guardians of public power and state 
resources, but failed to discharge his responsibilities in terms of the 
latter. I believe the President should have ideally asked questions 
regarding the scale, cost and affordability of the Nkandla Project. He 
may have also benchmarked with some of his colleagues. He also may 
have asked whose idea were some of these measures and viewed 
them with circumspection, given Mr Makhanya's non-security 
background and the potential of misguided belief that his main role was 
to please the President as his client and benefactor. 

(5) It is also not unreasonable to expect that when news broke in 
December 2009 of alleged exorbitant amounts, at the time R65 million 
on questioned security installations at his private residence, the dictates 
of sections 96 and 237 of the Constitution and the Executive Ethics 
Code required of President Zuma to take reasonable steps to order an 
immediate inquiry into the situation and immediate correction of any 
irregularities and excesses. 

(6) His failure to act in protection of state resources constitutes a violation 
of paragraph 2 of the Executive Ethics Code and accordingly, amounts 
to conduct that is inconsistent with his office as a member of Cabinet, 
as contemplated by section 96 of the Constitution. 

(7) Regarding the allegation that the President may have misled Parliament 
and accordingly violated the Executive Ethics Code when he 
announced that the renovations at his private residence were financed 
through a bank mortgage bond, I am unable to make a finding. Although 
having established through the Register of Financial Interests that the 
President has declared a mortgage bond in respect of his private 



65 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




residence at Nkandla since 2009, I am not able to establish if costs 
relating to his private renovations were separated from those of the 
state in the light of using the same contractors around the same time 
and the evidence of one invoice that had conflated the costs although 
with no proof of payment. 



(1 ) The occupation by the state of the land adjacent to that occupied by the 
President, and where security and other measures were constructed 
and installed by the DPW is unlawful and improper as it violates the 
provisions and requirements of the KwaZulu-Natal Ingonyama Trust 
Act, 1994 that requires a proper lease agreement. It also constitutes 
maladministration. 

(2) The conduct of some of the role players unduly delayed the 
investigation. 



(1) The anomalies in the Nkandla Project point to the existence of systemic 
policy gaps and administrative deficiencies in the regulatory framework 
used as authority for implementing security measures at the private 
residences of ones of Presidents, Deputy Presidents, former Presidents 
and former Deputy Presidents, key among these being the absence of a 
cap and an integrated instrument such as the Ministerial Handbook, 
where all permissible measures can be found. 

(2) In view of the fact that the Cabinet Policy of 2003 applies equally to all 
Presidents, Deputy Presidents, former Presidents and former Deputy 



(k) 



Other Findings of Maladministration 



(I) 



Systemic Deficiencies Observed During the Investigation 



66 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

Presidents, there is real risk of a repeat of the Nkandla excesses in 
respect of any of the four covered categories of public office bearers in 
the future. As the policy applies to all residences of incumbents in any 
of the four categories, the risk of unbridled expenditure in the future is 
very real and needs immediate curbing. 

(3) DOD deficiencies, including no instruments for according and regulating 
the exercise of discretion and concentration of power on a single 
individual with no accountability arrangements, emphasized the need 
for a proper policy regime regulating security measures at the private 
residences of the President, Deputy President, Minister and Deputy 
Minister of Defence. 

(4) Need for a clear demarcation of the roles of the SAPS, DPW and DOD 
in respect of such projects. 

(m) The Impact of the Nkandla Project 

(1) A number of the items installed by the DPW, such as the safe haven, 
swimming pool, paved roads and walkways as well as water and 
electricity supply, will require lifetime maintenance at cost to the state. 
Some maintenance costs may transcend the President's lifetime. 

(2) The military clinic also requires maintenance, supplies and permanent 
human resources as long as it exists, which may be beyond the 
President's lifetime. 

(3) The future of the buildings constructed at the request of the SAPS also 
need to be determined. 



67 



Secure In Comfort 



A Report of the 
Public Protector 




(xii) 



Appropriate remedial action to be taken on my findings of maladministration 



and as envisaged by section 182(1) of the Constitution is the following: 



(1 ) Take steps, with the assistance of the National Treasury and the SAPS, 
to determine the reasonable cost of the measures implemented by the 
DPW at his private residence that do not relate to security, and which 
include Visitors' Centre, the amphitheatre, the cattle kraal and chicken 
run and the swimming pool. 

(2) Pay a reasonable percentage of the cost of the measures as 
determined with the assistance of National Treasury, also considering 
the DPW apportionment document. 

(3) Reprimand the Ministers involved for the appalling manner in which the 
Nkandla Project was handled and state funds were abused. 

(4) Report to the National Assembly on his comments and actions on this 
report within 14 days. 



(1) Update the Cabinet Policy of 2003 to provide for a more detailed 
regime; 

(2) Assist Cabinet to set clear standards on the security measures that can 
be taken, the reasonable cost that can be incurred by the state and the 
conditions subject to which current and former Presidents and Deputy 
Presidents would qualify for such measures; 



(a) 



The President is to: 



(b) 



The Secretary to the Cabinet to take urgent steps to: 



68 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



JCjLIC F>EO>TE<:.TOk 



(3) Take periodic measures to familiarize all members of the Cabinet with 
the parameters for enjoying executive benefits and the responsibilities 
they have to ensure that officials do not give them benefits transcending 
what they are entitled to under the law or policies; and 

(4) Ensure that the Department of Defence creates Standard Operating 
Procedures regulating the implementation of the benefits extended to 
Presidents, Deputy Presidents, the Minister and Deputy Minister of 
Defence and foreign dignitaries (at the request of the Minister of 
International Relations and Cooperation), which is aligned with the 
principles of equality, proportionality, reasonableness and justifiability, 
within 6 months from the issuing of this report. 

(c) The Minister of Police to: 

(1) Take urgent steps to expedite the review of the National Key Points Act 
to clarify its applicability to presidential security privileges and align it 
with the Constitution and post-apartheid developments; 

(2) Ensure that no further security measures are installed at the President's 
private residence at Nkandla, except those determined to be absolutely 
necessary for the functionality of already installed measures; and 

(3) Ensure that the Nkandla Project does not set a precedent for measures 
implemented in respect of any future President, Former President, 
Deputy President and Former Deputy President 



69 



Secure In Comfort 



A Report of the 
Public Protector 




(d) 



The National Commissioner of the SAPS to: 



(1) Identify officials that were and may still be involved in the Nkandla 
Project and implement measures to identify why prescripts were not 
complied with and on the basis thereof decide if disciplinary action 
should be taken; and 

(2) Assist the Minister of Police in familiarizing himself with the contents of 
and his responsibilities under the National Key Points Act and the 
Cabinet Policy of 2003 and ensure that in future officials assisting 
Ministers to take action under any law include, in each relevant 
submission, a copy of the legal instrument in question and an outline of 
all steps required of the Minister. 



(1) Identify officials that were and may still be involved in the Nkandla 
Project and implement measures to identify why prescripts were not 
complied with and on the basis thereof decide if disciplinary action 
should be taken; 

(2) With the assistance of the National Treasury, obtain advice from an 
independent and reputable security consultant on the security measures 
that were necessary for the protection of the President and estimated 
legitimate costs thereof. On the basis of this information, the DPW to 
determine the extent of the over expenditure on the Nkandla project and 
to obtain legal advice on the recovery thereof; 

(3) With the assistance of the National Treasury, determine the extent to 
which the SAPS and the DOD should be held liable for the expenditure 



(e) 



The Director-General of the DPW to take urgent steps to: 



70 



Secure In Comfort A Report of the March 2014 

Public Protector 



v ■nn ill :.■!> n 



incurred in the implementation of the Nkandla Project and to recover the 
amounts accordingly; 

(4) Take urgent steps to enter into a lease agreement with the KwaZulu- 
Natal Ingonyama Trust Board in respect of the property occupied by the 
state adjacent to the President's private residence; 

(5) Take urgent steps to relocate the park homes to another organ of state 
that requires temporary accommodation; 

(6) Review the delegation of authority to Regional Offices of the 
Department; 

(7) Ensure that all DPW staff involved in supply chain management is 
properly trained on deviations from the normal prescribed procurement 
processes; 

(8) Ensure that all DPW staff involved in the implementation and execution 
of projects are properly trained and capacitated to manage projects 
assigned to them; 

(9) Comply with the provisions of GIAMA in respect of the assets acquired 
as a result of the Nkandla Project; and 

(10) Develop a policy for the implementation of security measures at the 
private residences of the President, Deputy President and former 
Presidents and Deputy Presidents. 



71 



Secure In Comfort 



A Report of the 
Public Protector 




(xiii) 
(a) 

(b) 

(c) 

(d) 



The Secretary for Defence, to take urgent steps to: 

(1) Consolidate prescripts relating to the medical, transport and evacuation 
of Presidents, Deputy Presidents, former Presidents and former Deputy 
Presidents; 

(2) Determine the role played by DOD Officials, and in particular the 
SAMHS, in the Nkandla Project to ascertain if it was in line with their 
remit and if legal authority boundaries and procedures were complied 
with; and 

(3) Ensure certainty and accountability in respect of the future 
implementation of measures relating to (1) above. 

In order to monitor and ensure the implementation of the remedial action 
indicated above, the following steps must be taken: 

When the President submits this report and his intentions regarding the 
findings and remedial action, within 14 days of its receipt, the Director 
General in the Presidency should notify my office and Cabinet. 

Accounting Officers of all organs of state required to take remedial action, are 
to provide implementation plans to the Public Protector's office not later than 
01 May 2014. 

Status reports on implementation are to be submitted by the affected 
accounting officers within three months and final reports on action taken to 
be submitted within 6 months of the issuing of this report. 

Public Office bearers of affected organs of state are to ensure compliance. 



72 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



"Let it never be said by future generations that indifference, cynicism or selfishness 
made us fail to live up to the ideals of humanism which the Nobel Peace Prize 

encapsulates. " 
President of South Africa, Nelson Rholihlahla Mandela 



73 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



LIST OF ACRONYMS 



AGS A 


Auditor-General South Africa 


ANC 


African National Congress 


BAC 


Bid Adjudication Committee 


Bonelena 


Bonelena Construction Enterprise and 
Projects CC 


CIDB 


Construction Industry Development Board 


DG 


Director-General 


Directive 


Directive: Acquisition and Disposal 
Management 


DOD 


Department of Defence 


DPW 


Department of Public Works 


GIAMA 


Government Immovable Asset 
Management Act, 2007 


HO 


Head Office 


IDC 


Industrial Development Corporation 


JCPS 


Justice, Crime Prevention and Security 


KAM 


Key Account Management 


MISS 


Minimum Information Security Standards 


Moneymine 


Moneymine 310 CC 


MTEF 


Medium Term Expenditure Framework 


MP 


Member of Parliament 


NIA 


National Intelligence Agency 


NKP 


National Key Point 


PFMA 


Public Finance Management Act, 1999 


PI 


Procurement Instruction 


PM 


Project Manager 


PMBC 


Planned Maintenance Budget Committee 


PMTE 


Property Management Trading Entity 


PPM 


Portfolio Performance and Monitoring 



74 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JM.K PftiOTECTOP? 
SC^UTH flfPKU 



QS 


Quantity Surveyor 


RBAC 


Regional Bid Adjudication Committee 


RDP 


Reconstruction and Development 
Programme 


SANDF 


South African National Defence Force 


SAPS 


South African Police Service 


SCM 


Supply Chain Management 


SAMHS 


South African Medical Health Services 


SNBAC 


Special National Bid Adjudication 
Committee 


SIU 


Special Investigating Unit 


SSA 


State Security Agency 


Voltex 


Voltex (Pty) Ltd 


WCS 


Work Control System 



75 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



LIST OF KEY ROLE PLAYERS 



NAME 


POSITION 


His Excsllencv J Zuma 


The President of the Republic of South 
Africa 


Mr J Radebe MP 


The Minister of Justice and Constitutional 
Development 


Ms N Mapisa-Nqakula MP 


The Minister of Defence and Military 
Veterans 


Mr N Mthethwa MP 


The Minister of Police 


Mr T W Nxesi MP 


The Minister of Public Works 


Dr S Cwele MP 


The Minister of State Security 


Amb. G Doidge 


A former Minister of Public Works 


Ms G Mahlangu-Nkabinde 


The former Minister of Public Works 


Ms H Rnnnnanp-7iilu MP 

ivio i i uuyuuui iu £— uiu ivii 


The former Deputy Minister of Public 
Works 


Lt Gen V Ramlakan 


The former Surgeon-General of the 
SANDF 


Dr C R Lubisi 


The Director-General in the Presidency 


Mr S Malebye 


A former Acting Director-General of the 
DPW 


Mr S Vukela 


A former Acting Director-General of the 
DPW 


Ms G Pasley 


Chief Quantity Surveyor of the DPW 


Mr K Khanyile 


Former Regional Manager of the Durban 
office of the DPW 


Mr J Rindel 


Project Manager of the Nkandla Project 


Mr J P Crafford 


Director: Architectural Services of the 
DPW 


Brigadier S J Adendorff 


Head of Security Advisory Services of the 
SAPS 



76 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 





Architect and Principal Agent appointed 


Mr M Makhanya 


by the DPW. He was also appointed by 




the President to design his private works 



77 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



1. INTRODUCTION 



1.1. "Secure In Comfort" is my report as the Public Protector of the Republic of 
South Africa on an investigation conducted into allegations of impropriety and 
unethical conduct relating to the installation and implementation of security 
measures at and in respect of the private residence of President J Zuma, at 
Nkandla in the KwaZulu-Natal Province. 



1.2. The investigation was conducted in terms of the provisions of section 182 of 
the Constitution of the Republic of South Africa, 1996 (the Constitution) and 
sections 6 and 7 of the Public Protector Act, 1994 (the Public Protector Act). 
Part of the investigation was also conducted in terms of sections 3 and 4 of 
the Executive Members' Ethics Act, 1998 (the Executive Members' Ethics 
Act). 

1 .3. The report is submitted to: 

1.3.1. The President of the Republic of South Africa, His Excellency, Mr J G Zuma; 
and 

1.3.2. The Joint Chairpersons of the Parliamentary Joint Committee on Ethics and 
Members Interests, the Honourable Prof B Turok, MP and Mr B Mashile, MP. 

1 .4. The report will also be presented to: 

1 .4.1 . The Minister of Police, the Honourable Mr N Mthethwa, MP; 



78 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC PEOTECTOf? 
SOUTH flfPICfl 

1 .4.2. The Minister of Defence and Military Veterans, the Honourable Ms N Mapisa- 
Nqakula, MP; 

1.4.3. The Deputy Minister of Women, Children and Persons with Disabilities, the 
Honourable Ms H Bogopane-Zulu, MP, who was the Deputy Minister of 
Public Works during certain times material to the investigation referred to in 
this report; 

1 .4.4. The South African High Commissioner to the Democratic Socialist Republic 
of Sri Lanka, Mr G Doidge, who was the Minister of Public Works when the 
project referred to in this report commenced; 

1 .4.5. The Director-General in the Presidency and Secretary to the Cabinet, Dr R C 
Lubisi; 

1.4.6. The Director-General of the Department of Public Works (DPW), Mr M 
Dlabantu; 

1.4.7. The National Commissioner of the South African Police Service (SAPS), 
General M V Phiyega; 

1 .4.8. The former Acting Directors General of the DPW, Messrs. S Malebye and S 
Vukela; 

1.4.9. The Section Head: Security Advisory Service of the SAPS, Brigadier S J 
Adendorff; 

1.4.10. The former Regional Manager of the DPW Durban Regional Office, Mr K 
Khanyile; and 



79 



Secure In Comfort A Report of the 

Public Protector 



1 .4.1 1 . The DPW Project Manager, Mr J Rindel. 
1 .5. Copies of the report will also be provided for noting to: 

1 .5.1 . The Minister of Justice and Constitutional Development, the Honourable Mr J 
Radebe, MP; 

1.5.2. The Minister of Public Service and Administration, the Honourable Ms L 
Sisulu, MP who was the Minister of Defence at certain times material to the 
investigation referred to in this report; 

1 .5.3. The Minister of Public Works, the Honourable Mr T Nxesi, MP; 

1 .5.4. The Minister of State Security, the Honourable Dr S Cwele, MP; 

1 .5.5. The South African Ambassador to the Republic of Angola, His Excellency, Mr 
G Ngwenya, who was the Chief of the South African National Defence Force 
(SANDF) at certain times material to the investigation referred to in this 
report; 

1 .5.6. The former National Commissioner of the SAPS, General B Cele; and 

1.5.7. The complainants. 
2. THE COMPLAINTS 

2.1. The complaints were lodged between 13 December 2011 and 12 December 
2012 the first complaint was lodged by a member of the public on 13 



March 2014 




80 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC 

SOUTH flfPICfl 

December 201 1 who expressed concern over and requested an investigation 
to verify allegations of impropriety relating to state funded upgrades at 
President Zuma's private residence, published by the Mail and Guardian on 
11 November 2011, under the heading: "Bunker, bunker time: Zuma's lavish 
Nkandla upgrade". According to this media report, the President's private 
residence was being improved and upgraded at enormous state expense. 
The improvements allegedly included a network of air conditioned living 
quarters, a clinic, gymnasium, 20 houses for security guards, underground 
parking, a helicopter pad, playground and a Visitors Centre. 



2.2. I immediately informed the Presidency of the request for an investigation into 
the matter and subsequently met with the Director-General of the Presidency, 
Dr R C Lubisi, in January 2012. He advised on appropriate departments to 
assist. 



2.3. I also informed the President and Dr Lubisi in writing of the compliant in 
letters addressed to them respectively, on 15 February 2012. 

2.4. Allegations of impropriety and excessive public expenditure relating to 
installation and implementation by the state of security measures at 
President Zuma's private residence (hereafter referred to as the Nkandla 
Project) subsequently appeared in the media on a regular basis. 



2.5. On 30 September 2012, for example, the City Press published an extensive 
article on the matter, alleging, inter alia, that the DPW had allocated funding 
of more than R203 million to the project and that the development included 
the construction of three sets of underground living quarters with 10 air 
conditioned rooms, a clinic for the President and his family, 10 houses for 
security personnel, a helipad and houses for members of the South African 
Air Force and the SAPS. 



81 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC F>EO>TE<:.TOk 
SOUTH flfPKU 



2.6. The Honourable Ms L Mazibuko, MP of the Democratic Alliance lodged a 
complaint based on this media article with my office on 30 September 2012, 
as did three members of the public in October 2012 and one in November 
2012. 



2.7. In their letters of complaint, the complainants raised, inter alia, the following 
concerns: 

2.7.1 . "Like all South Africans I have recently read in the media the appalling story 
of the sums of taxpayers' money being spent on the private residence of 
President Jacob Zuma. This is opulence on a grand scale and as an honest, 
loyal, taxpaying South African I need to understand how this is allowed to 
happen. Strangely civil society is quiet. This is wrong and highlights the 
complete disregard which this Government has for the citizens of this 
country. Where is this money coming from and how has it been approved?" 



2.7.2. "Whether any undue political influence was placed on the Department of 
Public Works to allocate these funds; 

Who issued the instruction for the allocation of these funds? 

Whether these funds have been properly budgeted for; 

Whether any funds have been transferred from other much needed projects 
for this revamp to take place; 

Whether the allocation of funds for what is essentially a private home - which 
will not remain within the state's ownership - represents irregular 
expenditure." 



82 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




2.7.3. "The Minister of Public Works has approved that highly debated, 



refurbishment of the current president's private residence in Nkandla, and 
she (sic) has indicated that this is in line with the Ministerial Handbook. This, I 
will show, is in fact not true. 

According to the handbook, 'Members are responsible for all costs related to 
the procurement, upkeep and maintenance of private residences used for 
official purposes' and furthermore The Minister of Public Works may approve 
a State contribution of a non-recoverable maximum amount of R 100 000, or 
the total cost of security measures not exceeding R100 000'. 

As the house in Nkandla is privately owned, the President should only be 
granted R100 000 for security measures, and not the allotted R203 million. 
This contradicts the handbook, and so the upgrade should be deemed 
unlawful, and I wish the Public Protector could investigate this, as the money 
is well spent on other things in South Africa. " 



2.7.4. "I do not understand how this money can be spent on a private residence of 
any government employee, especially when that employee has two 
residences at his disposal in Cape Town and Pretoria. " 

2.7.5. "Whether this construction is being performed for President Zuma as 



President of SA or as a favour as ANC President, I would suggest it is 
misuse of state funds to the benefit of a private individual, possibly to curry 
political favour for the Minister of Public Works or a DG. When the President 
is no longer the incumbent he is not entitled to state housing but he will enjoy 
the benefits of the modifications to his private estate in perpetuity . " 



83 



Secure In Comfort A Report of the March 2014 

Public Protector 



2.7.6. " While the majority of people in this country still struggle and fight for survival 
it is deeply disturbing to discover that the President and some of his close 
senior supporters feel that it is all right to abuse their positions to benefit 
themselves and each other at the expense of the nation and all her citizens. 
These individuals, in their capacities as servants of the people, should be 
held to task if they are in any way guilty of wrongdoing, abuse of power or 
corruption. If the allegations in the press on what is happening with the 
President's private homestead in Nkandla are true then the President and 
those involved in facilitating these massive renovations are possibly guilty of 
a number of transgressions and should be held accountable. At the least 
these allegations should be grounds for you and your team to conduct some 
sort of investigation." (emphases added) 

2.8. A complainant submitted that the allegations made by the media in 
connection with the developments at the President's private residence at 
Nkandla show that the President acted in violation of the Ministerial 
Handbook and that it was disingenuous for him to deny that he was unaware 
of the costs involved. 



2.9. Ms L Mazibuko, Member of Parliament and Parliamentary Leader of the 
Democratic Alliance (DA), lodged a further complaint with me in terms of the 
Executive Members' Ethics Act, on 12 December 2012. She requested that I 
investigate allegations that members of the President's family improperly 
benefitted from the Nkandla Project and that this constituted a violation of the 
Executive Ethics Code. 



2.10. Prof P De Vos of the University of Cape Town lodged a complaint on 21 
November 2012 in connection with a statement allegedly made by the 
President to the National Assembly on 15 November 2012, where he denied 
that the state had paid for the construction of any house for him and advised 



84 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

that the development of the first phase of his private residence was financed 
by a loan secured from a bank through a mortgage bond in respect of the 
property. A subsequent media article alleged that it was not true and Prof De 
Vos suggested that the President may have misled the National Assembly, 
which would constitute a violation of the Executive Ethics Code. Though 
making reference to the Executive Members' Ethics Act, Prof de Vos' 
complaint was investigated under the Public Protector Act as members of the 
public have no locus standi under this Act, as section 4 restricts the power to 
lodge complaints to members of national and provincial legislatures, the 
President and Premiers in the provinces. 

2.11. I informed the President in detail of the complaints received from Ms L 
Mazibuko and Prof De Vos in a letter addressed to him on 29 January 2013. 



2.12. I should mention that the article referred to in paragraph 2.1 above was not 
the first published by the media on allegations of opulent public spending at 
the Nkandla private residence of the President. The first article containing 
allegations of unwarranted excessive expenditure at President Zuma's 
private residence was published by the Mail and Guardian newspaper on 04 
December 2009, under the heading "Zuma's R65m Nkandla Splurge". 



2.13. Except for the release of a statement by the Presidency on 03 December 
2009, denying that government was footing the bill, nothing appears to have 
been done by government to verify the 2009 allegations or attempt to arrest 
the costs which the article predicted would continue to rise. Three years later 
and a year after a complaint was lodged with me, the Minister of Public 
Works appointed a Task Team of officials from the departments involved in 
the impugned upgrades at the President's private residence, to investigate 
specific matters in relation thereto. The Task Team's report was only 
released to the public on 1 9 December 201 3. 



85 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




2.14. 



The essence of the complaints had three key dimensions. The complainants 
were essentially alleging that: 



2.1 4.1 . There was no authority for the expenditure that was allegedly incurred by the 



state in respect of upgrades made at the President's private residence under 
the auspices of improving security. Even if there was authority, the upgrades 
were excessive or "opulent' and transcended such authority; 



2.14.2. The procurement process in respect of the security measures installed and 
implemented was improper and resulted in unduly excessive amounts of 
public money being spent unnecessarily; and 

2.14.3. The conduct of the President in relation to implementing the impugned 
upgrades at his private residence may have been unethical and in violation of 
the Executive Ethics Code. 

3. THE POWERS AND JURISDICTION OF THE PUBLIC PROTECTOR 

3.1 . Mandate of the Public Protector 

3.1.1. The Public Protector is an independent institution, established under section 



181 (2) of the Constitution to support and strengthen constitutional democracy 
by investigating any conduct in state affairs or in the public administration in 
any sphere of government, that is alleged or suspected to be improper or to 
result in any impropriety or prejudice; reporting on that conduct; and taking 
appropriate remedial action as mandated by section 1 82 of the Constitution 
and relevant legislation. 



86 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC PISOTCCTOf? 
SOUTH flfPICfl 

3.1.2. Section 182(2) of the Constitution states that the Public Protector has 
additional powers and functions prescribed by national legislation. 

3.1 .3. The Public Protector Act elaborates on the investigation powers of the Public 
Protector and section 6(4) thereof specifically provides that the Public 
Protector shall be competent to investigate, on his or her own initiative or on 
receipt of a complaint, inter alia, any alleged: 

3.1 .3.1 Maladministration in connection with the affairs of government at any level; 

3.1 .3.2 Abuse or unjustifiable exercise of power or other improper conduct by a 
person performing a public function; and 

3.1 .3.3 Improper or unlawful enrichment or receipt of any improper advantage by a 
person as a result of an act or omission in the public administration or in 
connection with the affairs of government at any level or of a person 
performing a public function. 

3.1.4. Section 8(1) of the Public Protector Act states that the Public Protector may 
make known to any person any finding, point of view or recommendation in 
respect of a matter investigated by him or her. 

3.1.5. Sections 3(1) and 4(1 )(a) of the Executive Members' Ethics Act provide that 
the Public Protector must investigate any alleged breach of the Executive 
Ethics Code on receipt of a complaint by a Member of Parliament against a 
Cabinet member. According to section 1 of the Act, "Cabinet member" 
includes the President. 

3.1.6. When investigating an alleged breach of the Executive Ethics Code, the 
Public Protector, by virtue of section 3(4) of this Act, has all the powers 



87 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




vested in her/him in terms of the Public Protector Act. Section 4 further states 
that nothing in this Act may prevent the Public Protector from investigating 
any complaint by a member of the public in accordance with the Public 
Protector Act. 



3.1 .7. The complaints lodged and the insinuations made against President Zuma 



relate to allegations of maladministration and improper conduct in state 
affairs and unethical conduct by the President, and accordingly fall within the 
jurisdiction and powers of the Public Protector. 



3.2.1. The investigation was conducted in terms of the provisions of section 182 of 



the Constitution, sections 6 and 7 of the Public Protector Act. The complaint 
lodged by Ms Mazibuko of a possible violation by the President of the 
Executive Ethics Code was received when an investigation was already 
under way, albeit at a slow pace due to capacity constraints, among others. 
The complaint was addressed by ensuring that part of the investigation that 
had been on-going for a year, was conducted in terms of sections 3 and 4 of 
the Executive Members' Ethics Act. 



3.2.2. Section 3(2) of this Act provides that the Public Protector must submit a 



report on an alleged breach of the Executive Ethics Code to the President, if 
the complaint is about a cabinet member, within 30 days of the receipt of 
thereof. 



3.2.3. However, section 3(3) states that if the Public Protector reports at the end of 
the 30 day period that the investigation has not been completed, the Public 
Protector must submit a report when the investigation has been completed. 



3.2. 



The legal framework of the investigation 



88 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



3.2.4. The President suggested, in submissions to me during the investigation, that 
I failed to comply with the 30 day period and also to report that my 
investigation had not been completed. He requested that I should indicate in 
my report whether I had complied with the said provisions, and if not, whether 
the delay in doing so is justifiable. The President further required of me to 
indicate whether he has the power to condone any non-compliance. 



3.2.5. The President's legal team further contended that the provisions of sections 
3(2) and 3(3) are prescriptive and that non-compliance would negate the 
validity of the investigation. 



3.2.6. As I have indicated above, I received only one compliant in terms of the 
Executive Members' Ethics Act, i.e. from Ms L Mazibuko, MP of the 
Democratic Alliance, in connection with allegations that the President's family 
improperly benefitted from the Nkandla Project. Her complaint was lodged on 
1 2 December 201 2, a year after the investigation commenced. 



3.2.7. On 29 January 2013, I informed the President in writing of the complaint and 
my investigation thereof and that he would be afforded an opportunity to 
respond thereto, once I had obtained more detailed information pertaining 
thereto. 



3.2.8. The President was therefore not only informed of the investigation. He was 
also advised that it was not completed 48 days after receipt of the complaint. 
This period included the end of the year festive season and therefore several 
public holidays. 



3.2.9. It was simply not possible to have concluded the investigation earlier, 
because it was an integral part of the on-going investigation in terms of the 
Public Protector Act. The President never raised this issue with me in 



89 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



subsequent correspondence and when I met with him on 11 August 2011 or 
at any other stage objected to my investigation. 



3.2.10. More importantly though, I respectfully do not accept the contention by the 
President and his lawyers' that if the Public Protector fails to comply with the 
30 day period, it could impact on the validity of the investigation. This period, 
in my respectful view, was determined by the Legislature to ensure that an 
investigation against a member of the executive regarding a violation of the 
Executive Ethics Code should be expeditious, if possible. An executive 
members' public accountability, in my view, cannot lapse if the 30 days 
period is not met. I am particularly saddened by the fact that such a 
submission was made by the ultimate custodian of executive accountability. 



3.2.11. If the investigation takes longer than 30 days, then the Public Protector can 
issue the report when he/she is ready to do so. The only requirement is that 
the President should be informed. Regarding the President's complaint in his 
submission that inadequate regard had been given for the delay in finalizing 
the investigation, I advised him and his lawyers that there is also no provision 
in this Act or any other law that requires of the Public Protector to explain to 
the President why the investigation took longer than 30 days to complete. 
The explanation in the Provisional Report was accordingly not exhaustive as 
it simply meant to highlight some of the hurdles faced in undertaking the 
investigation leading to the delay in its finalisation. 



3.2.12. Section 3(4) provides that when the Public Protector conducts an 
investigation in terms of the Act, he/she has all the powers vested in the 
Public Protector, in terms of the Public Protector Act. Consequently, even if 
the submissions made by the President and his legal team carried any merit, 
it would not have any impact on the validity of my investigation in terms of 



90 



Secure In Comfort A Report of the March 2014 

Public Protector 



v ■mil mi :.■!'. II 



section 182 of the Constitution and sections 6 and 7 of the Public Protector 
Act, that covered the very same issues. 



3.2.13. There is no provision in the Constitution, the Public Protector Act or the 
Executive Members' Ethics Act, that authorizes the President to condone any 
action or omission of the Public Protector. In this case, as I have stated 
above, I respectfully hold the firm view that there was no conduct failure on 
my part in the investigation of the matters concerned. 



3.2.14. The suggestion that the duty to account for one's alleged ethical violations 
lapses in the event of non-compliance with the reporting requirements appear 
at odds with the spirit of the Act and public accountability in general. It seems 
odd that the right of members of the public to exact accountability with regard 
to ethical conduct by members of the Cabinet, through their legislative 
representatives, would be extinguished simply because investigative 
timelines have been missed. Clearly the timelines are meant to ensure 
efficient handling of such matters but certainly not for members of the 
Executive to evade accountability. 



3.2.15. It must be noted that this is the first time such an objection is raised. When I 
came in as Public Protector there were matters that had been going on for 
longer than 30 days from my predecessor which I completed as soon as 
possible and presented the reports to the President without hurdles. 

3.2.16. I have also considered that if time lines have an impact of the validity of an 
on-going investigation, it could be equally true that failure by the President to 
meet his 14 day timeline would absolve Parliament of its duty to entertain the 
President's report regarding how he has dealt with the Public Protector's 
report. This certainly could not have been the intention of the architects of the 
legislation. 



91 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



JCjLIC F>EO>TE<:.TOk 



3.2.17. The need for a speedy resolution of these matters cannot be contested. 

However, an approach that supports public accountability and, accordingly, 
the rule of law, would not seek to aid members of the executive to evade 
accountability. The approach would help review the resource requirements 
and assist to address capacity gaps. It is a well-known fact that I have 
appealed to Parliament for more resources for my office, particularly 
resources dedicated to the additional statutory mandates that were given to 
the office in the past few years, without additional resources specifically 
dedicated to those new mandates. This applies particularly to the Executive 
Members' Ethics Act, Protected Disclosures Act, 26 of 2000 and Housing 
Measures Protection Act, 95 of 1998. While Parliament initially accepted the 
request without reservation, in the last two years, questions have been raised 
regarding the deservability of the additional resources. The reality though is 
that no resources were ever assigned for the implementation of these 
additional mandates and while the office has always struggled to meet the 30 
day requirement, the increase in work load and delays in securing answers 
have compounded the situation. 



3.3. Balancing State Security Considerations with Open Democracy 
Requirements 



3.3.1 . As the investigation progressed towards reporting, questions arose regarding 
whether the report should be kept as a confidential report in view of the 
subject matter being security installations and many of the regulatory 
instruments and sources of evidence being classified documents. These 
questions had to be dealt with against the backdrop of the matter already 
being in the public domain since 2009 and the narrative being riddled with 
suspicions of impropriety and a cover up. The context of open democracy 



92 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




being one of the foundational values of South Africa's democracy, as 
entrenched in section 1 of the Constitution, also had to be taken into account. 



3.3.2. Organs of state affected by the investigation, mainly the security cluster, 



sharply raised the security question towards the conclusion of the 
investigation. By February 2013, the concerns culminated in outstanding 
documents being withheld on account of security and delays in conducting an 
inspection in loco at the Nkandla residence. Threats of litigation were made 
and eventually on 8 November 2013, government departments took me to 
court ostensibly for not giving them enough time to assess the Provisional 
Report for possible security breaches. In reality the cluster advanced 
arguments that questioned my power to scrutinize the exercise of power by 
security Ministers and that also challenged security implications of the 
provisions of the Provisional Report that had no relevance to security. 
Incidentally, the bulk of the objections were withdrawn when the investigation 
team eventually met with a Task Team of security cluster officials I had 
requested be constituted to depoliticize the security assessment of the 
Provisional Report. By then it had dawned on the security cluster that 
government had made public most of the contested information in a 12 000+ 
page batch of documents given to the M&G Centre for Investigative 
Journalism {amaBhungane). This had been done in June 2013 in response to 
a court application brought in terms of the Promotion of Access to Information 
Act 3 of 2000. 



3.3.3. My approach regarding balancing the dictates of open democracy as a pillar 



of public accountability with legitimate state security concerns, was informed 
by section 32 of the Constitution read with Section 8(2A)(a) of the Public 
Protector Act provides that any report issued by the Public Protector shall be 
open to the public, unless the Public Protector is of the opinion that 
exceptional circumstances require that the report be kept confidential. 



93 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

3.3.4. In the event that the Public Protector is of the opinion that exceptional 
circumstances require that a report be kept confidential, the Parliamentary 
Committee on Justice and Constitutional Development must be furnished 
with the reasons therefor and, if the Committee concurs, such report shall be 
dealt with as a confidential document in terms of the rules of Parliament. 



3.3.5. Exceptional circumstances shall, in terms of section 8(2A)(c) of the Public 
Protector Act, exist if the publication of the report is likely to, inter alia: 



• Endanger the security of the citizens of the Republic; 

• Disturb the public order or undermine the public peace or security of the 
Republic; 

• Be prejudicial to the interests of the Republic. 

3.3.6. In considering this issue, I took cognizance of the fact that some of the 
information that was provided to me during the investigation related to the 
security measures that were taken at the President's private residence in its 
capacity as a National Key Point. The witnesses and officials that provided 
such information during the investigation did so in terms of their obligation to 
cooperate with my investigation in terms of the Public Protector Act. 



3.3.7. Some of the information obtained during the investigation was classified as 
"Top Secret" by the owners thereof. In terms of the provisions of the 
Minimum Information Security Standards policy, this means that the 
information is regarded as being of such a nature that its unauthorized 
disclosure/exposure can be used by malicious/opposing/hostile elements to 
neutralize the objectives and functions of institutions and/or the state. 



94 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



3.3.8. The security of the President is of utmost importance to the safety of the 
state and the information in respect of the Nkandla Project was throughout 
the investigation handled with sensitivity and the necessary precautions. 



3.3.9. I took the additional precaution in this regard to provide the Ministers of the 
Security Cluster with an opportunity to comment on security issues, referred 
to in my draft provisional report, which concerned them to enable me to 
consider whether it should be masked in or removed from my final report. 
The court application (referred to below) brought by the Ministers of Public 
Works, Police, State Security and Defence was later withdrawn. 

3.3.10. Having considered all the inputs provided to me in this regard, I had to strike 
a balance between the obligation in terms of the Public Protector Act to issue 
a report that is open to the public, and not compromising the security of the 
President and the state. I concluded that: 



(a) Since Public Protector proceedings are inquisitorial, based on the 
relevant provisions of the Constitution, the Public Protector Act and the 
Executive Members' Ethics Act and as the matter involved the President 
of our country and the appropriation of public funds, the reporting has to 
be open and transparent; 

(b) The information referred to in this report relates to matters of 
procurement and ethical conduct. The focus is not on the nature and 
extent of the security measures installed and implemented at the 
President's private residence; 

(c) Most of the information concerned has been in the public domain for 
approximately two years. It reached the public domain by means of 
media reports based on information obtained by investigative journalists 



95 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH flfPKIl 



and voluminous documents provided by the Minister of Public Works; 
and 



(d) The impact of the failure to disclose the relevant information contained 
in this Report would be that the public would not be informed of the 
extent of my investigation, the basis for my findings and the reasoning 
for the remedial action taken. This would not be in the public interest or 
in the interest of the affected parties and institutions. 



(e) Due to the fact that the report of the DPW Task Team was declassified, 
and the bulk of the information and documentation relating to matters of 
security were already in the public domain by the time my investigation 
was concluded, the issue of whether or not my report should be made 
public became moot. 



3.4. Security Cluster objections to the investigation and preference for 
investigations by the SIU and Auditor General 



3.4.1. After a smooth flow of information from affected organs of state, including 
extensive documents received from the DPW, the Minister of Police suddenly 
raised an objection to the investigation. He questioned the need in the light of 
government having established an internal task team that had made findings 
on the matter and that the internal process had not yet been concluded as 
investigations by the Auditor General and the Special Investigation Unit 
(SIU), which had been recommended by the Task Team had not yet been 
undertaken. There was also a veiled questioning of the authority of my office 
to investigate a security matter and to access related security documents. 



3.4.2. The objection was first expressed in Minister Nathi Mthethwa's letter of 22 
March 2013, which should have been a response to a request for information 



96 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

in the possession of the SAPS. He indicated that he had difficulty providing 
the information in the light of the concerns I have alluded to, and requested a 
joint meeting with his security cluster colleagues to iron out issues. 

3.4.3. This followed my approach to Minister Mthethwa in writing on 1 1 February 
2013, informing him of my investigation and requesting copies of the relevant 
documents relating to the declaration of the President's private residence as 
a National Key Point and the procedure followed in terms of the relevant Act 
and the Cabinet Policy on Security Measures at the Private Residences of 
the President, Deputy President and former Presidents and Deputy 
Presidents of 2003. 

3.4.4. In his letter to me dated 22 March 2013,, Minister Mthethwa alluded to a 
statement issued by the Minister of Public Works on the report of the internal 
Task Team that was appointed by the latter and specifically to the 
recommendations made in the report that the matters concerned should be 
referred to a (at the time) to-be-established Special Investigating Unit and the 
Auditor-General for further investigation and stated that: 

"/ am concerned that you have now decided to investigate the matter even 
though a number of processes are underway to deal with the 
maladministration identified by the Task Team. In effect, an allegation or 
suspicion of maladministration no longer exists . The Task Team has 
identified maladministration and, therefore, the Ministers in the JCPS Cluster 
have decided that a Special Investigating Unit and the Auditor-General must 
conduct a full investigation and audit. Any other appropriate steps will also be 
taken. 

I have considerable difficulty in complying with your reguest to provide you 
with all the documents relating to the declaration . Not only will this 



97 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

compromise the security arrangements in place at the President's private 
residence, it will subject to scrutiny the methodology used and the factors 
taken into account when considering the declaration of a national key point. 
This could compromise national security. 

I have discussed your request with the other Ministers of the J CPS Cluster 
involved in the matter and with the Minister of Justice and Constitutional 
Development. Whilst every effort has been made to cooperate with you and 
while every effort will continue to be made to continue to cooperate with you, 
the Ministers do share some of my concerns and have raised others. They 
have, therefore, directed me to request you to meet with all of us to discuss 
your investigation and the documents which you have requested." (emphasis 
added) 

3.4.5. The meeting as requested by the Minister of Police took place on 22 April 
2013 and was also attended by the Ministers of Public Works and State 
Security. At the meeting, I explained in detail the constitutional and statutory 
mandate of the Public Protector to investigate the matters concerned. I also 
emphasized the fact that my investigation was already at an advanced stage 
and that the Minister of Public Works and the President had been informed of 
the investigation when it commenced and complied with consequent 
document and information requests. A letter from me addressed to the 
Minister of Police, dated the same day, was also presented to the Ministers. 
In this letter I stated, inter alia, that: 

"It was noted during my investigation to date that reference is often made to 
the fact that the information that I requested is classified or 'Top Secret' and 
could therefore not be provided to me. However, I could find no indication in 
the National Key Points Act, 1980, the said Cabinet Policy, the Protection of 
Information Act, 1982 or the Minimum Information Security Standards that 



98 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

could be interpreted as prohibiting the Public Protector from having access to 
any information that relates to state affairs, which, I must point out, would be 
a contradiction of section 7(4) of the Public Protector Act. 

Section 7(4) gives the Public Protector full and free access to any information 
or document that has a bearing on any matter that is being investigated by 
him or her, whether it was classified as top secret or not. 

You will note that section 7(4) (a) of the Public Protector Act authorizes me to 
request and subpoena any such information from any person in the Republic 
with no exceptions. The Public Protector also has powers of search and 
seizure to obtain documentation and information relevant to any 
investigation. The provisions are consistent with the Public Protector being 
one of the only 2 specified safe harbours under the Protected Disclosures Act 
and one of the enforcers of the Promotion of Access to Information Act No 2 
of 2000. 

Information in the possession of the Public Protector is furthermore protected 
by the provisions of section 7(2) of the Public Protector Act, in terms of which 
it may not be disclosed without his or her consent. In terms of section 6(8), 
not even a court of law can force the Public Protector to disclose such 
information. 

Under the circumstances, you will appreciate that I find it difficult to 
understand why classified and top secret information can be shared with the 
internal Task Team, the Special Investigation Unit and the Auditor-General, 
which according to your letter under reply will be mandated to investigate this 
matter, but not with the Public Protector. I am further perplexed and 
perturbed by the statement in your letter under reply that to disclose the 



99 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

information that I am by law entitled to have access to 'could compromise 
national security. ' 

I must further express my concern about the intention expressed in your 
letter to establish a Special Investigating Unit (appointed by and reporting to 
the President) to investigate the matters that I am currently investigating. As 
indicated earlier, my investigation is already at an advanced stage, about 
90% complete. The investigation team has already interviewed a number of 
witnesses, studied a wide range of voluminous documents and the relevant 
legislation and other prescripts applicable. Obviously, my office has incurred 
substantial expenditure in conducting the investigation so far. To appoint 
another body to investigate the same matters would, in my respectful view, 
constitute a duplication of efforts and associated costs and other resources. 

From what is stated above, you will note that my investigation into the 
matters referred to had already commenced in 201 1, before the internal Task 
Team was appointed by the Minister of Public Works. As indicated, my 
investigation is already at an advanced stage and will be concluded soon, 
provided that I receive the outstanding information that is required from your 
office and the Minister of Public Works timeously. " 

3.4.6. It should be noted that when approached by my office on 25 March 201 3, the 
Auditor General South Africa, indicated that the request by the DPW to 
investigate the matter concerned had been declined. During the meeting with 
the said Ministers on 22 April 2013, I informed them accordingly. 

3.4.7. It was agreed at the meeting of 22 April 2013 that I would continue with my 
investigation. The Ministers attending indicated that they would cooperate 
with me by providing me access to the requested classified documents 
during a briefing of the processes followed. It was also agreed that I would be 



100 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

briefed on the report of the Internal Task Team that investigated certain 
aspects of the Nkandla Project. 

3.4.8. I was therefore surprised to receive a letter from the Acting State Attorney on 
24 April 2013, acting on behalf of the Ministers of Public Works, State 
Security and Police. Referring to the meeting of 22 April 2013, he stated, 
inter alia, that: 

"Monday's meeting with you suggests to our clients that you have embarked 
on a parallel process to investigate the matters currently under investigation 
by them. The additional steps being taken by them will also impact on the 
final determination of the matter by our clients who will decide in consultation 
with the JCPS Cluster Ministers and with the Cabinet what further measures 
should be taken. Any transgressions will be dealt with firmly by our clients. 
Our clients believe that the SIU has the competency and powers to 
conduct this investigation and also point out that you yourself have 
previously collaborated with the SIU during the handling of sensitive 
complaints. In any situation where you seek to hold people accountable, the 
existence of parallel investigations can compromise the outcome. 

Our clients, therefore propose that they continue to brief you on the matter 
and that they continue to update you on the investigations, but that you hold 
your investigation in abeyance until the processes embarked upon have 
been completed." (emphases added) 

3.4.9. The Head of my Private Office responded to the Acting State Attorney on 10 
May 2013, informing him in detail of the steps that had been taken by me in 
the investigation and that to suspend it would have been tantamount to a 
breach of my constitutional and legislative responsibilities. 



101 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC PISOTCCTOf? 
SOUTH flfPICfl 

3.4.10. The proposed briefing meeting was held on 31 May 2013. It was attended by 
the Ministers of Public Works, Police, Justice and Constitutional 
Development and Defence and Military Veterans. Also present was Mr E 
Daniels, the Chief State Law Advisor, Lt Gen Ramlakan, the former Surgeon- 
General, and other high ranking officials. 



3.4.11. The Chief State Law Advisor suggested that I should stop my investigation 
until the recommendations of the internal Task Team had been implemented 
and the investigations of the Auditor-General and the Special Investigating 
Unit had been concluded. 



3.4.12. At the time of the conclusion of my investigation, no investigation had been 
conducted by the Auditor-General and the Special Investigating Unit had not 
yet been authorized to investigate the matter. In the first week of January 
2014, I was advised by the Head of the SIU, Advocate Vas Soni, SC that a 
proclamation was finally received shortly before the SIU offices closed for the 
Christmas holiday. He further advised that the terms of reference are limited 
to the conduct of officials and service providers in relation to the procurement 
of goods and services in the Nkandla Project. 



3.4.13. At a further meeting that took place on 31 May 2013 arguments were again 
advanced that it was improper of me to continue to investigate against the 
wishes of the Ministers, who were satisfied with the findings of the Task 
Team and had decided, at the recommendation of the Task Team, that the 
next phase should be investigations by the Auditor General and the SIU. The 
Chief State Law Advisor, Mr Enver Daniels supported the Ministers at the 
meeting in question, arguing at some point that "constitutionally speaking" it 
was improper for me to investigate when the Ministers had clearly decided as 
members of the Executive how they wanted the matter investigated. 



102 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




3.4.13.1 With the support of the Chief State Law Advisor and the State Attorney, the 



Minister insisted that my investigation should be suspended, (despite the fact 
that it was already well advanced at the time and my persistently making this 
point to them) pending the outcome of investigations to be initiated by the 
Auditor-General South Africa and a to-be-established Special Investigating 
Unit, which was requested by the Minister of Public Works. 



3.4.14. The impasse was eventually overcome when an agreement was reached 



with the Ministers involved at the meeting of 31 May 2013, that I would 
continue with the investigation and that they would assist with providing the 
outstanding information. The contributions of the Minister of Justice and 
Constitutional Development and the Minister of Defence and Military 
Veterans regarding my office's powers were instrumental in the 
breakthrough. 



3.5.1. On 5 November 2013, an article appeared in The Star newspaper claiming 



that information was leaked from my draft Provisional Report, which indicated 
that I had exonerated the President from all wrongdoing. The journalist 
responsible for the article later told me at a media briefing that his information 
came from two senior government officials of the security cluster. 



3.5.2. The Mail and Guardian newspaper published an extensive article on 29 



November 2013, on what purported to be "key features" of my draft 
Provisional Report learnt from undisclosed sources. This article was also 
based on 12 000 pages of documents obtained from the Minister of Public 
Works by the M&G Centre for Investigative Journalism in June 2013 by 
means of an application in terms of the Promotion of Access to Information 



3.5. 



The Alleged Leaking of Information from the Provisional Report: 



103 



Secure In Comfort A Report of the March 2014 

Public Protector 



s<"3um ill i.>k.u 



Act, 2000. All these documents, including several that are classified, were 
published on the Internet and are available at www.amabhungane.co.za. 



3.5.3. The President and Gen Cele raised concerns during the investigation 
regarding the impact of the alleged leaks of parts of my Provisional Report to 
the media. 



3.5.4. The leaking of information to the media on my investigation occurred despite 
extreme measures implemented by my office to secure the information and 
evidence obtained during the investigation. 

3.5.5. Although the alleged leaking of information from my draft Provisional Report 
may have constituted a violation of the provisions of section 7(2) of the Public 
Protector Act that provides only for disclosure if the Public Protector so 
determines, I decided not to lodge any criminal charges, as there had been a 
number of leaks involving a large part of the print media. An investigation 
would have been counter-productive and, in my view, not in the public 
interest. I stated my view in this regard publicly and indicated that forthwith 
no provisional reports will be given to parties. 



3.5.6. I was therefore surprised to receive a letter from the Minister of State 
Security on 3 December 2013 informing me of his intention to investigate the 
so called "leaks" from my draft provisional report, in terms of section 2(1 )(b) 
of the National Strategic Intelligence Act, 1994. 



3.5.7. I informed the Minister on 3 December 2013 and 12 December 2013 that he, 
in my respectful view, does not have powers in terms of the said Act, to 
initiate any investigation and that I was very uncomfortable with the fact one 
of the parties to whom my draft provisional report was presented on 1 
November 2013, was now investigating the alleged leaking thereof to the 



104 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

media. In addition, I expressed my concern that any such action by the 
Minister would have an impact on my staff assisting me in this investigation, 
who are to act without the fear of being intimidated or victimized. The Minister 
was further advised that it would be improper for me and my staff to be 
subjected to the process that he initiated as it would infringe on the 
constitutional independence of my office. 

3.5.8. The National Commissioner of the SAPS subsequently informed me in 
writing on 18 December 2013 that she had given instructions for a criminal 
investigation in terms of section 7(2) of the Public Protector Act. In my 
response dated 19 December 2013, I indicated to the National Commissioner 
that four of what purported to be Provisional Reports in respect of different 
matters unfortunately leaked to the media in the last week of November 
2013. I explained my reasoning for not laying any chargers and requested 
her to advise whether she was investigating all four instances or only the 
Nkandla matter. The National Commissioner was also referred to the 
provisions of section 6(8) of the Public Protector Act in terms of which the 
Public Protector and her/his staff are not compellable to answer any 
questions in proceedings before a court of law or any other body or 
institution, in connection with information relating to any investigation, and 
that I was not willing to be subjected and to subject any of my staff to her 
investigation. 

3.5.9. From her response, dated 24 January 2014, it was clear that the National 
Commissioner was only investigating the alleged leaking of my draft 
Provisional Report on the Nkandla Project and that she was persisting with it, 
for reasons unknown to me. I obtained legal advice and informed the 
National Commissioner on 28 January 2014 that as it is only the Public 
Protector that can make a determination of disclosure in terms of section 7(2) 
of the Public Protector Act, it is only the Public Protector that can lodge a 



105 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

complaint of a violation thereof. The National Commissioner, in my respectful 
view, does not have the powers to decide mero motu, to conduct an 
investigation into this matter where I do not wish to press any charges. Her 
investigation therefore has no legal standing and I reiterated that my staff and 
I would not be part of it. 



3.5.10. The investigations by the Minister of State Security and the National 
Commissioner of the SAPS caused discomfort among the members of the 
investigation team, who perceived it to be aimed at intimidating and 
victimizing them and me. My team and I were especially offended by 
insinuations that the leak originated from my office and that I had personally 
admitted to the leak. I was also concerned about the fact that some members 
of Parliament, charged with the duty to hold my office to account, while 
protecting it from undue attacks, joined in the unfair and unwarranted 
mudslinging. 



4. THE ISSUES CONSIDERED AND INVESTIGATED 



Based on an analysis of the complaints, the following issues were considered 
and investigated: 

4.1 . Was there any legal authority for the installation and implementation of 
security measures and the construction of buildings and other items by the 
state at the President's private residence and was such authority violated or 
exceeded? 



4.2. Was the conduct of relevant authorities in respect of the procurement of 
goods services relating to the upgrades, improper and in violation of relevant 
Supply Chain Management prescripts? 



106 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




4.3. 

4.4. 
4.5. 

4.6. 

4.7. 
4.8. 

4.9. 
4.10. 

4.11. 

4.12. 



Did the measures taken and buildings and items that were constructed and 
installed by the DPW at the President's private residence go beyond what 
was required for his security? 

Was the expenditure incurred by the state in this regard excessive or amount 
to opulence at a grand scale, as alleged? 

Did the President's family and/or relatives improperly benefit from the 
measures taken and buildings and other items constructed and installed at 
the President's private residence? 

Was there any maladministration by the public office bearers, officials and 
other parties involved in this project? 

Was there any political interference in the implementation of this project? 

Were funds transferred from other much needed DPW projects to fund this 
project? 

Is the President liable for some of the cost incurred? 

Were there ethical violations on the part of the President in respect of this 
project? 

Are there other maladministration issues that arose from the complaints and 
the investigation process? 

Are there systemic deficiencies regarding the administration of security 
benefits of Presidents, Deputy Presidents, Former Presidents and Former 
Deputy Presidents? 



107 



Secure In Comfort 



A Report of the 
Public Protector 




5. 



THE INVESTIGATION 



5.1. 



The Scope of the Investigation 



5.1.1. The investigation focused mainly on the period from the date that President 



Zuma took office on 9 May 2009 to the end of July 2013. The substantive 
scope focused on compliance with the law and prescripts in regard to 
implementation of the security measures installed and implemented and the 
propriety of the conduct of the President and others involved in the Nkandla 
Project. 



5.1 .2. Due to the lack of resources in my office, the delays in the investigation and 



the other challenges referred to in this report, it was not possible to 
investigate every allegation and suspicion of impropriety that was raised by 
different role players that were approached and engaged. 



5.1 .3. This investigation did not include accessing bank statements and telephone 



records of people with questionable relationships. Among the suspicions 
raised were favouritism in the selection of and overcharging by service 
providers contracted by the DPW and improper benefits that may have been 
provided to officials in return for the awarding of contracts. 



5.1 .4. Fortunately, the Proclamation issued by the President on 20 December 2013 



mandated the Special Investigation Unit (SIU) to investigate, inter alia, 
overpayments and duplicate payments made to the suppliers of the DPW in 
respect of the Nkandla Project and any actual or potential benefits received 
by officials of the DPW due to their interest in the awarding contracts to 
certain suppliers. 



108 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




5.1.6. 



5.2. 



5.2.1. 



5.2.1.1 



5.2.1.2 



Section 5(6)(b) of the Special Investigations and Special Tribunals Act, 1996 
provides that the Public Protector may, if she or he deems it appropriate, 
refer any matter which comes to her or his attention and which falls within the 
terms of reference of a Special Investigation Unit, to such Unit. 

I have accordingly decided to alert the SIU of the allegations and suspicions 
referred to above to the SIU to investigate further in terms of the said 
Proclamation. 

The Methodology Employed in the Investigation 

The investigation included: 
Interviews: 

Interviews were conducted with: 

Ms G Mahlangu-Nkabinde, the former Minister of Public Works (telephonic) 
on 23 August 2013; 

Deputy Minister H Bogopane-Zulu, who was the Deputy Minister of Public 
Works at times material to the investigation, on 14 May 2013; 

The following officials of the DPW that were involved in the Nkandla Project: 

(a) Ms G Pasley, the Chief Quantity Surveyor, on 21 February 2013; 

(b) Ms S Subban, Deputy Director-General, on 22 February 201 3; 



109 



A Report of the 
Public Protector 



March 2014 




(C) 

(d) 
(e) 
(f) 

(g) 

(h) 

(i) 
(j) 

(k) 
(I) 



Mr Z Rambau, the Chief Director: Security Management, on 22 
February 2013; 

Ms M Foki, the Director: Portfolio Performance and Monitoring, on 22 
February 2013; 

Mr K Khanyile, the former Regional Manager of the Durban Regional 
Office, on 27 February 2013; 

Mr J Rindel; the Project Manager, on 4 and 5 March 2013; 

Mr S Mahadeo, the original Project Manager, on 5 March 2013; 

Mr S Nadu, Assistant Director: Project Budget Administration based at 
the Durban Regional Office, on 5 March 2013; 

Mr R Danhiram, Head of Key Accounts Management and member of 
the Regional Bid Adjudication Committee, on 5 March 2013; 

Ms S Ngubane, Director: Finance and Supply Chain Management and 
Chairperson of the Regional Bid Adjudication Committee, on 6 March 
2013; 

Mr J P Crafford, the Director: Architectural Services, on 13 and 18 
March 2013; 

Ms C Motsisi, the former Chief Financial Officer, on 14 March 2013; 
Mr R Samuel, the former Deputy Director-General, on 20 March 2013; 



110 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC PEOTECTOfc 
SOUTH flfPICfl 

(n) Mr S Malebye, the former Acting Director-General, on 12 September 
2013; 

(o) Brigadier S J Adendorff, the Head of Security Advisory Service of the 
South African Police Service (SAPS), on 23 May 2013; 

(p) Mr M Makhanya of Minenhle Makhanya Architects, on 5 March 201 3; 

(q) Mr D Gqwaru and Ms. P Naidoo of R&G Consultants, on 7 March 201 3; 

(r) Mr L Uys and Ms. G Higgins of Uys and White Landscape Architects, on 
16 April 2013; 

(s) Ms P Mfeka and Mr N Mfeka of Moneymine 31 CC, on 1 5 April 201 3; 

(t) Mr Y Ramsudh and Ms. Y Patel of Ramcon Project Managers, on 15 
April 2013; and 

(u) Ms T Nene of Bonelena Construction Enterprise and Projects, on 16 
April 2013. 
5.2.2. Meetings: 

I held meetings with: 

5.2.2.1 His Excellency President J G Zuma, on 1 1 August 201 3; 

5.2.2.2 Dr R C Lubisi, the Director-General in the Presidency, in January 2012 and 
17 December 2013; 



111 




Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



5.2.2.3 The Ministers of Police, Mr N Mthethwa, Public Works, Mr T W Nxesi and 
State Security, Dr S Cwele on 22 April 2013, 31 May 2013, and 8 August 
201 3. The meeting of 31 May 201 3 was also attended by the Chief State Law 
Adviser, Mr E Daniels, and other high ranking officials of the Departments 
involved; 



5.2.2.4 The Minister of Justice and Constitutional Development, Mr J T Radebe, who 
also attended the meeting of 31 May 201 3; 



5.2.2.5 The Minister of Public Works Mr T Nxesi on 2 July 201 3; 



5.2.2.6 The Minister of Defence and Military Veterans, Ms N Mapisa-Nqakula, who 
also attended the meetings of 31 May and 8 August 2013; 

5.2.2.7 The former Surgeon-General, Lt Gen V Ramlakan and his legal team; 

5.2.2.8 Ms J Irish-Qhobosheane, the Acting Chief of Staff of the Ministry of Police; 

5.2.2.9 Gen. B Cele, the former National Commissioner of the SAPS and the legal 
team that assisted him in in his response to the evidence and information 
obtained during the investigation that appeared to implicate him, on 21 
January 2014; 



5.2.2.10 Mr M Hulley and Adv. B Makhene, the legal team that assisted the President 
in his response to the evidence and information obtained during the 
investigation that appeared to implicate him, on 21 February 2014; 



5.2.3. Analysis of documents and/or information: 



5.2.3.1 The following were analysed and perused: 



112 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



5.2.3.2 Voluminous documents obtained from the DPW, SAPS and DOD, including: 

(a) Internal Memoranda of the DPW; 

(b) Minutes of meetings of the DPW Regional Bid Adjudication Committee 
(RBAC); 

(c) Minutes of progress meetings held during the implementation of the 
Nkandla Project; 

(d) Supply Chain Management records pertaining to the procurement by 
the DPW of goods and services; 

(e) Cost estimates and Bills of Quantities prepared by R&G Consultants, 
the Quantity Surveyors appointed by the DPW for the Nkandla Project; 

(f) Records of the WCS financial system of the DPW relating to the cost of 
the Nkandla Project; 

(g) Certificates of payment by the DPW of consultants and contractors 
appointed for the Nkandla Project; 

(h) Security Evaluations Reports of the SAPS in respect of the President's 
private residence, dated 28 May 2009 and 25 September 2010; 

(i) Requirement requests presented to the DPW by the South African Air 
Force and the South African Military Health Services; 



113 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

(j) Report of the internal Task Team appointed by the Minister of Public 
Works to investigate aspects of the Nkandla Project; 

(k) An SAPS needs analysis; 

(I) Correspondence between the DPW and consultants and contractors; 

(m) Documents relating to the apportionment of costs in respect of the 
Nkandla Project; 

(n) Internal email messages of officials of the DPW and consultants and 
contractors; 

(o) Designs and site plans of the Nkandla Project; 
(p) Progress reports; 

(q) A letter addressed to the President by the former Minister of Public 
Works, Ms G Mahlangu-Nkabinde reporting progress in respect of the 
project, dated 5 November 2010; 

(r) An SAPS Information Note relating to the declaration of the President's 
private residence as a National Key Point, signed by the Minister of 
Police on 8 April 2010; 

(s) A Declaration Certificate issued by the Minister of Police on 8 April 
2010, declaring the President's Private residence a National Key Point; 

(t) Documents of the Industrial Development Corporation relating to its 
granting of financial assistance in February 201 1 to Bonelena; 

114 




Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




(u) Numerous newspaper articles published in connection with the project; 

(v) Court papers filed in the High Court litigation between Voltex (Pty) Ltd 
and Moneymine in case no: 8146/12; and 

(w) The 2009-201 4 DPW Strategic Plans. 

5.2.3.3 I also accessed the Register of Financial Interests of Members of the 
National Executive, referred to in the Executive Ethics Code, on 17 
December 2013. 

5.2.4. Correspondence 

5.2.4.1 Consideration was given to the contents of correspondence with: 

(a) The President; 

(b) The Minister of Public Works; 

(c) The Minister of Police; 

(d) High Commissioner Doidge; 

(e) The Director-General of the DPW; 

(f) The Director-General of the Presidency; 

(g) The National Commissioner of the SAPS; 

115 



Secure In Comfort 



A Report of the 
Public Protector 




5.2.5.1 
5.2.5.2 
5.2.5.3 
5.2.5.4 
5.2.5.5 
5.2.5.6 
5.2.5.7 
5.2.5.8 
5.2.5.9 
5.2.5.10 



(h) The Acting State Attorney; 

(i) The Legal General Manager of Voltex (Pty) Ltd; and 
(j) The complainants 

Legislation and other prescripts: 

The relevant provisions of the following legislation and other prescripts were 
considered and applied, where appropriate: 

The Constitution; 

The Public Protector Act 23 of 1994; 

The Executive Members' Ethics Act 82 of 1998; 

The Executive Ethics Code of 2000; 

The Public Finance Management Act 1 of 1999 (PFMA); 

Government Immovable Asset Management Act 19 of 2007 (GIAMA) 

The Protection of Information Act 84 of 1982; 

The National Key Points Act 102 of 1980 (National Key Points Act); 

The Remuneration of Public Office Bearers Act 20 of 1998; 

The Kwazulu-Natal Ingonyama Trust Act 3 of 1994; 



116 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




5.2.5.11 The Treasury Regulations and Guidelines and directives issued by the 
National Treasury; 

5.2.5.12 The Ministerial Handbook approved by the Cabinet on 7 February 2007; 

5.2.5.13 The Cabinet Policy: Security Measures at the Private Residences of the 



President, Deputy President and former Presidents and Deputy Presidents, 
approved on 20 August 2003; 



5.2.5.14 The South African Defence Review of 1998 (the Defence Review); 

5.2.5.15 The Minimum Information Security Standards (the MISS); 

5.2.5.16 The Minimum Physical Security Standards; and 

5.2.5.1 7 The Supply Chain Management Policy of the DPW adopted on 29 April 2008. 
5.2.6. Submissions: 



I received submissions in terms of section 7(9) of the Public Protector Act on 
the evidence and information obtained during the investigation that appear to 
implicate several parties, from: 



5.2.6.1 The President; 

5.2.6.2 The Minister of Police; 

5.2.6.3 The Minister of Public Service and Administration (who was the former 



Minister of Defence); 



117 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



5.2.6.4 Deputy Minister Bogopane-Zulu; 

5.2.6.5 Gen. B Cele, a former National Commissioner of the SAPS; 

5.2.6.6 Mr S Malebye, a former Acting Director-General of the DPW; 

5.2.6.7 Maj.-Gen. T Kulu, the former Head: Government Security Regulator of the 
SAPS; 

5.2.6.8 Lt. Gen. V Ramlakan, the former Surgeon-General; 

5.2.6.9 Brigadier S J Adendorff, the Section Head: Security Advisory Service of the 
SAPS; 

5.2.6.10 Mr J Rindel of the DPW Durban Regional Office, who was the DPW Project 
Manager of the Nkandla Project from January 2010; and 

5.2.6.11 Mr B K Khanyile, who was the Regional Manager of the DPW Durban 
Regional OFFICE at times material to the implementation of the Nkandla 
Project. 

5.2.7. Jurisprudence and Touch Stones from previous Public Protector Reports: 

5.2.7.1 On the issue of balancing state security considerations and open democracy 
and public accountability imperatives, I also considered and applied the 
judgment of the Constitutional Court in the case of Independent Newspapers 
(Pty) Ltd v Minister for Intelligence Services; Freedom of Expression Institute 
In re: Masetlha v President of the Republic of South Africa and Another 
(2008(8) BCLR 771 [CC]). 



118 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



5.2.7.2 Touch stones or principles from previous Public Protector Reports were also 
considered. In this regard, principles regarding different responsibilities and 
processes in a valid supply chain process discussed in reports such as 
Against the Rules and Against the Rules Too, On the Point of Tenders, and 
Yes We Made Mistakes were considered during the assessment of the 
propriety of the conduct of various actors during various stages of the 
process of procuring goods and services in relation to the Nkandla Project. 
Principles relating to ethical standards developed in the Public Protector 
Report titled "The Ethics of Staying in Comfort" were used a part of the 
benchmarks when the ethical questions were dealt with. 

5.2.7.3 I also considered precedents relating to findings on excesses in the use of 
executive privileges made in the Public Protector reports titled "Costly 
Moves" and "In the Extreme". 

5.2.7 .4 In the case of my investigation into extravagant expenditure by the Minister of 
Police on hotel accommodation (Report no 7 of 2011/12), I found that the 
Minister, when he became aware of the extent of the expenditure, took steps 
to contain it and to prevent a recurrence thereof. 

5.2.8. Inspection in loco: 

5.2.8.1 I visited the President's private residence and the adjacent premises of the 
Nkandla Project to conduct an inspection in loco, on 12 August 2013. During 
the visit, I was accompanied by a member of my investigation team, the 
Minister of Defence and Military Veterans, Lt. Gen. Ramlakan and officials of 
the State Security Agency, the DPW, the SAPS and the DOD. 



119 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




5.2.9. Challenges resulting in a delay in finalising the investigation 

5.2.9.1 Earlier on I indicated that the President has complained about the delay in 



concluding the investigation. He also submitted that his duty to account under 
the Executive Members' Ethics Act, including informing Parliament on how he 
has dealt with my findings, has lapsed due to such delay. The African 
National Congress, which is the governing party in this country, has 
periodically insinuated that I was delaying the release of the report to ensure 
that I release it close to and in order to influence the 2014 National and 
Provincial elections. Such insinuations have not only been untruthful, but 
hurtful to my team and I, while having the potential to erode the credibility of 
my office and my professional integrity. 



5.2.9.2 The reality is that the Presidency was part of the problem as were other 



organs of state regarding the delays. My team and I sat in silence when 
organs of state that had requested extension after extension to submit 
submissions in response to my Provisional Report said nothing when insults 
were hurled at my office by their colleagues or supporters in Parliament and 
civil society for allegedly sitting on the report in pursuit of a political agenda. 
The Presidency repeated the concerns in its final submissions despite having 
taken a cumulative period of 9 months to supply requested information. 



5.2.9.3 In fact, despite capacity constraints, the report should have been issued by 
the end of April 2013, if it were not for delays on the part of the state, 
including the Presidency. 

5.2.9.4 The investigation process was hampered by a number of challenges, some 
of which were alluded to above. Notable among the hurdles already alluded 
to are the shenanigans of the security cluster as the investigation 



120 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

approached finalisation in the first quarter of 2013. Other hurdles that 
militated against the speedy finalisation of the investigation are the following: 

(a) Resources: 

(i) Due to a lack of resources, the assistance that could be provided to me 
to investigate the issues identified from the complaints that related to a 
procurement project on the magnitude of more than R200 million, was 
confined to a small investigation team operating on a part time basis 
while handling other investigations. For a brief period of approximately 
three months, an accountant from an audit firm assisted with the 
investigation but could not be retained for a longer period due to 
financial constraints. If we compare the resources given by government 
to Commissions of Inquiries, it must be noted that the budget we are 
expected to deploy towards these investigations, is hopelessly 
unrealistic. For example, the budget of the commission currently 
investigating the so-called arms deal is R42 million. 

(b) Access to classified documents: 

(i) The fact that the investigation pertained to security measures that were 
taken in respect of the President presented a major challenge. Some of 
the information that had to be considered is classified and sensitive. It 
was sometimes problematic to gain access to relevant documents and 
information for the purposes of considering and evaluating the veracity 
of the allegations made in respect of the Nkandla Project. 

(ii) Gaining access to the report of the internal Task Team appointed by the 
Minister of Public Works that investigated certain allegations relating to 
the Nkandla Project was a mission. After the Minister of Public Works 



121 



A Report of the 
Public Protector 



March 2014 




(iii) 

(iv) 

(C) 
(i) 



issued a statement to the media on the findings of the report, I 
requested to be provided with a copy thereof, on 24 January 2013. 
Several further requests had to be made in this regard. I was only 
allowed access to the report of the Task Team on 2 July 201 3. 

Despite my several requests, I was not furnished with a copy, but only 
allowed to peruse the contents thereof, after which it had to be returned 
to the officials of the Ministry of Public Works and the Department of 
State Security, due to the fact that it was classified. 

A copy of the report has since been secured from the internet following 
the declassification and public release of the report by the Minister of 
Public Works in mid-December 201 3. 

General delays experienced in obtaining information: 

The investigation was further hampered by delays experienced in 
obtaining information from the relevant departments and Ministries. The 
Presidency also took some time to respond to some of the document 
and information requests. For example, my request to the Director- 
General of the Presidency for information relating to the involvement of 
the Presidency in the Nkandla Project and the application of the 
Ministerial Handbook, which was addressed to him on 26 August 2013 
only got an answer telephonically and from a meeting held in mid- 
December 2013. He apologized and advised that he had not received 
the correspondence in question. My request to him in his capacity as 
the Cabinet Secretary, for access to the Register of Financial Interests 
referred to in the Executive Ethics Code to enable me to verify some of 
the information that relates to my investigation, also suffered the same 
fate. However, I did finally get access in December 2013. 



122 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



(ii) When I got an opportunity to enquire from Dr Lubisi about the lack of 
response from his office on 31 October 2013, he explained that all 
enquiries to the Presidency in respect of my investigation were referred 
to the legal advisors. On 31 January 2014, he advised that the 
information that I requested in respect of the interaction between the 
Presidency and Deputy Minister Bogopane-Zulu would be responded to 
by the President. However, I never received any such response from 
the President. 

(iii) The table below is an indication of some of the other delays that 
impacted on the investigation, excluding delays due to the litigation on 
security concerns and extensions requested for responses to the 
Provisional Report.: 











Uhhllt BbAKbK UK 
OFFICIAL APPROACHED 


REQUEST FOR 
INFORMATION 


The President 


29/01/2013 


01/10/2013 


9 months 


DG: Public Works 


15/02/2013 


19/03/2013 


32 days 


Minister of Police 


11/02/2013 


22/03/2013 


41 days 


Lt Gen V Ramlakan 


06/03/2013 


31/07/2013 


4 months 


DG: Public Works 


04/04/2013 


26/08/2013 


4 months 



Figure 1: Breakdown of Delays in Respect of the Investigation 



(iv) The urgent High Court application by the Ministers of Public Works, 
Police, Defence and Military Veterans and State Security: 

(a) On 1 November 2013, I provided the Minister of Public Works and the 
Ministers of the Security Cluster with password protected electronic 
copies of my draft provisional report on the investigation. This was in 
terms of an understanding between us that they would be provided with 



123 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




an opportunity to raise any issue that might, in their view, compromise 
the security of the President, if contained in my final report to be made 
public. I requested them to provide me with their response by 6 
November 2013 and later extended the date to 8 November 2013, at 
the request of the Minister of Public Works. 

(b) However, the Minister of Public Works sent a letter to my office on 7 
November 2013 insisting that a further extension be granted to 15 
November 2013. He further demanded that I respond within two hours. 
At the time I was not in Pretoria and could not be reached by my office. 
Before I could further engage with the Ministers on the request, court 
papers in respect of an urgent application brought against me by the 
Ministers of Public Works, Police, State Security and Defence and 
Military Veterans in the North Gauteng High Court, were served on my 
office at approximately 09:00 on 8 November 2013. The relief that the 
Ministers requested from the High Court was that I should be interdicted 
from releasing my provisional report to other affected, implicated and 
interested parties, that a further extension should be granted to the 
Ministers to respond to the security issues in the draft provisional report 
that I presented to them and that once they have submitted their 
comments my provisional report should be revised accordingly and 
resubmitted to them for their approval that I had dealt with such issues 
to their satisfaction. 

(c) I had no option but to oppose the application to protect the constitutional 
independence and integrity of the institution of the Public Protector and 
briefed attorneys and counsel accordingly. After the filing of opposing 
and replying affidavits, the Ministers withdrew the application on the 
date of the hearing, i.e. 15 November 2013, tendering the legal costs 
that the Public Protector SA had to incur, which amounted to more than 



124 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




R600 000, excluding the legal costs incurred by the Ministers. This 
excessive expenditure could have been avoided had the Ministers acted 
reasonably and engaged me personally on the matter instead of 
resorting to court action. 

(d) The court action by the Ministers also caused a further delay in the 
conclusion of the matter as the investigation team had to focus all its 
attention to it, instead of expediting the conclusion of the investigation. 



5.2.10. Extension of time lines for Submissions in Response to the Provisional 



(e) I received numerous requests for extensions of timelines within which 
responses, information and evidence were requested from the affected 
parties. A number of them were represented by multiple legal teams 
who adopted an adversarial approach to my proceedings and their 
unavailability to respond to expeditiously, compounded the delays. 



(f) The investigation has had an unprecedented number of threats to 
litigate right up to the eve of the release of the report. Many of these 
threats involved an intention to prevent the publication of the report. The 
security cluster minister litigation saga incorporated a threat to litigate to 
prevent the publication of the report if the Ministers were not happy with 
the final look of the report regarding what they regarded as security 
concerns. Most of these, turned out, by the admission of the Task Team 
assigned to work with my team to assess the report in question, to be 
concerns unrelated to security. 



Report 



5.2.1 1 . Litigation and Threatened Litigation 



125 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

(g) Threats to interdict the issuing of the report were made, inter alia, by 
former Commissioner of Police, General Bheki Cele, High 
Commissioner Doidge and Mr Makhanya. The latter made an 
unprecedented demand that his name be excised from the report as he 
does not work for the state and the investigation, in line with "the Public 
Protector's mandate" being confined to state affairs. Of course it was 
pointed out to the lawyer assisting Mr Makhanya that "state affairs" 
include the acts of private actors involved in state operations. It was 
pointed out in his case that he acted as Principal Agent for the DPW, in 
addition to acting as a private architect and the Principal Agent of 
President Zuma, as a private citizen. Reference to jurisprudence from 
the Public Protector South Africa v Mail & Guardian Ltd & Others (201 1 
(4) SA 420 SCA) court case regarding a PETRO SA investigation by my 
office did not seem to assist. The jurisprudence in question enjoins the 
Public Protector to follow the state's money, amongst other things. 

(h) Some of the threats were founded on a mistaken belief that parties are 
entitled to a provisional report and to be given ample time. Some 
required periods in excess of a month, to scrutinise such report. All 
efforts were made to accommodate access to information needs and to 
create further opportunities for engagement, which inevitably caused 
further delays. Efforts were also made to accommodate those who felt 
being asked to respond in writing was not enough. 



126 



Secure In Comfort 



A Report of the 
Public Protector 




6. 



THE EVIDENCE AND INFORMATION OBTAINED DURING THE 



INVESTIGATION 



PART A: EVIDENCE ON THE SEQUENCE OF EVENTS 



6.1. 



The Area of Nkandla: 



6.1.1. President Zuma was born and raised in the Nkandla area and always 



regarded it as his home. His private residence is located on traditional land 
leased from the Ngonyama Trust in a rural village approximately 47 km from 
Eshowe Town. 



6.1 .2. According to the 201 1 Census Report, the Nkandla Municipal area has a 



population of 114 416. About forty per cent (43.9%) of the population 
between the ages of 15 and 64 are unemployed. Only approximately 10 000 
households in the area have access to electricity and more than 7000 have 
no access to piped water. Almost 12 000 households are still using pit 
latrines. 



6.1 .3. The SAPS has a satellite Police Station in the Nkandla area that is managed 
by the SAPS in Eshowe. 

6.1 .4. According to the records of the KwaZulu-Natal Provincial Department of 
Health, there are two district hospitals in the Nkandla area, namely the 
Nkandla Hospital, with a bed capacity of 212 and the Ekombe Hospital. 

6.1 .5. According to a report of the KwaZulu Natal Department of Health issued on 6 



November 2013, the Nkandla area remains one of the most underserved in 
terms of the provision of health services, and greater effort is required for the 
improvement of service delivery to the community at large. The response 



127 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




time for ambulance services, for example, is way below the norm, and this is 
compounded by the fact that there are no advanced life support personnel in 
the area. 



6.1 .6. These harsh conditions were advanced as the basis for the unprecedented 



installations in the name of security at the President's private residence. I will 
later allude extensively to the questions I raised with the state actors involved 
regarding whether or not an approach that is more in line with the role of 
public office bearers regarding putting citizens first, was one that provided for 
both the first citizen, and the caretakers. This was particularly so as there 
were complaints about the paucity of health facilities such as equipped 
hospitals, ambulances and adequately resourced police stations. 



6.2.1 . President Zuma assumed office on 9 May 2009 as the fourth President of the 



Republic of South Africa, since the dawn of democracy, following national 
elections in April the same year. He had been the Deputy President of the 
republic previously and subject to the same regulatory framework for security 
measures for Presidents, Deputy Presidents, Former Presidents and Former 
Deputy Presidents. 



6.2.2. It was established from the evidence of Mr Rindel, the DPW Regional 
Manager and Brigadier Adendorff, the Section Head: Security Advisory 
Service that: 

6.2.2.1 At the time when Mr Zuma took office as the President of the Republic of 
South Africa, his private residence at Nkandla in the KwaZulu-Natal Province 
consisted of seven relatively small buildings, commonly referred to as 



6.2. 



The Events prior to the Nkandla Project 



128 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




rondavels, and a kraal for farm animals. There was also a small tuck shop 
and a guard hut. 



6.2.2.2 The ablution facilities were connected to a french drain system and there was 
limited water and electricity supply. 

6.2.2.3 The perimeter fencing on the property consisted of a steel palisade fence, 
which was of poor quality. 



6.3.1 . According to a letter addressed to me by the Minister of Public Works dated 



05 December 2012 and the evidence of Mr Malebye, the then Acting 
Director-General and Mr Rambau, the Security Manager of the DPW, Messrs 
Malebye and Rambau visited the President's private residence on 19 May 
2009 to make general observations on what was required in terms of a 
security upgrade of the premises, to ensure adequate protection of the 
President and his immediate family. 



6.3.2. The professional services team of the Durban Regional Office of the DPW 



(the Regional Office) was briefed on the observations made. This team, 
consisting of an architect, quantity surveyor, civil, structural, mechanical and 
electrical engineers then visited the site on 21 May 2009 to conduct a more 
detailed scoping exercise on the immediate security measures that had to be 
taken. 



6.3. 



The First Steps Taken to Initiate the Upgrading of the Security at the 



President's Private Residence 



129 



Secure In Comfort 



A Report of the 
Public Protector 




6.4. 



The Initial Requirements of the DOD and the SAPS 



6.4.1. The Office of the Surgeon-General of the DOD prepared a list of its 



requirements in respect of a health facility for the President and his 
immediate family, as well as staff accommodation, offices and associated 
space required at the President's private residence, amounting to floor space 
of 239m 2 . These requirements were contained in a document entitled: 
"MILITARY HEALTH SUPPORT TO THE PRESIDENT" which was submitted 
to the Acting Director-General of the DPW, in a letter addressed to him on 22 
May 2009. Mr J Rindel indicated during the investigation that this document 
was never provided to him. 



6.4.2. Representatives of the SAPS, led by Brigadier Adendorff, visited the site of 



the President's private residence on 28 May 2009 and conducted a security 
evaluation in respect of the premises (as it was at the time), which was 
recorded in a Security Evaluation Report and presented to the DPW Regional 
Office for implementation of the proposed security measures. 



6.5.1 . According to the evidence of Mr K Khanyile, former Regional Manager of the 
DPW Regional Office and Mr Rindel, Mr Malebye, visited the Regional Office 
again in July 2009, to officially introduce the Nkandla Project to the officials 
that would be involved. 

6.5.2. The Head of Projects in the Regional Office then appointed Mr S Mahadeo 



as the Project Manager of the Nkandla Project, in August 2009. The latter 
indicated in his evidence during the investigation that although the project 
was registered in the Region, it was primarily driven from the DPW Head 
Office. 



6.5. 



Getting the Project Started 



130 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.5.3. On 4 August 2009, an inter-departmental meeting in connection with the 



Nkandla Project was held at the Regional Office, where the additional 
requirements of the South African Medical Health Services (SAMHS) were 
discussed. These additional requirements, as per the discussions held at the 
meeting, were confirmed in writing in a letter from the former Surgeon 
General, Lt Gen V Ramlakan addressed to the Acting Director of DPW on 7 
August 2009, and related mainly to staff accommodation, including parking. 



6.5.4. The Officer Commanding of the South African Air Force Base in Durban 



submitted its requirements in respect of the safe landing of helicopters at the 
President's private residence in a letter to the DPW, dated 5 August 2009, 
which included the removal of obstructions and the provision of crew facilities 
for adequate rest, relaxation and nutrition, to comply with international safety 
regulations. 



6.5.5. According to the former Chief Financial Officer, Ms Motsisi and Mr Khanyile 



of the DPW interviewed during the investigation, the DPWs internal 

arrangements provided that funding for the installation of the security 

measures had to be approved by the Planned Maintenance Budget 
Committee of the DPW (PMBC). 



6.5.6. On 6 August 2009, the Director: PPM: Prestige of the DPW submitted an 
Internal Memorandum to the Chairperson of the PMBC, requesting approval 
of the amount of R27 893 067 for the Nkandla Project. This request was 
approved. 

6.5.7. Ms S Subban, the then Acting Deputy Director-General of the DPW and a 
member of the PMBC, made the following comment on the approval 
document, on 7 August 2009: 



131 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



"Due to urgent nature of service -service must be proceed (sic) and funds will 
be made available periodically, as and when savings materialize from 
prestige/DPW budget. " 

6.5.8. According to the evidence of Mr M Makhanya, who was the architect 
appointed by the President in his private capacity for the design of the three 
new houses on the premises and who was later appointed as the Principal 
Agent of the Nkandla Project by the DPW, the DPW and the SAPS held a 
meeting on site with the President, on 12 August 2009. 

6.5.9. The purpose of this meeting was to inform the President of the security 
measures that would be installed at his three new dwellings. It was also 
attended by the then Minister of Public Works, Mr G Doidge. 

6.5.10. On 18 August 2009, Ms Subban issued a Procurement Instruction to the 
Regional Manager stating, inter alia, the following: 

"In order to comply with the provisions of the Ministerial Handbook, the 
Department of Public Works has the responsibility of providing security 
measures at the residential accommodation of all members of the Executive 
of the Government of South Africa. 

In giving effect to this responsibility, a project was initiated to provide security 
measures at the private residence of the newly elected President of South 
Africa, in Inkandla, district of Eshowe, Kwazulu Natal. 

In consultation with SAPS, SANDF and NIA, the Professional Services 
component of the Durban Regional office compiled a draft scope of works 
and cost estimate for the provision of the security measures, based upon 



132 



Secure In Comfort 



A Report of the 
Public Protector 




which approval was obtained from the Planned Maintenance Bid Committee 
(sic) to implement the execution of the service. 

You are requested to procure the services of suitably qualified specialist 
service providers to do the planning, design and construction of the project in 
compliance with the reguirements of the SAPS, SANDF and NIA. 

The estimated cost of the project amounts to R27 893 067.00 inclusive of 
VAT, for construction costs and professional fees, for anticipated expenditure 
during the current (2009/10) financial year. 

Funding for this project will be made available from the Capital Works 
Baseline allocation of the Department of Public Works." (emphases added) 



6.5.11. Mr Makhanya indicated during the investigation that a meeting was held at 



the DPW Regional Office on 20 August 2009 in Durban, attended by all the 
key role players in the Nkandla Project. Minenhle Makhanya Architects was 
requested to make a presentation on the design of the three new houses. 
The discussion related to the synchronizing of the DPW project with the 
private construction. 



6.5.12. Mr Makhanya confirmed during the investigation that the construction of the 
President's three new private dwellings commenced on 24 August 2009. 



6.6.1. Several of the DPW officials interviewed during the investigation stated that 
Mr Malebye advised in September 2009 that the President preferred that the 
team of people already employed on the site, should be appointed for the 
Nkandla Project. He accordingly instructed the Regional Office to appoint the 



6.6. 



The Appointment of Consultants for the Project 



133 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



consultants and contractor appointed by the President for the construction of 
the three private residences, for the DPW project. I could however find no 
reference to this request by Mr Malebye in the documents perused during the 
investigation. 

6.6.2. The Nkandla Project was to be implemented in three phases: 

6.6.2.2 The First Phase was the emergency works, which consisted mainly of the 
most essential items that had to be installed in order to ensure a minimum 
level of security; 

6.6.2.3 The Second and Third Phases were regarded as low security, but necessary 
for the safe keeping of the President and his family. 



6.6.3. On 4 September 2009, the Acting Director: Projects of the Durban Regional 
Office of the DPW submitted an Internal Memorandum to the Regional Bid 
Adjudication Committee (RBAC) requesting approval for the appointment of 
Minenhle Makhanya Architects and R&G Consultants (quantity surveyors) for 
professional assistance in the Nkandla Project. The motivation for the 
request was as follows: 



"The instructed scope of works must be integrated with the future building 
plans of the owner of the property. The future plans include substantial 
changes. The changes are currently in design by the following consulting 
team as appointed by the owner: 

• Architect: Minenhle Makhanya Architects 

• Quantity Surveyor: R&G Consultants 

• Engineers. 



134 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




The security measures that the Department will be responsible for will be 
designed in-house (Departmental project team). This is in line with verbal 
instructions from the Acting DG in order to ensure better security-and cost 
control over this project. 

The appointment of the architect and quantity surveyor is however essential 
in order to ensure complete integration between the two design 
teams."(emphasis added) 



6.6.4. The Minutes of the RBAC show that it approved the appointment of Minenhle 
Makhanya Architects and R&G Consultants on 8 September 2009, in the 
estimated amounts of R415 440 and R415 440, respectively. 

6.6.5. On 10 September 2009, the Acting Director: Projects of the DPW 



approached Mr Malebye, via the then Acting Regional Manager, with an 
Internal Memorandum requesting his approval for the appointment of 
professional consultants to design, provide tender documents and supervise 
the construction of relevant support buildings and the installation of security 
measures at the Nkandla Project. Added to the list of private consultants that 
was approved by the RBAC, referred to above, was the name of Ibhongo 
Consulting Engineers. 



6.6.6. It was again emphasized that the President had appointed the consultants in 
his private capacity, more than two years earlier. The Internal Memorandum 
further stated that: 



"It is essential that the same professionals be appointed for this project for 
the following reasons: 



135 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



The appointment of the team is essential in order to ensure complete 
integration between the two separate projects (installation of security 
measures and owner's own upgrading project). 
It is not advisable to utilize the Departmental Professionals, as they do 
not carry professional indemnity. 

This is a fast track project and it is essential that one team work on all 
aspects of the project.' '(emphasis added) 



6.6.7. Mr Malebye approved the request on the same day (10 September 2009). 

The estimated cost of the professional fees was calculated at 18.5% of the 
estimated cost of the Nkandla Project (R27 million at the time) and amounted 
to R4 995 000. 

6.7. Approval of Parts of the Concept Design 

6.7.2. Correspondence between Lt. Gen. Ramlakan and the Chief Architect of the 
DPW Professional Services dated 16 September 2009, indicate that they met 
on 22 September 2009 to discuss the concept design of aspects of the 
Nkandla Project. The Lt. Gen. Ramlakan approved the drawings of the 
military clinic, subject to further requirements. A copy of the drawings 
indicates that he also approved other designs relating to the crew pavilion for 
helicopter pilots, the safe haven and communication systems, subject to 
further additions. 

6.8. First Cost Estimate and List of Contractors Prepared by R & G 
Consultants 

6.8.2. According to Mr Makhanya, it became obvious soon after his appointment 
that the DPW did not take into account the full scope of the security 



136 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



requirements of the SAPS in its initial evaluation of what needed to be done. 
These requirements were also still in a process of further development. The 
final details thereof were not available at that stage. 



6.8.3. On the basis of the information in respect of the security and medical care 
requirements that were submitted to the DPW by the DOD and the SAPS by 
September 2009, R&G Consultants prepared a detailed cost estimation 
document in respect of the Nkandla Project, which concluded that the 
estimated cost would amount to R47 323 102. This document was addressed 
to the Acting Director-General, who was Mr Malebye. 

6.9. The Delegation of Authority to the RBAC and the Selection of 
Contractors 

6.9.2. A Procurement Certificate for the Nkandla Project was signed by several 
officials of the Regional Office of the DPW on 5 and 6 October 2009. 

6.9.3. Mr Danhiram, the Deputy Director: Key Account Management noted on the 
document that "No norms have been received". During the investigation, he 
explained in this regard that the Procurement Certificate was the start of the 
procurement process when the estimates based on the norms submitted by 
the client department are determined before a tender process commenced. 
In this case there were no such norms provided. 

6.9.4. Mr Mahadeo, the Project Manager at the time, certified on the document that 
the project as designed and documented was within the approved space and 
cost norms. On his part Mr Nadu, the Assistant Director: Key Account 
Management noted that the necessity of the project had been confirmed and 
that funds were available. 



137 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

6.9.5. The Quantity Surveyors appointed by the DPW for the Nkandla Project, R&G 
Consultants, presented a list of proposed contractors to Mr Mahadeo by 
email on 8 October 2009. R&G Consultants explained the basis for the 
selection of the contractors as follows: 

"Further to our meeting of even date and acting on instruction from the 
Principal Agent (Minenhle Makhanya Architects), we submit a list of proposed 
contractors who are to be invited to tender on this project. Please note as 
indicated at yesterday's meeting with the Minister and Director-General of 
Public Works at Tshwane, the basis of our nomination is that: 

1. These contractors are registered with the CIDB and most of them have 
the necessary grading 6GB PE. 

2. They are currently doing in (sic) the area and therefore understand the 
local communities. 



3. We, as a professional team, have screened them, and we are satisfied 
that they can deliver the goods." (emphases added) 

6.9.6. On 9 October 2009, Mr Khanyile, the former Regional Manager of the DPW 
Regional Office, submitted a request by means of an Internal Memorandum 
to Mr Malebye, to approve a delegation that would allow the RBAC to 
approve a procurement strategy to the value of more than R20 million. It was 
stated in the Internal Memorandum that: 

" The DG held a meeting with the project team, including the PM (Project 
Manager) on 5 October 2009. In the meeting it was confirmed that: 



138 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

• The nominated procedure will be utilized. Contractors in larger northern 
KZN should be targeted in order to benefit from the works. 

• The private QS identify firms for general building, civil engineering 
works and electrical installations. This would be utilized for a nominated 
procedure. 

• The RBAC must approve the procurement strategy above R 20 
000,000.00. 

In order for the RBAC to complete its mandate, the following delegations is 
(sic) requested to be given to the committee specifically for this project in lieu 
of the standard delegations: 

The required delegations are as follows: 

1. The responsibility of selecting contractors vests with SCM in the 
regional office. It is requested that DG confirms that this office may 
deviate from this responsibility in that the list as provided by the private 
QS may be used. 



2. The RBAC currently only has the delegation to approve any 
procurement strategy or tender below a limit of R20 OOO OOO.OO. It is 
requested that for this project only this delegation should be 
increased to above R 20 OOO OOO. 



This will result in this office gaining complete control over the 
procurement process and that any communication with the SNBAC 
(Special National Bid Adjudication Committee) will not delay the project. 

If this request is denied, the RBAC will still forward the procurement 
strategy to the SNBAC by 9 October 2009, but no guarantee can be 
given on the expected date of approval." 



139 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



3. The list of names for the nominated tender for NIA clearance had been 
forwarded to HO for assistance in fast tracking." (emphases added) 

6.9.7. Mr Khanyile explained during the investigation that he requested the 
delegation because Mr Malebye impressed upon him that the Nkandla 
Project had to be fast tracked. He advised that he also knew from experience 
that to have involved the SNBAC could have delayed implementation. 

6.9.8. On the basis of this Internal Memorandum, Mr Malebye approved the 
following recommendations on 9 October 2009: 

" 1. The list as provided by the private QS be regarded as acceptable (only 
CIDB registered contractors); 

2. The delegation to approve the procurement strategy above R 20 000 
000. 

3. Head of Security Services assist in fast tracking the NIA clearance on 
the nominated contractors." 

6.1 0. The Accommodation Needs Submitted by the SAPS 

6.10.2. According to the records of the DPW and a response to my enquiries by the 
Minister of Public Works, dated 5 December 2012, the DPW and the SAPS 
Divisions: Supply Chain Management and Protection and Security Service 
met in connection with the Nkandla Project on 12 October 2009. On 15 
October 2009, the SAPS Divisional Commissioner: Supply Chain 
Management submitted to the Acting Director-General of the DPW "a 



140 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




certified needs assessment for accommodation to be constructed at the 



residence of State President (sic) Zuma as well as applicable specifications. " 

6.1 0.3. According to the certified needs assessment of the SAPS, it required: 

6.1 0.3.1 1 three bedroom park home as interim accommodation 

6.10.3.2 2 offices 

6.10.3.3 2 guard houses 

6.10.3.4 1 control room 

6.10.3.5 8 bachelor flats 

6.1 0.3.6 1 3 lock up garages; and 

6.10.3.7 8 car ports. 

6.10.4. The total estimated cost of the certified needs assessment of the SAPS 
amounted to R1 1 405 004.47. 

6.10.5. However, on 23 October 2009, SAPS Divisional Commissioner: Supply 



Chain Management informed the Director-General of the DPW in writing that: 

" By instruction of the State President, President Zuma the existing house at 
Nkandla currently accommodates SAPS members, (sic) must be converted 
as part of the President's household. 



141 



Secure In Comfort A Report of the March 2014 

Public Protector 



v ■mi ill :.■!> n 



To cater for the needs of the members currently accommodated in the house 
as referred to above, additional bachelor flats need to be added to the needs 
assessment previously provided to your department.' '(emphasis added) 



6.10.6. The attached certified needs assessments almost doubled the number of 
required bachelor flats, lock up garages and car ports. The cost estimate for 
the revised needs assessment concomitantly increased to R13 260 827.63. 

6.10.7. According to the evidence of Mr Khanyile, there was a need for 
accommodation of the staff of the SAPS and the DOD looking after the safety 
of the President as the nearest town, Eshowe, is about 47 km from the site 
and no other accommodation was available for them in the area. 

6.1 1 . Procurement Strategies Approved by RBAC 

6.11.2. The Minutes of the RBAC meetings indicate that during October 2009 it 
approved procurement strategies in respect of nominated procurement 
procedures for electrical works, engineering and construction for the Nkandla 
Project. 

6.12. Project Manager Replaced 

6.12.2. It was explained in the evidence of officials of the DPW Regional Office that 
due to operational changes that occurred in the Regional Office of the DPW, 
the original Project Manager, Mr Mahadeo, was replaced by Mr J Rindel, in 
January 2010. Mr Rindel testified during the investigation that when he 
visited the Nkandla Project site towards the end of January 2010, he 
discovered that the construction of the President's three private residences 
was well advanced. Due to the fact that the three new residences were not 



142 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




taken into account when the original security audit was conducted by the 
SAPS, an updated security evaluation was required. 



6.1 2.3. Mr Rindel was of the view that the scale of the proposed project was too big 



for the Regional Office to handle on its own. The Regional Office does not 
have a Prestige Unit dealing with projects under the Prestige Programme of 
the DPW and has no policy or specific delegations from the DPW Head 
Office on how to handle such a project. 



6.12.4. At the time that he took over as the Project Manager, the Nkandla Project 



was progressing slowly. Meetings with the consultants were only held every 
two to three weeks. After the former Acting Director-General, Mr Malebye, left 
the DPW at the end of March 2010, little guidance was provided to the DPW 
Regional Office. The implementation of the project was accelerated when 
Minister Doidge became personally involved and regular progress meetings 
were held. 



6.12.5. It was confirmed by Mr Rindel that the Nkandla Project comprised three 



phases. Phase 1 consisted of the so called "emergency works" and was to 
include a perimeter fence, access control buildings, all the infrastructure 
upgrades for water, sewerage and electricity and the relocation of the tuck 
shop. Space also had to be made for the two helipads. 



6.1 3. The Second Cost Estimate 

6.13.1. The second cost estimate prepared by R&G Consultants in February 2010, 



shows that by that time they were provided with more detailed information on 
the scope of works. The increase in staff accommodation, the helicopter crew 
pavilion that was required as well as the increase in the size of the safe 
haven and the bulk earth works caused the estimated costs of the Nkandla 



143 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



Project to increase from R47 323 1 02 to R80 836 249. The cost estimate was 
also prepared for and addressed to the Acting Director-General, who was Mr 
Malebye at the time. 



6.14. The First Progress Meeting 

6.14.1. The first Progress Meeting, in respect of which minutes were found during 
the investigation, was held on 15 February 2010. It was chaired by Mr 
Khanyile. 

6.14.2. It was, inter alia, reported that Mr Rindel had made certain observations 
about the security on the site during construction and concluded that due to 
the fact that the construction of the private dwellings was well advanced, the 
DPW had to expedite the implementation of security measures. 

6.15. The Nominated Procurement Strategy for the Appointment of 
Contractors for the Emergency Works 

6.15.1. On 1 March 2010, Mr Rindel approached the RBAC with an Internal 
Memorandum requesting the approval of a nominated procurement strategy 
in respect of contractors for the emergency works that had to be performed 
as part of the Nkandla Project. He motivated his request for the approval of 
the nominated procurement strategy as follows: 

" The use of the nominated process is the process that will achieve the most 
speedy results when compared to other SCM processes. This is proven as 
follows: 

• Open process - This cannot be concluded, as the secret information 
cannot be advertised openly. 



144 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

• P 're-qualification process - The process is expected to take up to 4 
months, including the NIA clearance and screening processes. This is 
much too long. 

• Quotation process - same as Open process. 

• Nominated process - This process empowers the State to select 
contractors that had previously been NIA screened and approved, thus 
allowing this office to immediately provide the approved contractors with 
tender documents. It is thus proven that this be the preferred and 
fastest method to procure the works. 



The proposed nominated strategy shall be based on the following basis: 

• Nominations were previously done for contractors nominated by the 
Private Architect as instructed by the then acting DG, Mr S Malebye. 
The contractors were nominated from northern KZN for the works to be 
concluded. This strategy was thereafter changed to a pre -qualification 
process. 

• The profiles/details of the nominated contractors were handed over to 
NIA for screening purposes. This was concluded and the Department is 
in possession of the results. 

• The criteria for the nomination of the contractors are as follows: 

• The contractors must have passed the required NIA clearance. 

• The contractors must be registered at the minimum CIDB grading, being 
7GB, ICE or 6 GBPE, 6 CEPE or higher. " 



6.15.2. According to Mr Rindel's memorandum, the following contractors qualified in 
terms of the requirements of the nomination process and were recommended 
for appointment: 



145 



Secure In Comfort A Report of the 

Public Protector 



6.1 5.2.1 Gwabini Development Contractors. 

6.1 5.2.2 Zethembe Maintenance and General Services CC. 

6.1 5.2.3 Bonelena Construction Enterprize. 

6.1 5.2.4 Makhathini Projects CC. 

6.15.3. The Minutes of the RBAC indicate that it approved the nominated 
procurement strategy as requested by Mr Rindel, on 2 March 2010. 

6.16. The Negotiated Procurement Strategy for Selected Works During Phase 
One of the Nkandla Project 

6.1 6.1 . Mr Rindel submitted a further Internal Memorandum to the RBAC on 1 March 
2010, requesting it to approve the procurement of selected works on the 
Nkandla Project by means of a negotiated procurement process. The 
following extract of that memorandum is of particular significance to the 
matters investigated: 

"BACKGROUND 

The scope of the works on the complete project consists of the following: 

• New parameter security fence, complete with intruder detection; 

• New SAPS guard rooms 

• New hospital 

• New helicopter landing pads 

• Upgrading of water supply 

• Upgrading of sewerage disposal 



March 2014 




146 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

• Upgrading of firefighting installations. 

The Owner (sic) of the property had appointed a contractor, Messrs 
Moneymine Investments to construct new accommodation at the site. The 
current status of that project is that the contractor is on site and construction 
is 15% completed. 

The State has the obligation to include the security measures in the existing 
and new accommodation. This was confirmed by SAPS in a meeting on site 
on 26 January 2010. 

The scope of the works as indicated above, intrudes on the building works of 
the contractor, Messrs Moneymine Investments, as the security needs to be 
extended into the buildings that is currently being constructed. 



It is essential that Messrs Moneymine construction (sic) be appointed under 
the negotiated procedure to eliminate the following risks: 

• The above works cannot be done by any other contractor (appointed by 
open/nominated procedure) as all guarantees that the current contractor 
has/will provide, will be null and void. 

• The construction is in progress and the contractor is on program. The 
works that is (sic) included here is (sic) already delaying the contractor 
as 1 building is already at window height and the windows must be 
installed. This action cannot wait. 

• The contractor is security cleared by NIA and is trusted by the Owner of 
the Property (sic). 



147 



Secure In Comfort 



A Report of the 
Public Protector 




6.16.2. 

6.17. 
6.17.1. 



6.17.2. 
6.17.3. 



It is thus essential that the same contractor, Messrs Moneymine Investments, 
be appointed to complete the i//or/<s."(emphasis added) 

The memorandum proposed a negotiated strategy for the appointment of 
Moneymine Investments (Moneymine), which was approved. 

The SAPS Complains About the Slow Progress 

On 23 March 2010 a project Progress Meeting was held. The Minutes of this 
meeting indicate that the SAPS complained about lack of progress made by 
the DPW. The "Roll-Out Plan" agreed on was recorded as: 

"The Public Works Regional Bid Committee had approved the 
implementation of the entire project through a public tender process and 
allowing a few negotiated sections that affected the principal's residence." 

Mr Rindel further reported that the expression of interest submissions for the 
entire project was due on 24 March 2010. The envisaged process at the time 
was a pre-qualification tender, followed by "NIA screening of prospective 
tenderers. " 

As far as works directly related to the houses of the President were 
concerned, a negotiated process with the contractors on the site was decided 
upon. Emergency works were to be implemented by "previously screened 
organisations. " 

In this regard, Mr Rindel explained that the building contractor that was 
already on the site and involved with the President's private buildings was 
used for the works relating to those buildings for the sake of convenience, 
expedience and integration of the DPW works. As far as the other emergency 



148 



Secure In Comfort A Report of the March 2014 

Public Protector 




v XIII III :.■!' II 



works were concerned, he proposed that four contractors that were already 
cleared by NIA and that were involved in the Kings House Project, be 
approached for competitive quotes. 

6.18. The Declaration of the President's Private Residence as a National Key 
Point 

6.18.1. According to a Declaration Certificate provided to me by the Ministers of 
Public Works and Police, the President's private residence was declared a 
National Key Point by the Minister of Police, in terms of the National Key 
Points Act, 1 980, on 8 April 201 0. 

6.19. The President Complains About the Slow Progress Made with the 
Nkandla Project 

6.19.1. Mr Rindel indicated in his evidence during the investigation that much 
pressure was applied on the officials involved in the implementation of the 
Nkandla Project from the DPW Head Office by May/June 2010, due to the 
fact that the President had complained about the slow progress made and 
the negative impact that it had on the finalization of the construction of his 
private dwellings. 

6.19.2. At some point, according to him, the President called some of the SAPS 
officials involved to his house on the site to discuss the matter as he felt that 
the construction works were causing chaos on his property. 

6.19.3. On 2 June 2010, Mr Rindel submitted a progress report to the Head of 
Prestige of the DPW. As far as the norms required for the Nkandla Project 
were concerned, the progress report stated that: 



149 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

"Defence: No norms were received. However, the architects have drawn 
the required facilities as indicated by the POD Generals, and this was 
approved by their Top Management and signed off. These include POD 
Surgeon General (New clinic) and Air Force (New helicopter landing pads). 

SAPS: This office is in possession of the proposed norms, but is awaiting the 
final approval. 

Site Clearance: The Site Clearance of this project is not clear and had not 
been concluded as far as I know. The ownership of the site is in guestion, 
and it is believed that it is based on agreements between the Principal and 
the Local Nkhosi (sic)." (emphasis added) 



6.19.4. The progress report further indicated that no funding was allocated for the 
project, which resorted under the Capital Works budget allocation of the 
DPW. The required funding was stated as follows: 









Contractor 


R 30,000,000 


R 36,165,484 


Consultant 


R 8,920,896 


R 2,016,581 


Total 


R 38,920,896 


R 38,182,065 



Figure 2: Required funding as stated by Mr Rindel in the progress report to DPW Head of Prestige 

6.19.5. It was recommended that the stipulated funding be obtained for the Nkandla 
Project. 



6.19.6. The progress report referred to above was converted into an Internal 
Memorandum submitted by Mr Khanyile to Mr S Vukela, who by then had 
replaced Mr Malebye as the Acting Director-General of the DPW, on 10 June 
2010, recommending the approval for the Nkandla Project for the 2010/2011 



150 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



financial year of an amount of R38 920 896. Mr Vukela approved the funding 
on 1 1 June 2010, noting the following: 



"Funding must be transferred to budget to facilitate Pf 



6.20. The Shifting of Funds to Pay for the Project 

6.20.1. On 14 June 2010, the Director: PPM of the DPW approached the 
Chairperson of the PMBC with a written request for the approval of the 
shifting of funds from the Inner City Regeneration Programme of the DPW 
and the DPW Dolomite Programme "to fund a Prestige capital project WCS 
047455: Installation of Security Measures & Related at the private residence 
of the State President in Inkandla, KwaZulu-Natal." 

6.20.2. It was stated in the Internal Memorandum that there was no funding for the 
Nkandla Project and that the Acting Director-General had approved that R40 
million be made available from the Capital Works Budget. It also indicated 
that the Deputy Director-General was instructed to source funds urgently. 

6.20.3. The PMBC approved the request for the shifting of funds on 30 June 201 0. 

6.20.4. On 12 July 2010, the Chief Director: PPM of the DPW submitted an Internal 
Memorandum to the Chairperson of the Central Budget Committee of the 
Department in respect of the reallocation of the Capital Works budget for the 
2010/11 financial year. The motivation for requesting the Committee to 
approve the reallocation was as follows: 

"Due to high cash flows the regional offices were requested to update the 
system by 1 7 May 20 1 0. 



151 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



Capital Works budget was overcommitted. It was however noticed that RKTP 
and Dolomite programmes were under spending as the results funds (sic) 
were transferred from the said programmes to cover Prestige urgent projects. 
In addition BCOCC has also identified savings from their allocation and 
amount of R 18m will be utilized to fund security measures for Prestige and 
R 10m for appointment of consultants for DPW for the construction of regional 
offices. In order to compensate for the shortfall Prestige funds had to be 
sourced from BCOCC as the request for security measures are critical and of 
high importance. 

The Prestige original allocation was R336m and has since increased to 
R376m. The allocation on all the above services has been done in order to 
cover critical projects for Prestige and DPW." 

6.20.5. The requested reallocation of the Capital Works budget for 2010/11 was 
approved by the DPW Central Budget Committee on 1 3 July 201 0. 

6.21 . Cost Estimate No 4 

6.21.1. At a Progress Meeting held on 16 July 2010, chaired by Mr Rindel, issues 
such as the utilization of and funding for the Military Clinic, designs for 
security at the SAPS Control Room, the construction of a road to the helipad, 
and additional parking, were raised. It was also minuted that the SAPS 
confirmed that it required 20 bachelor flats, consisting of 10 buildings. 

6.21.2. On 28 July 2010, C A Du Toit Consulting Engineers that was appointed as 
the security consultants for the Nkandla Project submitted a preliminary 
report on the security measures that were required, which had to be 



152 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



considered for implementation in conjunction with the measures stipulated by 
the SAPS Security Evaluation Reports. 



6.21.3. R&G Consultants presented the DPW with its Cost Estimate No 4 in July 
2010. It amounted to R130 604 267.02. The main reasons for the increase in 
the cost estimation of the Nkandla Project were recorded as the redistribution 
of items to correct building installations, further increase in the earth and 
electrical works, the installation of sprinklers, an increase in security 
measures based on the assessment of the security consultant and 
communication systems. 



6.21.4. Mr Rindel explained during the investigation that from January 2010 to June 
2010, the focus of the Nkandla Project was only on Phase 1, i.e. the 
emergency works. From June 2010, the design of Phase 2 started in earnest, 
which is why the cost of the project started to escalate rapidly. Mr 
Makhanya's initial designs were not detailed and costed as such. However, 
once the details started to be added, it impacted on the cost of the project. 

6.22. The Utilization of the Military Clinic, Discussions with the President and 
Appointment of a Landscape Architect 



6.22.1 . The Minutes of the Progress Meeting held on 30 July 2010 recorded that Mr 
Makhanya confirmed that the Military Clinic would not be utilized for public 
use, "but for military use only." Further modifications to, inter alia, the roads, 
escape hatches, perimeter fencing were also discussed. The Civil Engineer 
was requested to pay attention to the issue of storm water drainage and 
excavations. 



6.22.2. It was also recorded that Mr Makhanya would discuss the road surface 
required for the driving of tractors with "the principal" {the President). 



153 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.22.3. 



6.22.4. 

6.22.5. 

6.22.5.1 

6.22.5.2 

6.22.5.3 
6.22.5.4 
6.22.6. 



The Mechanical Engineer was requested to make provision for fresh air 
supply to all the buildings and the construction of an additional guard house 
at the cattle gate was requested. Ms Pasley, the Chief Quantity Surveyor of 
the DPW was recorded as having stated that: 

"... firm financial control must be in place and consultants must ensure strict 
disciplines for financial measures." 

Mr Rindel approached the RBAC on 16 August 2010 with a request that the 
appointment of a Landscape Architect, via the Principal Agent (Mr 
Makhanya) is approved. He indicated during the investigation that his request 
was the result of instructions received from the DPW architects at head 
office. 

According to his Internal Memorandum, the scope of the landscaping works 
fell outside that of the appointed architect and included the following: 

Generation and submission of an Environmental Impact Assessment 
required for the new sewerage package plant; 

Design and documentation for all ground levels, banks, positions of retaining 
walls and storm water flows; 

Levelling of grounds for security fencing; and 

Designing measures aimed at security, visibility and privacy in specific areas. 

The estimated cost of the landscaping works was presented as R8.3 million 
and the associated professional fees as R1 .5 million. 



154 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.22.7. Based on a nominated procurement process that was followed, Mr Rindel 
recommended that the RBAC approve the appointment of the firm Uys and 
White Architects to do the design of the proposed landscaping. 

6.22.8. The Minutes of the RBAC show that it approved Mr Rindel's recommendation 



on 17 August 2010, but noted that it was subject to the condition that: 
"landscaping forms part of final scope for security measures." 



6.23. Cost Estimate No 5 

6.23.1. On 16 August 2010, R&G Consultants submitted Cost Estimate No 5 to the 
Acting Director-General of the DPW. It indicated that the total estimated cost 
of the Nkandla Project increased by a further 11% from the previous cost 
estimate, to R145 086 964. The hiked cost was attributed to expansion in the 
scope of work, which involved: 

6.23.1.1 Additional blocks of staff houses; 

6.23.1 .2 An expanded Safe Haven; 

6.23.1 .3 Additional Guard House; 

6.23.1.4 Additional SAPS Garages; 

6.23.1 .5 Additional measures around the fence; and 

6.23.1.6 Landscape Architect and Environmental Consultant fees (Based on 



assumption that the value of their work will be around R3 mil). 



155 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



6.24. Progress Reported on the Landscaping 



6.24.1. A Progress Meeting of the Project Team was held on 19 August 2010. The 
Minutes of the meeting state that Mr Rindel confirmed that a Landscape 
Architect was appointed. 



6.24.2. After discussions on the progress made in respect of a number of items, Mr 
Rindel suggested that Mr Makhanya meet with the President, "for signing off 
of documents." He indicated during the investigation that both Mr Makhanya 
and the appointed Landscape Architect were tasked at the meeting to obtain 
approval of the landscape design from the President. The officials of the 
Regional Office were not allowed to be part of that process. No further 
evidence was provided indicating that the President was indeed consulted in 
this regard. 

6.24.3. Mr J Crafford, the Director: Architectural Services of the DPW approached Mr 
R Samuel, former Deputy Director-General of the DPW that was involved in 
the management of the Nkandla Project, on 20 August 2010, providing him 
with a progress report in writing. He stated the following as far as the planned 
landscaping was concerned: 

"The appointment of the landscape architect (based in Durban) was only 
made during the course of the present week. Briefing and further discussions 
as well as a site visit could therefore only have been undertaken during the 
latter part of this week. The landscape architect fully comprehends the nature 
of her work, i.e. to reinstate the veld where interventions occur, to deal with 
interventions in the most sensitive terms, (large volumes of rainwater runoff 
generated by roads and roofs, etc.) the possible need for an El A process, the 
planting of trees, the care of the dry farmland as well as the vegetable 
garden, the finding of alternative water sources, the laying out of pathways, 



156 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



stairs and ramps, etc. attention to gardening and so on will only follow last on 
the list, although an outdoor living area common to all the houses has been 
identified and will be designed." 



6.25. Concerns raised about the budget 

6.25.1. It was noted that Mr Crafford also raised his concerns on 20 August 2010 
about the cost of the Nkandla Project with Mr Samuel, as follows: 

"An item of major concern is the budget, which has assumed gigantic 
proportions, given the fact that: 

• A more comprehensive overview has only now become apparent; 

• The project is quite extensive, given the number of buildings to be 
erected, and 

• Given the very humble beginnings of the project, nothing short of full 
township establishment now required with all the civil services yet to be 
put in place, inclusive of roads, storm water, potable water, telephone 
and electricity, standby power, security fencing, etc., and the list is 
growing , and 

• Compliance with statutory requirements with reference to interventions 
made in the landscape has yet to be costed and included in the budget. " 
(emphasis added) 



6.25.2. According to Mr Rindel, it was only at this time that the DPW head office 
became aware of the full scope of the works as proposed by Mr Makhanya 
and the other consultants. 



157 



Secure In Comfort A Report of the March 2014 

Public Protector 



111 l.'K.II 



6.26. Emergency Progress Meeting and the Appointment of a Private Project 
Manager 

6.26.1. An "Emergency Progress Meeting" was held on the site of the Nkandla 
Project on 6 September 201 0. 

6.26.2. According to the Minutes of the meeting, the former Minister of Public Works, 
Mr G Doidge, and Mr Samuel, were in attendance. After the Minister was 
introduced to the Project Team by the Regional Manager, Mr Doidge chaired 
the meeting. 

6.26.3. The progress made with items such as the installation of the bullet resistant 
glass and the perimeter fence was raised. Additions, including the 
improvement of the water supply, were also discussed. It was recorded that 
Minister Doidge would schedule two further visits to the site. 

6.26.4. The Project Team was requested to fully commit to the project. It was evident 
from the discussions recorded that there was an urgency to complete at least 
the first phase of the project by the end of November 201 0. 

6.26.5. On 14 September 2010, Mr Rindel chaired a Coordination Meeting relating to 
the Nkandla Project. It was recorded in the Minutes of the meeting that he 
confirmed that a private Project Manager was to be appointed by 24 
September 2010, "to accelerate works on site and to assist with NDPW 
critical outstanding issues." Mr Rindel indicated that the appointment of a 
private Project Manager was based on an instruction from the DPW Deputy 
Director-General, Mr Samuel. 

6.26.6. Other issues, such as the redesign of roads, the water treatment plant, air 
conditioning of the houses, landscaping, the installation of the bullet resistant 



158 



Secure In Comfort 



A Report of the 
Public Protector 




6.26.7. 
6.26.8. 

6.26.9. 

6.26.10. 

6.27. 
6.27.1. 

6.27.2. 



glass, lights for the helipads, earth works at the cattle kraal, safe heaven, 
electrical supply and lifts were discussed. 

On 16 September 2010 another Emergency Progress Meeting was held on 
the site. According to the Minutes, Mr Rindel chaired the meeting and Mr 
Khanyile tendered an apology on behalf of Minister Doidge. 

The appointment of the private Project Manager by means of a negotiated 
procurement process was, according to its Minutes, approved by the RBAC 
on 17 September 2010. The estimated cost of the appointment was R2.9 
million. 

At a Progress Meeting held on 17 September 2010, the appointment of the 
Private Project manager was also confirmed. It was noted in the Minutes that 
the primary objective of the private Project Manager was to "get works on site 
accelerated. " 

The issue of whether or not the Military Clinic would be used by people of the 
village was again raised by the SAPS with the request that a decision is 
taken. 

Cost Estimate No 6 

On 17 September 2010, R&G Consultants presented the Director-General of 
the DPW with yet another cost estimate on the project (Cost Estimate No 6). 

It represented a further 33% increase to R193 533 873. This time the extras 
to the previous scope of works responsible for the increase included: 

(a) An adjustment to the Safe Haven. 



159 



Secure In Comfort 



A Report of the 
Public Protector 




(b) Additions in all specialist services. 

(c) Additions in Landscaping. 

(d) Availability of Plant Room Designs. 

(e) Additions to Communications. 



6.28. Urgency to Complete Works by 30 November 201 

6.28.1. The next Emergency Progress Meeting was held with the Project Team on 
the site and chaired by Minister Doidge, on 23 September 2010. 

6.28.2. According to the Minutes of the meeting, the urgency of completing the 



installation of the bullet resistant glass, the construction of the fences and the 
accommodation of the SAPS officials were attended to. The progress made 
with the construction of the helipads and landscaping were also discussed. 



6.28.3. Minister Doidge stressed again that as much as possible of the works had to 
be completed by 30 November 2010. 

6.29. The Second SAPS Security Evaluation 

6.29.1 . The Office of the Divisional Commissioner: Protection and Security Service of 



the South African Police Service submitted a further security evaluation to the 
Director-General of the DPW on 25 September 2010. It contained details of 
the security measures required by the SAPS in addition to what was 
presented to the DPW in the report on the security evaluation that was 
conducted on 28 May 2009. 



6.29.2. According to Mr Rindel's evidence, the "new" security evaluation by the 
SAPS only focused on the security measures that were required. It was 



160 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




based on a performance specification. The professional consultants had to 
determine the exact scope, specification and cost of the works for the 
purposes of procurement. 



6.30. Progress Reported in October 2010 

6.30.1. The Durban Regional Office prepared a comprehensive progress report on 
the Nkandla Project on 10 October 2010. 

6.30.2. A Progress Meeting was held on the site on 12 October 2010, chaired by 
Minister Doidge. 

6.31 . Mr Doidge Replaced as Minister of Public Works 

6.31.1. It is common cause that Mr Doidge was removed from his position as the 
Minister of Public Works on 31 October 2010 and replaced by former Minister 
G Mahlangu-Nkabinde. 

6.32. Minister Mahlangu-Nkabinde Reports to the President on the Progress 
Made with the Nkandla Project 

6.32.1. On 5 November 2010, Minister Mahlangu-Nkabinde addressed a letter to 
President Zuma providing him with a detailed progress report on the following 
activities relating to the project: 

6.32.1.1 Cattle culvert 

6.32.1.2 Perimeter fence 

6.32.1 .3 Inner high security fence 



161 



Secure In Comfort 



A Report of the 
Public Protector 




6.32.1 .4 Guard House, Tuck Shop, Refuse and electrical rooms 

6.32.1.5 Electrical supply 

6.32.1.6 Sewer treatment plant 

6.32.1 .7 Relocation of families 

6.32.1.8 Upgrade of water supply 

6.32.1.9 Helipad 

6.32.1 .1 Excavation for clinic 

6.32.1 .1 1 Entrance by-pass 

6.32.1 .1 2 Services to park homes 

6.32.1.13 Entrance road 

6.32.1 .14 A security installation relating to the safe Haven 

6.32.1.15 Safe haven 

6.32.1 .1 6 Bullet Proof Glazing 

6.32.1.17 High Impact Glazing. 
6.32.2. She further reported that: 



162 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




" Taking the above report into consideration I am pleased to report that all the 
work for which my department is responsible will be completed by the 
deadline of the 30 November 2010 as per the commitment given to you by 
my predecessor. I have also taken the liberty of attaching hereto a progress 
report as updated on the 5 November 2010 detailing the various activities, 
the percentage completed per activity and comments for your information." 



6.32.3. Attached to Minister Mahlangu-Nkabinde's letter was an Internal 



Memorandum addressed to her by the Director-General of the DPW (Mr S 
Dongwana), signed by him on 5 November 2010, setting out the background 
of the project and including a detailed progress report prepared by the private 
Project Manager appointed by the DPW, Ramcon Project Managers. 



6.32.4. Mr Samuel (Deputy Director-General) chaired the subsequent Progress 



Meeting held on 9 November 2010 and reported, according to the Minutes 
and his evidence during the investigation, that the President was informed of 
the progress made with the project and that he was satisfied. 



6.33. Cost Estimate No 7 

6.33.1. Cost Estimate No 7 prepared by R&G Consultants was submitted to the 
Director-General of the DPW on 9 November 2010. 

6.33.2. The increase in the cost estimate from R193 533 873 to R196 864 037 was 



ascribed by them to additional park homes, an additional five staff houses, 
laundry facilities, design changes and the installation of solar power to staff 
houses. 



163 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.34. Further Concerns Raised About the Cost of the Project and the 
Consideration of Cost Apportionment 

6.34.1. The Ms G Pasley, Chief Quantity Surveyor of the DPW raised her concerns 
about the escalation of the costs of the Nkandla Project in an email message 
sent to Mr Rindel, on 3 December 2010. She stated, inter alia, that: 



"The scope of work and estimated costs have increased considerably over 
the past four months and continue to change which has given rise to further 
cost increases as can be seen from the budget reports already submitted by 
the consultant team and which are currently in the process of being revised 
again. The estimated costs have almost doubled over this period and it is 
essential that the parameters in respect of the scope of work and the budget 
are established and confirmed. Information pertaining to the exact 
apportionment of work and costs is critical in order that a detailed cost 
analysis can be done by the consultant Quantity Surveyors within the 
confines of the budget." (emphasis added) 



6.34.2. By 10 November 2010, the Regional Office started to prepare a document 



itemizing the scope of work and identifying what the DPW was responsible 
for and which items could be regarded as "private" i.e. for the account of the 
President. 



6.35. Feedback from Further Discussions with the President 

6.35.1. One of the issues discussed at the Progress Meeting held on 16 November 



2010 was the relocation of certain households as part of the project. 
According to the Minutes of the meeting, Mr Makhanya indicated that he was 
advised by the President that the households to be relocated 7s waiting for a 
family member to arrive before relocation can take place." Mr Khanyile was 



164 



Secure In Comfort A Report of the March 2014 

Public Protector 



requested to inform the President in writing of the circumstances relating to 
the relocation. 



6.35.2. At the progress meeting held on 23 November 2010, it was recorded that the 
President had requested to be informed about the delay in their relocation 
from the site. 

6.36. Enter Deputy Minister Bogopane-Zulu 

6.36.1 . Deputy Minister Bogopane-Zulu was introduced to the Nkandla Project Team 
at a Progress Meeting held on 30 November 2010. 

6.36.2. The Minutes of the meeting show that she immediately became involved in 
the discussions regarding the progress made in respect of several elements 
of the Nkandla Project. 

6.36.3. She also indicated to the meeting that she had discussions regarding the 
Nkandla Project with the President and that she would have further 
discussions with him regarding issues, such as the relocation of the affected 
households. 

6.36.4. The next Progress Meeting was held on 6 December 2010 and chaired by 
Deputy Minister Bogopane-Zulu. According to the Minutes of the meeting, 
she, inter alia, requested the contractors to improve the security on the site, 
offered her assistance and provided guidance in respect of expediting the 
project. 

6.36.5. It was also minuted that she stated that the President had requested that no 
new contractors be permitted to work on the site in Phase 2 of the Project. 



165 



Secure In Comfort 



A Report of the 
Public Protector 




6.37. Cost Estimate No 8 

6.37.1. R&G Consultants submitted Cost Estimate No 8 to the Director-General of 
the DPW on 8 December 2010. It indicated a 13,96% increase, stating that 
the following had to be added: 

6.37.1 .1 The 5 additional staff residential houses; 

6.37.1 .2 Additions to the relocation of households; 

6.37.1 .3 A Booster Pump Station; 

6.37.1 .4 Availability of certain values for direct contracts; 

6.37.1 .5 Inclusion of contractor rates; and 

6.37.1.6 Design changes to the SAPS, Pavilion and garage buildings that had not 
been finalized. 

6.37.2. The estimated increased from R196 864 037 to R224 344 542, as set out in 



the following graph: 



166 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



Cost Estimates 



1/0/1900 



3£ 

"Z 1/0/1900 

| 1/0/1900 
ro 

13 1/0/1900 
ro 

| 1/0/1900 
</i 

UJ 

1/0/1900 






1 






/ 
















i 


2 


3 


4 


5 


6 


7 


8 


□ Estimated Amount (R) 


R27,893, 


R47,323, 


R80,836 


U30,60^ 


={145,086 


={193,53: 


U96,86' 


={224,344 


■ Date of Estimate 


5/1/2009 


9/2/2009 


2/3/201C 


7/4/201C 


3/5/201C 


10/6/20] 


Ll/7/20] 


12/8/201 



F/gure 3; Estimated costing of the Nkandla Project as calculated from May 2009 to December 
2010 

6.38. Completion of Phase 1 of the Nkandla Project and the Reasons for the 
Delay and Escalation in Costs 



6.38.1. According to Mr Rindel's evidence, Phase 1 of the Nkandla Project was 
completed by about 10 December 2010 and handed over to the client 
departments (SAPS and DOD) by February 201 1 . 

6.38.2. The three new private residences of the President were also completed 
during 2010. 

6.38.3. He explained that it was only by December 201 that the Project Team had a 
clear indication of what the design by the consultants of Phase 2 of the 
Nkandla Project would look like and how much it would cost. That was after 
all the designs were finalized. 



167 



Secure In Comfort A Report of the March 2014 

Public Protector 



SO-UTI1 111 l.'K.II 



6.38.4. According to Mr Rindel, the scale of the project steadily grew from its 
inception, not because the basic requirements changed, but because of the 
design by the consultants of the implementation thereof. 



6.38.5. Mr Makhanya, the Principal Agent, explained during the investigation that the 
terrain of the site is on a slope, which, according to him, posed a further 
challenge as did the fact that the Nkandla Project had to be implemented in a 
very rural area. He further stated that many of the major issues that 
materialized during the implementation of the project were not or could not 
have been envisaged at its conception. A number of designs had to change 
and be reconsidered, which impacted on the costs. 



6.38.6. Mr Rindel described the implementation of the Nkandla Project during the 
investigation as very much "like building a puzzle without a picture". He 
explained that almost everyone involved in the project was exposed to such a 
venture for the first time and they therefore basically "wrote the rules as they 
went along." Officials of the Regional Office further expressed the view that 
the project was "doomed from the start" as the managers of the project were 
denied critical information and structures that were in place to manage it 
were often bypassed, which was unreasonable. 



6.38.7. Mr Makhanya stated in this regard that due to the nature of the Nkandla 
Project, the Project Team did not have the luxury of time to plan properly in 
advance. Planning had to take place whilst works were being implemented. 
Mr Rindel also indicated that design changes were regularly presented by the 
SAPS and the DOD and Mr Makhanya. It was his understanding that some of 
the changes were as a result of comments or instructions of the President. 



6.38.8. Mr Crafford described the Nkandla Project as working with a moving target. 

According to his experience, the scale of the project continued to grow, as 



168 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




additional items were added practically every month. It was his impression 
that these items mainly came from Mr Makhanya, who in his discussions with 
the President and the client departments, changed his designs. 



6.38.9. According to Mr Khanyile's evidence, the Nkandla Project did not follow the 



normal process of demand management and budget planning in the DPW. 
Under normal circumstances, a Planning Instruction would have been issued 
on the basis of which consultants would have been appointed to design the 
project and estimate the costs. The project would then go out on tender. In 
this case, he stated, the project was not fully planned in the initial stages. 
Information kept coming to the Project Team in pieces on what had to be 
done. Much of this information came forth at meetings where the DOD and 
the SAPS presented additional requirements. If it was a normal project there 
would have been proper planning and budgeting. 



6.38.10. It was noted during the investigation that all the officials interviewed agreed 



that the pressure coming from DPW Head Office and the Ministry of Public 
Works in respect of the Nkandla Project was immense. Mr Khanyile stated in 
his evidence in this regard that: 

"The project manager and the Regional officials were even terrified that they 
will be fired or transferred somewhere else if they do not comply with the 
instructions given to them on the project. " 



6.38.11. On 21 December 2010, Mr Khanyile submitted an Internal Memorandum to 



the new Acting Director-General (Mr Vukela) requesting approval to extend 
the Supply Chain Management Delegations of the RBAC to approve all 
procurements in respect of Phases 1 and 2 of the project in amounts above 
R20 million. The Internal Memorandum stated that such approval as well as 



169 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



approval to utilize the nominated procurement process had been granted by 
the former Acting Director- General, Mr Malebye. (as referred to above). 



6.38.12. The Memorandum furthermore advised that Phase 1 of the Nkandla Project 
(emergency works) had been 99% completed and that the Regional Office 
was ready to commence with Phase 2. 

6.38.13. Reference was made to a meeting held with senior officials of the DPW and 
Deputy Minister Bogopane-Zulu on 20 December 2010, where it was 
indicated that the works had to be fast tracked. Mr Rindel explained that the 
purpose of this meeting was to confirm the scope of works in respect of 
Phase 2 and to discuss the final procurement processes that would be used 
for implementation. 

6.38.14. The proposed date of the completion of Phase 2 was stated as 9 October 
201 1 . In this regard the memorandum explained that: 

"It must be stated that it is essential that these deadlines be met as the State 
already delayed the Owner (sic) of the property and this caused much 
embarrassment to the State." 

6.38.15. The memorandum was approved by Mr Vukela, on 21 December 2010. 

6.39. Reallocation of the 201 0/1 1 Capital Works Budget 

6.39.1. The Executive Committee of the DPW approved a reallocation of the DPW 
Capital Works budget for the 2010/1 1 financial year that included an amount 
of R 57 545 020 under Prestige for the Durban Region, on 1 6 February 201 1 . 



170 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



6.40. Further Interaction with the President 

6.40.1 . At the Progress Meeting held on 25 February 201 1 , Mr Makhanya confirmed 
that the design of the bullet resistant windows was in accordance with the 
President's request. It was also recorded in the Minutes of the meeting that Lt 
Gen Ramlakan requested that the designs be signed off by the President 
before installation could take place. 

6.40.2. It was noted that Deputy Minister Bogopane-Zulu requested that all 
outstanding works in respect of Phase 1 of the Nkandla Project is completed 
by 1 March 201 1 when the President would be going to his home for Easter. 

6.40.3. The Minutes further state that Lt Gen Ramlakan had a discussion with the 
President in connection with the helipads and that it was confirmed that after 
his term of office the helipads could be used for civilian aircraft, subject to the 
approval by the relevant aviation authorities. 

6.40.4. The issue of the utilization by the Department of Health of part of the Military 
Clinic was also discussed and it was recorded that the Deputy Minister would 
have a discussion with that Department in this regard. The possibility of the 
Department of Health utilizing 25% of the clinic was referred to as a "clip-on". 

6.40.5. It was also reported that the Deputy Minister requested a revised estimated 
costing of the landscaping, which was submitted to her for her input and 
further discussion. She had also raised her concerns about the high 
estimated cost of the fire-pool (which was converted into a swimming pool). 



171 



Secure In Comfort 



A Report of the 
Public Protector 




6.41. 
6.41.1. 

6.42. 
6.42.1. 



6.42.2. 
6.42.3. 



The Exit of Deputy Minister Bogopane-Zulu 

Deputy Minister Bogopane-Zulu was informed in writing by the then Minister 
of Public Works, Ms G Mahlangu-Nkabinde, on 7 March 201 1 that she was 
relieved from the responsibility of managing the Prestige Portfolio of the 
Department, with effect from 8 March 201 1 . 

Requesting Guidance on the Apportionment of Costs 

Mr Khanyile submitted an Internal Memorandum to the then Minister of Public 
Works under the heading: "DISCUSSION OF APPORTIONMENT OF 
COSTS BETWEEN STATE AND PRINCIPAL" on 28 March 201 1 . The aim of 
the memorandum was stated as: 

"...to provide all the applicable information to Top Management in line with 
the apportionment of cost between the State's responsibility and Private (cost 
to the owner)". 

According Mr Khanyile's evidence, the Regional Office determined the 
apportionment of costs with the assistance of Professional Services of the 
DPW Head Office. The relevant document was attached to the 
memorandum. 

The memorandum stated the scope of works was divided as follows: 

"Public (State) portion: R203 079 677. 18 
Private (Owner) portion RIO 651 580. 64 



172 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

The scope of the works included in the Public (sic) is approved and agreed in 
the meeting held in HO on 10 March 2011 and is in the process of being 
implemented and shall be concluded in line with the mandate given to the 
NDPW. 

The portion included under "Private" required additional attention 
before this can be implemented as it falls outside the scope of security 
measures. Please note that the implementation of some of these issues was 
unavoidable and some had already been completed. 



It was agreed at that meeting that the Department cannot implement any of 
the works included in the indicated above without the written instructions from 
Top management to do the same. This is a precaution that must be taken 
as the works fall outside the mandate piven to the Department. 

It is proposed that the works included herein be discussed between Top 
Management and Ministry and guidance be given to the way forward with 
these issues. It may be necessary to discuss these issues with the 
Principal as the financial implication directly affects him (He may want 
to implement these issues himself without the interference of the 
Department or else he may want to opt to reimburse the Department 
after we complete the same), "(emphases added) 

6.42.4. Mr Khanyile recommended in his memorandum to the Minister: 

• "That the scope of works falling within the mandate of the Department 
continues as previously instructed. 



173 



Secure In Comfort A Report of the March 2014 

Public Protector 



v ■nn ill :.■!> n 



That the scope of works apportioned to the Principal be discussed and 
guidance be given to the Team pertaining on (sic) the implementation 
thereof before construction will continue". 



6.42.5. R&G Consultants explained during the investigation that the cost 
apportionment document was prepared with their assistance. The whole 
professional team involved in the Nkandla Project participated and every item 
of significance was considered and debated before a decision was taken to 
qualify it as "private" or "public". They emphasized that every item referred to 
in the document was not implemented. 



6.42.6. According to Mr Rindel, he never received any response to Mr Khanyile's 
letter. He claimed that he was never given any instruction to implement the 
portion that was referred to as "private" in the apportionment document and 
did not do so. 



6.43. Concerns Raised About the Exclusion of the DPW Head Office 
Professional Team 



6.43.1 . The Ms Pasley, Chief Quantity Surveyor of the DPW, complained in an email 
message to Mr Rindel on 30 March 201 1 as follows: 

"As you are ware, we are not receiving the required monthly financial reports 
on the above-mentioned project. 



The consultant Quantity Surveyors are required to submit said reports to the 
Department strictly on a monthly basis in accordance with item 13.6 of the 
QS Manual and the QS unit is required to scrutinize these reports in 
accordance with the Department's revised project management delegations. 



174 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



It is imperative that we are kept fully informed, on an on-going basis, of the 
financial status of each of the projects. This is unfortunately not happening." 

6.43.2. She requested Mr Rindel to ensure that the outstanding reports were 
submitted urgently. 

6.43.3. In his response, dated 31 March 201 1 , Mr Rindel requested the project team 
to comply with Ms Pasley's request. He reiterated: 

" The matter indicated by Glenda is a serious issue, as financial management 
is core to this project, even more so since the project will probably be audited 
by many interested parties. Without the required inputs from all the parties, 
this may become a big embarrassment that will sink us. The information is 
further required by HO to defend any queries about the scope of works and 
costs included therein. " 

6.43.4. Mr Rindel explained during the investigation that due to reports that started to 
appear in the media in connection with the Nkandla Project, he was 
instructed by the office of the DPW Director-General to drastically reduce the 
number of people involved and to keep it at a bare minimum. This instruction 
included officials from DPW Head Office. The management of information 
leaks on the Nkandla Project at this time apparently became as important as 
managing the project itself. 

6.44. The meeting of 1 April 2011 

6.44.1. Despite having been removed from the Nkandla Project by the Minister of 
Public Works on 8 March 201 1 , the Minutes of a Progress Meeting held on 1 
April 2011 indicate that Deputy Minister Bogopane-Zulu was still very much 



175 



Secure In Comfort 



A Report of the 
Public Protector 




involved. During the investigation, the Deputy Minister denied that she 
attended this meeting as she had already been removed from the Nkandla 
Project. However, it was minuted that she expressed her concerns about the 
delays with the installation of the bullet resistant glass and the lifts that form 
part of the safe haven. As far as the Military Clinic is concerned the following 
was recorded in the minutes: 

"Hon. Deputy Minister H Bogopane-Zulu confirmed that the Clip-On will be an 
add-on to the military clinic. Further, she requested that the Clip-On design 
be made available for her perusal. 

Hon. Deputy Minister H Bogopane-Zulu said that a meeting was held with the 
Deputy Minister of Health who confirmed that a Primary Health Facility stage 
2 is required. Standard drawings can be obtained from the Department of 



6.44.2. It was also recorded that the Deputy Minister raised her concerns about the 



apportionment of costs. Mr Rindel indicated that a document outlining the 
apportionment between private and public was available. The Deputy 
Minister requested to be provided with document. 



6.44.3. As far as the fire-pool was concerned, it was recorded that the Deputy 
Minister stated that she would discuss the use of the pool by surrounding 
schools with the President. 

6.45. The involvement of Deputy Minister Bogopane-Zulu Terminated, 
Discussions with the President on Aspects of the Nkandla Project and 
further Progress Meetings 



Health. 



176 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.45.1. 



6.45.2. 



6.45.3. 



6.45.4. 



6.45.5. 



6.45.6. 



At the Progress Meeting held on 11 May 2011, Mr Rindel reported that 
Deputy Minister Bogopane-Zulu was not part of the project anymore. The 
Minutes of the meeting indicate that there was uncertainty about the 
implementation of her initiative as far as the utilization of the Military Clinic 
was concerned, that had to be clarified. 

It was further recorded that the implementation of landscaping had not been 
approved and that the Deputy Minister had discussions with the President in 
regard thereto. Mr Makhanya was requested to submit the landscaping 
changes that were made by the DPW to the President for his approval. 

Mr Rindel reported at this meeting that the construction of the fire-pool was 
put on hold due to uncertainty about the apportionment of costs in respect 
thereof. Mr Makhanya confirmed that the design of the fire-pool was 
presented to the President. 

The next Progress Meeting was held on 25 May 2011, where Mr Samuel 
confirmed that Deputy Minister Bogopane-Zulu was not part of the project 
anymore. It was decided to continue with the original design of the Clinic. 

Mr Makhanya reported that he had met with the President about the 
landscaping, but that the issues raised were not concluded and that he had 
to reschedule a further meeting for his approval. He indicated that he would 
probably meet with the President during the week of 25 May 201 1 . 

The Landscape Architect indicated that they could not proceed without the 
approval of the President. She also advised that an agreement had been 
reached that full public participation was not required for the Environmental 
Impact Assessment process. 



177 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



6.45.7. Mr Makhanya was also requested to discuss the issue of the fire-pool with 
the President. It was recorded in the minutes of the meeting that: " Makhanya 
said that the pool has been placed on hold because of the pool bearing a 
private costing which the principal (the President) did not accommodate for." 
He was also requested to discuss the "infrastructure reguirements 
(Marguee)" with him, (emphasis added) 



6.45.8. The Project Team discussed the progress made again at a meeting held on 
22 June 201 1 . The Chairperson, Mr Samuel, pointed out that the focus was 
to complete the project timeously. He also indicated that he was not familiar 
with the request for a "clip-on" as far as the clinic was concerned as it was 
not requested by the client department. 

6.45.9. Lt Gen Ramlakan confirmed that the "clip-on" was not approved by the DOD. 

6.45.10. It was further recorded that Mr Makhanya was to have further discussions 
with the President on infrastructure requirements. Mr Rindel indicated that 
the Landscape Architect was in the process of updating the design on what 
had been agreed with the President. 



6.45.11. No report back on discussion with the President in respect of the fire-pool 
was recorded. It was noted that infrastructure requirements still had to be 
discussed with the President. 

6.45.12. On 4 July 2011, a Progress Meeting was held on the site, chaired by Mr 
Samuel. He requested the expedition of several outstanding items. It was 
also recorded in the minutes of the meeting that the Civil Aviation Authority 
had agreed to classify the helipads as civilian landing facilities. 



178 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



6.45.13. The Landscape Architect indicated that the kraal and the amphitheatre 
should not fall under the landscaping component, but under its own structural 
entity. The Chairperson "pointed out that it was discussed previously that 
landscaping methodology is crucial." 



6.45.14. It was further recorded that the fire-pool submission was with the Bid 
Committee for approval and that all outstanding matters discussed between 
the Deputy Minister and the President had been resolved. No details were 
provided in this regard. This confirms the evidence of Deputy Minister 
Bogopane-Zulu that the matter of the swimming pool was discussed with the 
President. 



6.45.15. Mr R Samuel again chaired a Steering and Progress Meeting on 20 July 
201 1 . From the Minutes of this meeting (and other similar meetings) it 
appears that the Security Manager insisted that the information shared at the 
meetings should be handled with discretion. It was specifically recorded that 
no correspondence by email relating to the Nkandla Project was permitted 
and that all documents considered at these meetings had to be returned to 
the Principal Agent. 



6.45.16. Officials of the Regional Office indicated during the investigation that the 
instructions relating to the secrecy of the Nkandla Project created the 
impression that they were not allowed to discuss it with anyone that was not 
part of the Project Team, thus limiting them from obtaining outside advice 
when it was necessary. 

6.45.17. The Chairperson requested that the pace on all aspects of the project 
needed to be increased. 



179 



Secure In Comfort 



A Report of the 
Public Protector 




6.46. 
6.46.1. 



6.46.2. 

6.47. 
6.47.1. 



The Head Office Professional Team Excluded from Further Involvement 

On 20 July 201 1 , the Mr Crafford informed members of the Project Team by 
email that the Minister of Public Works had given instructions the previous 
day that the involvement of Professional Services of the DPW in the Nkandla 
Project should continue. However by 28 July 2011, Ms Pasley wrote as 
follows to Mr Rindel: 

"We currently find ourselves in the unfortunate situation where we are no 
longer in touch with the project, as you have excluded us from the project for 
the past ±2V 2 months. " 

The Minutes of the Progress Meeting held on 4 August 201 1 recorded that 
the Security Manager of the DPW expressed the view that as the project was 
nearing completion, "we should limit the need for new people to attend the 
meetings. " 

Additional Funding Requested for 2012/13 Financial Year 

Mr Rindel approached senior officials at the DPW Head Office on 16 August 
201 1 for the approval of additional funding for the Nkandla Project. He stated 
in his memorandum that: 

"The approval of the total funding amount, being R200 202 844. 13 (estimated 
final cost) is what is needed to be authorised for this project to be 
successfully completed. Please note that the allocated amount in the current 
fin year is sufficient, being R123 900 000.00 and that no additional funding is 
required for this year. The additional amount is required for the next fin year 
in order to pay for the last works and final account in the next (2012/13) fin 
year. It is not clear to me who is responsible to request this approval from 



180 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

PP&M (or other authority?) but I suspect that it may be starting with either of 
you. This is quite urgent as I am expected to issue instructions to the 
contractors for the completion of the additional works which must be 
completed already by 30 October 2011. Note that failure to assist me with 
the financial side of this project will result in all of us failinp the 
Principal, which will not be accepted lightly by the powers that be." 
(emphasis added) 



6.47.2. The records of the DPW show that the PMTE Central Budget Committee of 
the DPW approved a reallocation of the 201 1/12 Capital Works budget on 16 
September 201 1 , which included a reallocated amount for "Special and Major 
Projects" (previously listed as "Prestige") in the Durban Region of R132 
900 497. 

6.48. Final Series of Progress Meetings 

6.48.1. On 17 August 2011, the Project Team held a Progress Meeting on the site. 
According to the Minutes of the meeting, one of the issues raised was the 
outstanding requirements of the DOD in respect of the Military Clinic. Mr 
Makhanya reported that the matter was discussed with the Surgeon-General 
and that a list of the final requirements would follow shortly. 

6.48.2. It was recorded in the Minutes of a Progress Meeting held on the site on 31 
August 201 1 that Mr Khanyile and Mr Rindel, expressed their concerns 
about the slow progress made throughout the project. 

6.48.3. Subsequent Progress Meetings were also held, on 14 September 2011, 28 
September 201 1 , 1 2 October 201 1 , 1 9 October 201 1 , and 2 November 201 1 . 



181 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.48.4. The Minutes of the meeting of 28 September 2011 indicate that Mr 



Makhanya reported that the President was concerned about the progress 
made on the site and that it might not be available for him to use during 
December 201 1. 



6.48.5. The Minutes of a Steering and Progress Meeting held and chaired by Mr 
Rindel on 30 November 2011 indicate that a number of outstanding items of 
the Nkandla Project were in the process of being completed. 

6.48.6. The staff quarters were, inter alia, reported as ready for handover to the user 



departments, the bullet resistant installations were to be completed on 2 
December 201 1 , and safe haven installations were in the final stages. It was 
also recorded that works in respect of the guard houses, visitors centre, crew 
pavilion and VIP garages were complete or being finalized. Some work still 
had to be done on the roads, the helipads, the clinic, security equipment and 
the landscaping. 



6.49. Further Allocations and Reallocations of the Capital Works Budget 

6.49.1. The Acting Chief Financial Officer of the DPW informed its Acting Chief 
Operations Officer in writing on 19 November 2012 that the expenditure 
incurred, according to the WCS (Work Control System) of the Department, 
amounted to R206 420 664. According to the records, the DPW PMTE 
Central Budget Committee approved the Capital Budget allocation for the 
2012/13 financial year on 7 March 2012. It included an allocation of R36 755 
983 under the item "Special and Major Projects" in respect of the Durban 
Regional Office. 

6.49.2. On 29 August 2012, the Deputy Director: Budget and Planning: PMTE 
submitted a written request for the reallocation of the DPW Capital Works 



182 



Secure In Comfort 



A Report of the 
Public Protector 




6.49.3. 



6.50. 



6.50.1. 



6.50.2. 



6.50.3. 



Budget, which included a reallocated amount of R39 731 029 for "Prestige" \n 
respect of the Durban Regional Office. The request was approved by the 
PMTE Central Budget Committee on 12 September 2012. 

The site was handed over to the client departments on 27 February 2013. Mr 
Rindel confirmed in his evidence that all the works implemented by the DPW 
in terms of the Nkandla Project, were paid for by the Department. 

PART B: THE EVIDENCE ON THE GOODS AND SERVICES PROCURED 
BY THE DPW 

The Contracts Awarded by the DPW to Contractors for the 
Implementation of the Nkandla Project 

It was established from the records of the DPW that it awarded 12 contracts 
amounting to a total of R157 409 1 19 on the Nkandla Project. 

The total value of the above contracts was adjusted/increased after taking 
into account variation orders, contract price adjustments (CPA) and 
unforeseen items. The total value of the contracts after the 
adjustments/increases amounted to R193 814 014. 

The contracts were recorded on the WCS system of the DPW. It was noted 
that the total value authorised on the system amounted to R189 016 829.00 
instead of R193 814 014.75, resulting in a variance of R4 797 185.75 
between the amounts approved after taking into account variation orders, 
CPA and unforeseen items (R193 814 014.75) and the amounts authorised 
(R189 016 829.00). 



183 



Secure In Comfort 



A Report of the 
Public Protector 




6.50.4. 



6.51. 
6.51.1. 

6.51.2. 
6.51.3. 

6.51.4. 
6.51.5. 



Mr Rindel could not explain the above variance during the investigation, but 
pointed out that the total project expenditure did not exceed the total 
authorised amount above. It was noted that 94% of the variance (R4 520 
052.54 of R4 797 185.75) was as a result of the Bonelena Construction 
Enterprise & Projects' contract being authorised on the Works Control 
System (WCS) for an amount of R64 853 188.00. The contract was approved 
for an amount of R69 373 240.54. 

Payments Made to Contractors Appointed by the DPW 

During the investigation a review of the recorded payments made by the 
DPW to contractors was performed in order to determine the total amounts 
paid and whether the authorised amounts were not exceeded. 

It was found that the total payments to contractors amounted to R161 418 
824.26 and that the authorised amounts were not exceeded. 

Although an amount of R189 016 829.00 was authorised on the WCS, the 
total amount paid to contractors at the time of the conclusion of the 
investigation was R161 418 824.26, resulting in a saving of R27 598 004.74 
on the authorised amount. 

R&G Consultants confirmed during the investigation that the said contracts 
have been completed. 

R&G Consultants further indicated that over and above the total amount paid 
to contractors, six additional payment certificates amounting to a total of R3 
672 748.49 had been certified for payment at the time of the conclusion of 
the investigation. These payment certificates were yet to be paid by the DPW 
and will increase the total contractor payments to R165 091 572.74. 



184 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC F>EO>TE<:.TOk 
SOUTH flfPKU 



6.51.6. The saving on the authorized amount referred to above will accordingly be 
reduced to R23 925 256.26 (R189 016 829.00 - R165 091 572.74). 

6.51 .7. R&G Consultants confirmed that they were finalising the final accounts on the 
Nkandla Project and that it was expected that the final contractor payments 
would be around R167 million. 

6.51.8. It should be noted that that the project was segmented into 3 phases. Phase 
3 had not commenced at the conclusion of the investigation. 

6.52. The Payments Made to Consultants Appointed by the DPW 

6.52.1. From the investigation it was found that 7 teams of professional consultants 
were involved in the Nkandla Project and were paid a total of R50 352 842.93 
for Phases 1 & 2 only. The list of consultants involved and total payments 
made to them are as follows: 









TOTAL PAYMENTS 


1 


CA du Toit 


Security Consultants 


R 2,691,231.49 


2 


Ibhongo Consulting CC 


Civil & Structural Engineers 


R 6,006,457.36 


3 


Igoda Projects (Pty) Ltd 


Electrical Engineers 


R 2,503,732.89 


4 


R&G Consultants 


Quantity Surveyors 


R 13,794,957.70 


5 


Minenhle Makhanya Architects 


Architects, Principal Agent 


R 16,587,537.71 


6 


Mustapha & Cachalia CC 


Mechanical Engineers 


R 3,676,448.05 


7 


Ramcon 


Project Management 
Project Managers 


R 5,092,477.73 




TOTAL 




R 50,352,842.93 



Figure 4: List of Consultants and total payments made to each 



185 



Secure In Comfort A Report of the March 2014 

Public Protector 



SO-UTI1 111 l.'K.II 



6.53. Summary of the Works Implemented by the DPW 

6.53.1. From the investigation a summary of the works implemented by the DPW 
and the items constructed and/or service installed was found to be as follows: 





DESCRIPTION 


AMOUNT (R) 


1 


Safe Haven, Corridor Link, Walkway Above & Exit Portion 


R 19,598,804.10 


2 


20 Residential Staff Houses (40 units) and Laundry Facility 


R 17,466,309.67 


3 


Relocation of 1,5 Households - Moneymine 310 CC* 


R 4,223,506.68 


4 


Relocation of 2 Households - Bonelena Construction 


R 3,698,010.76 


5 


Clinic and SAPS Garage 


R 11,900,233.76 


6 


Visitors Centre & Control Room # 


R 6,720,852.95 


7 


Tuck-shop, Transformer & LV Room, Genset Room & Refuse Area 


R 956,381.16 


8 


Guard House 1 


R 1,205,827.49 


9 


Guard House 2 & 3 


R 1,367,770.87 


10 


Crew Pavilion 


R 997,831.00 


11 


Sewer Pump Station 


R 807,782.16 


12 


Fire Pool and Parking 


R 2,819,051.66 


13 


Sewer Treatment Plant 


R 1,030,673.68 


14 


Booster Pump Station and Steel Reservoir Tank 


R 571,278.25 


15 


New Residences: Security Measures & Air-conditioning 


R 5,038,036.33 


16 


General Siteworks(A/ote 1) 


R 67,964,858.55 




SUB-TOTAL CONSTRUCTION COST 


R 146,367,209.07 




ADD: CONTRACT PRICE ADJUSTMENT PROVISION 


R 1,231,109.08 




LESS: PENALTIES IMPOSED FOR LATE COMPLETION OF THE CONTRACT 


-R 2,781,149.08 




SUB-TOTAL NET ESCALATED CONSTRUCTION COST 


R 144,817,169.07 




VAT (14%) 


R 20,274,403.67 









Figure 5: Summary of the works implemented by the DPW 



* The reference to 1 .5 households here relates to the fact that not all of the buildings of the one 
household were replaced as it already had an existing building at the place of relocation. 

# The control room referred to here is the lower part of the building. The visitors centre (lounge) is on the 
first floor. 



186 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



6.53.2. The above table shows that various structures/items were constructed and 
services installed at a cost of R165 million. This amount includes the 6 
additional payments certificates amounting to R3.6 million which have been 
certified by R&G Consultants but not yet paid by the Department at the 
conclusion of the investigation. 

6.53.3. It was noted that an amount of R67 964 858.55 was allocated to "General 
Site Works". 

6.54. The Total Cost of the Nkandla Project 

6.54.1. At the time of the conclusion of the investigation, the total expenditure 
incurred by the DPW in respect of the Nkandla Project amounted to R215 
444 415.68 constituted as follows: 









1 


Total payments to contractors 


R 161,418,824.26 


2 


Value of contractor payment certificates certified 
but no yet paid 


R 3,672,748.49 


3 


Total payments to Professional Consultants 


R 50,352,842.93 


4 


Cost estimate for Phase III excluding Consultants 
fees 


R 31,186,887.36 




TOTAL 


R 246,631,303.04 



Figure 6: Total Expenditure in Respect of the Nkandla Project 



187 



Secure In Comfort 



A Report of the 
Public Protector 




6.55. 
6.55.1. 

6.55.1.1 
6.55.1.2 
6.55.1.3 
6.55.1.4 

6.55.1.5 
6.55.1.6 
6.55.1.7 

6.55.1.8 
6.55.1.9 



The Estimated Cost to the State of the Implementation of Phase 3 of the 
Nkandla Project 

From the evidence and information obtained during the investigation, it was 
established that, inter alia, the following works still need to be completed as 
envisaged by Phase 3 of the Nkandla Project: 

Safe Haven; 

Fire truck garage and waste disposal facility to be constructed; 

Rehabilitation and landscaping to park homes site to be implemented; 

High security inner perimeter fence around the Military Clinic area and main 
entrance to be constructed; 

Storm drainage to sloped earth banks to be rehabilitated. 

The installation of aviation equipment to be completed. 

Medical equipment to be provided and installed at the Military Clinic in 
accordance with the DOD standards. 

Paved Road to helipad and access control to be constructed. 

Landscaping and fencing to excess parking area, located to the south of the 
precinct. 

Electrical works. 



188 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.55.1.11 Civil works 



6.55.1 .1 2 A few other internal installations. 



6.55.2. It is estimated that the above works will cost a total of R31 186 887.36 
excluding consultants' fees. Should the above outstanding works be carried 
out at the estimated value provided, the Nkandla Project would cost a 
minimum of R246 631 303.04 calculated as follows: 









1 


Total payments to contractors 


R 161,418,824.26 


2 


Value of contractor payment certificates certified but no yet paid 


R 3,672,748.49 


3 


Total payments to Professional Consultants 


R 50,352,842.93 


4 


Cost estimate for Phase III excluding Consultants fees 


R 31,186,887.36 




TOTAL 


R 246,631,303.04 



Figure 7: Estimated Total Costs of the Nkandla Project (Including Phase 3) 



6.55.3. It was noted that the Mr Rindel approached the Acting Director-General of 
the DPW in an Internal Memorandum, dated 15 August 2012, recommending 
approval of the commencing of Phase 3 of the Nkandla Project, a negotiated 
procurement strategy in respect of the appointment of Moneymine for the 
works and a delegation allowing the Regional Office to approve all 
procurements in respect thereof. The Acting Director-General approved the 
Memorandum on 16 August 2012. 



6.55.4. However, it appeared during the investigation that due to the investigations 
into the propriety of the Nkandla Project, the implementation of Phase 3 
thereof was suspended. 



6.55.5. During the investigation I requested the DPW and the DOD to provide me 
with information relating to the security measures that were installed by the 
state at the private residences of former Presidents Botha, De Klerk, 

189 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

Mandela and Mbeki, to enable me to make a comparison. The idea was to 
use the comparison to get a sense of what was the original vision of the 
crafters of the policy instruments authorizing security measures at private 
residences of Presidents, Deputy Presidents, former Presidents and former 
Deputy Presidents. The underlying thinking was that the cost indications 
would give some idea of the scale of works that was envisaged. 

6.55.6. The information supplied revealed that at R215 million and still rising, the 
cost of security installations at President Zuma's private residence far 
exceeds similar expenditure in respect of all his recent predecessors. The 
difference is acute, even if an allowance is made for real Rand value, the 
rural nature of the Nkandla area and the size of President Zuma's household 
made detached dwellings. According to information supplied by the DPW, the 
cost involved in securing the private residences of the last five SA Presidents 
is as indicated in the table below: 



190 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



v. - - ' J I ii III :■■!'. II 



R 250,000,000 



R 200,000,000 



R 150,000,000 



R 100,000,000 



R 50,000,000 



R0 



R 241 000 000.00 



R 173 338.32 

(R20 101.67) 



R 236 484.78 

(R42 196.19) 



R 32 000 000.00 R 12 483 938.17 

(R 8 113 703.24) 

-TP m 



33.24) 



Botha De Klerk Mandela Mbeki 

□ (Actual Value) □ Estimated 2013 Value 



Zuma 



Figure 8: Past and Present Presidential Private Residence Security Costs 



191 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




PART C: THE SUPPLY CHAIN MANAGEMENT PROCESS 
6.56. The Procurement of the Services of Consultants and Contractors 

6.56.1 . At the time when the Nkandla project was initiated, the internal arrangements 



of the DPW provided that the procurement of goods and services up to a 
maximum of R20 million per procurement could be approved at the level of a 
Regional Office. Any procurement of more than R20 million had to be 
submitted to the Special National Bid Adjudication Committee at the DPW 
National Office. 



6.56.2. During the investigation it was established that Mr Malebye, the Acting 



Director-General of the DPW, met with the Project Team and Mr Rindel on 5 
October 2009 in connection with the procurement process in respect of 
goods and services for the Nkandla Project. 



6.56.3. The issues discussed at the said meeting appear as follows from an Internal 
Memorandum submitted by Mr Khanyile to Mr Malebye, on 9 October 2009: 



"The nominated procedure will be utilized. Contractors in larger northern 
KZN should be targeted in order to benefit from the works. 
The private QS (Quantity Surveyor) identify firms for general building, 
civil engineering works and electrical installations. This would be utilized 
for a nominated procedure. 

The RBAC must approve the procurement strategy above R 20, 
000,000.00." 



6.56.4. Mr Khanyile described the delegations required from the Acting Director- 
General as follows: 



192 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

"1. The responsibility of selecting contractors vests with SCM in the 
regional office. It is requested that DG confirms that this office may 
deviate from this responsibility in that the list as provided by the private 
QS may be used. 

2. The RBAC currently only has the delegation to approve any 
procurement strategy or tender below a limit of R20,000,000.00. It is 
requested that for this project only this delegation should be increased 
to above R20,000,OO.OQ. 



This will result in this office gaining complete control over the 
procurement process and that any communication with the SNBAC will 
not delay the project. 

If this request is denied, the RBAC will still forward the Procurement 
strategy to the SNBAC by 9 October 2009, but no guarantee can be 
given on the expected date of approval. 

3. The list of names for the nominated tender for NIA clearance had been 
forwarded to HO for assistance in fast tracking, (emphasis added) 

6.56.5. Mr Malebye approved the requests on the same day (9 October 2009). 

6.56.6. In his evidence, Mr S Malebye, explained that he acted as Director-General 
from the beginning of 2009 until 31 March 2010, when he resigned. Mr S 
Vukela took over from him as Acting Director-General. 

6.56.7. Due to the fact that the original cost estimate of the Nkandla project, based 
on the analysis of the security measures that had to be taken, amounted to 
approximately R27 million, Mr Malebye was of the opinion, according to his 



193 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC PISOTCCTOK 
SOUTH flfPICfl 

evidence, that approval of the request from the Regional Office to provide the 
RBAC with a delegation to approve procurements above R20 million at the 
time implied that the delegation would not be utilised for an amount above 
R27 million. 



6.56.8. The list of contractors referred to by Mr Khanyile in his said Memorandum 
was prepared and sent by email to Mr Rindel on 8 October 2009, by R&G 
Consultants. In his email message, Mr Gqwaru of R&G Consultants stated, 
inter alia, the following: 



"Further to our meeting of even date and acting on instruction from the 
Principal Agent (Minenhle Makhanya Architects), we submit a list of proposed 
contractors who are to be invited to tender on this project. Please note as 
indicated at yesterday's meeting with the Minister and Director-General of 
Public Works at Tshwane, the basis for the nomination is that: 

1. These contractors are registered with the CIDG (sic) and most of them 
have the necessary grading 6GB PE. 

2. They are currently doing in the area (sic) and therefore understand the 
local communities. 

3. We, as a professional team, have screened them, and we are satisfied 
that they can deliver the goods. " 



6.56.9. The list provided by R&G Consultants included the names of 7 general 
building contractors, one of which was Bonelena Construction. 

6.56.10. Mr Khanyile submitted a further Internal Memorandum to the Acting Director- 
General (Mr S Vukela) on 21 December 2010, requesting reconfirmation of 
the delegation granted to the Regional Office by the former Acting Director- 
General (Mr S Malebye), in respect of which the Regional Office could 



194 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



procure goods and services for the security project in amounts exceeding 
R20 million. The Memorandum was approved the same day. 



6.56.11. When Mr Khanyile was provided with an opportunity to respond to the 
evidence obtained from the documents referred to above, he stated that the 
Project Manager of the Nkandla Project was subjected to unusual 
interference by DPW Head Office and the "political heads" of the DPW in the 
procurement of service providers. 



6.56.12. He further explained that at the time when the Nkandla Project was initiated, 
the officials of the Regional Office were not aware of the involvement of Mr 
Makhanya and other consultants and contractors in the President's private 
construction works. It was Mr Malebye that informed the Project Manager (Mr 
Mahadeo at the time) that Mr Makhanya was managing the President's 
private project. 



6.56.13. The procurement process of contractors consisted only of nominated and 
negotiated procurement strategies and direct appointments. The reasons for 
the deviations from the prescribed open tender process appear from the 
relevant DPW Internal Memoranda, Request for Approval of Procurement 
Strategies and the minutes of the RBAC meetings. 



6.56.1 4. The main reasons for the deviations were recorded as the following: 



6.56.14.1 Due to the security nature of the Nkandla Project, only contractors approved 
by NIA could be used. An open tender process would also have taken too 
long; 



195 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.56.14.2 Contractor (Moneymine) was appointed by the President to construct private 
dwellings on the site. The scope of security works assigned to this contractor 
had to be integrated with private works. 

6.56.1 4.3 "A meeting was held with Deputy Minister Bogopane-Zulu and DDG: ICR&PS 



on 21 December 2010 in which she confirmed that the Principal (President) 
indicated that he does not want other contractors on site Phase II opposed to 
Phase I. The meeting agreed that the works should be negotiated. The 
reasons for nominating this contractor is the contractor are (sic) currently on 
site, performing under Phase I. The contractor's performance is good, 
reached all the tight goals on time management and delivered the project on 
time." 



6.56.14.4 "It was identified during September 2011 that the SAPS and DOD housing 
during the December periods and thereafter, would not be sufficient. It was 
agreed with the SAPS, DOD and the Honourable Minister that additional 
accommodation would be provided for the clients in line with their security 
protocol." The contractor was the only park home supplier in the KZN 
Province. 

6.56.14.5 Due to the installation of BRG glass in the buildings, the installation of air 
conditioners became critical and had to be done on an emergency basis 

6.56.1 4.6 "It became clear that it would be beneficial to the State to issue a direct order 
to the supplier for the following reasons: 



expedite the works (reduce the security risk) 



No mark-up to contractor on site-financial benefit to the State." The 
order issued, was based on the instructions from Top Management, in 
order to procure the manufacture, supply and installation of the security 



196 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



glass at the above mentioned site. "This office (the Regional Office) was 
instructed to ensure that the order be given out on the same day as the 
decision taken. " 

6.56.14.7 Due to changes in SAPS requirements the installation of the fence became 
critical. Contractor the only supplier of the particular product in the country. 

6.56.14.8 The Acting Director-General directed that the procurement process should be 
limited to one supplier due to security reasons. 

6.56.15. The main reasons for the deviations for the appointment of consultants were 
similarly recorded as the following: 

6.56.15.1 Appointed by the President in respect of the construction of private 
residences. Scope of works of the security project had to be integrated with 
private works. 

6.56.15.2 The security project had to be fast tracked due to a deadline for completion 
set by the Ministry of Public Works. 

6.56.15.3 The time period within which the project had to be completed did not allow for 
an open tender process. 

6.56.16. Mr Khanyile stated the following in regard to reporting the deviations to the 
National Treasury: 

"When the project manager wanted to report deviations to Treasury, he was 
informed by head of security, Mr Z Rambau at head office that all deviation 
documents should be sent to him for discussion with the DG and Treasury. 



197 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

When the Auditor-General requested files for project A (the Nkandla project) 
to be audited, the security manager at head office and DG refused that such 
documents for project A, be given to AG. The Region informed them that it 
will be regarded by the Auditor-General as limitation of scope. They refused 
our advice. This is one of the reasons that the Department got a disclaimer 
from the Auditor-General. " 



6.56.17. No evidence was presented during the investigation that any of the 
deviations referred to above was reported to the National Treasury. 

6.56.18. Furthermore the explanation of internal memoranda that consultants 
procured without tenders were motivated by them being security vetted is 
contradicted by findings of the Ministerial Task Team that investigated the 
Nkandla irregularities. 



6.57. Variation Orders 



6.57.1 . The National Treasury Instruction Note on Enhancing Compliance Monitoring 
and Improving Transparency and Accountability in Supply Chain 
Management issued in terms of section 76(4) (c) of the PFMA on 31 May 
201 1 states the following in respect of Variation Orders: 



"It is recognized that, in exceptional cases, an accounting officer or 
accounting authority may deem it necessary to expand or vary orders against 
the original contract. 



The absence of a prescribed threshold for the expansion or variation of 
orders against the original contract has, however, led to gross abuse of the 
current SCM system. 



198 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

In order to mitigate against such practices, accounting officers and authorities 
are directed that, from the date of this instruction note taking effect, contracts 
may be expanded or varied by not more than 20% or R20 million (including 
all applicable taxes) for construction related goods, works and/or services 
and 15% or R15 million (including all applicable taxes) for all other goods 
and/or services of the original value of the contract, whichever is the lower 
amount. 

Any deviation in excess of these thresholds will only be allowed subject to the 
written approval of the relevant treasury. Whilst provision is made for 
deviations, it is imperative to note that requests for such deviations may only 
be submitted to the relevant treasury where good reasons exist. " 

6.57.2. The motivation submitted in respect of the variation order of R1 1 244 652.25, 
which amounted to 58,65% of the original contract amount, was as follows: 

• "Additional work was given to the contractor as this was an emergency 
contract and the works had to be completed for the December period; 

• The construction of the roads and helipads were required in order for 
the Principal (President) to gain access to the premises. 

• All site services to be commissioned (sewer treatment plant and steel 
reservoir) so that entire premises is operational by December. 

• Major earthworks for platforms had to be created for the park homes 
that will house SAPS and SANDF during the December period. 

• A cattle culvert area that contained a lot of earthworks had to be created 
to allow for access of the livestock." 

6.57.3. The variation order that represented 52.7% of Moneymine's original contract 
related mainly to re-measurements based on changes in and additions to the 
designs and bulk earthworks that had to be done as part of Phase 1 . 

199 




Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



PART D: EVIDENCE ON SPECIFIC ISSUES CONSIDERED DURING THE 
INVESTIGATION 

6.58. The Budget for the Nkandla Project 

6.58.1. The Explanation Provided by the Director-General of the DPW 

6.58.1.1 During the investigation, Mr Dlabanthu, the Director-General of the DPW, 
was requested to explain how the Nkandla project was budgeted for by the 
Department. 

6.58.1 .2 In his written reply, dated 1 9 March 201 3, the Director-General stated that: 

"As far as the budget for the above mentioned is concerned, it seems that 
there was no specific budget allocated for the upgrade of security measures 
at the President's private residence in Nkandla. The approach adopted was 
that funds would be made available when savings materialized from Prestige 
and DPW capital projects. 

In 2010 finds were shifted from Inner City Regeneration and DPW dolomite 
programme for the security upgrade in Nkandla." (emphasis added) 



6.58.2. The Evidence of the Former Chief Financial Officer of the DPW 

6.58.2.1 Ms C Motsitsi, who was the Chief Financial Officer of the DPW when the 
Nkandla project commenced, was interviewed during the investigation. 

6.58.2.2 According to her, the budgetary process of the DPW entailed that the 
Regional Managers submitted proposed budgets for the regions for the next 



200 



Secure In Comfort 



A Report of the 
Public Protector 




6.58.2.3 



6.58.2.4 



6.58.2.5 



6.58.3. 



6.58.3.1 



6.58.3.2 



financial year(s) to the Budget Committees at the Head Office, which would 
consider it against the total amount available for the Department, and 
allocate budgets according to priorities. 

Despite having been in the position of Chief Financial Officer of the 
Department at the relevant times, she was not involved in the funding of the 
Nkandla project. The project was, in her view, not managed at the normal 
levels of officials as the Director-General, Minister and Deputy Minister were 
directly involved. 

All she knows is that at some stage funds had to be relocated from other 
projects of the Department in order to fund the Nkandla project. 

In this regard she had often raised the issue of the Prestige Programme of 
the DPW, which caters for the residential accommodation of members of the 
Executive and was often over committed and not properly budgeted for. This 
resulted in regular relocation of funds from other necessary projects of the 
DPW to the Prestige budget. 

Information Provided by Ms S Subban, Deputy Director General of the DPW 
and Mr K Khanyile, the Former Regional Manager During the Investigation 

Ms Subban was a member of the Capital Budget Committee of the DPW at 
times relevant to the Nkandla Project. 

She explained that in June 2010, she was requested by the then Acting 
Director-General (Mr Vukela) to find a way of making funding available for the 
Nkandla project as the funding allocated to the Prestige budget was 
inadequate. 



201 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



6.58.3.3 The request for funding emanated from the Durban Regional Office. It was 
submitted to the Planned Maintenance Budget Committee (PMBC) that 
approved and it was then submitted to the Capital Budget Committee of the 
DPW for ratification. 

6.58.3.4 She further explained that it was initially envisaged that the Nkandla Project 
could be funded from the savings of the DPW on other projects, as the 
original amount requested was only R27 million. 

6.58.3.5 In order for the funding of the project to be properly administered, it was 
registered on the Works Control System (WCS) of the DPW. 

6.58.3.6 Mr Khanyile confirmed that the Nkandla Project was not budgeted for in 
advance and that the Regional Office had to approach the PMBC for 
additional funding in August 2009. It was regarded as an emergency due to 
the urgency that arose as a result of the appointment of Mr Zuma as the 
President in May 2009. 

6.58.4. The Evidence of the Project Manager and the Project Budget Administration 
Manager of the Regional Office 



6.58.4.1 Mr Rindel and Mr Nadu, the Assistant Director: Project Budget Administration 
of the Regional Office, explained during the investigation that after the initial 
request for funding was approved by the DPW Head Office, the Nkandla 
project was registered on the WCS of the DPW, which is an electronic 
budgetary tool that enables the Department to update the estimated costs 
and payments made to assist it to budget and allocate funding when 
necessary. 



202 



Secure In Comfort A Report of the March 2014 

Public Protector 




111 l.'K.II 



6.58.4.2 As the project progressed and designs by the professional team of 
consultants were costed, the WCS was updated. The process was reviewed 
every month and budget allocations reconsidered quarterly. 



6.58.4.3 The initial cash flow projections of the DPW as recorded on the WCS in 
respect of the Nkandla project were as follows: 







2010/2011 


R 36,136,364 


2011/2012 


R 108,817,103 


2012/2013 


R 18,000,000 


2013/2014 


R 30,939,249 


Total 


R193 89 716 



Figure 9: DPW Cash Flow Projections in respect of the Nkandla Project 



6.58.5. The Evidence and Information Obtained from the Records of the DPW 



6.58.5.1 From the limited documents that I could obtain from the DPW during the 
investigation relating to the budget for the Nkandla Project (already referred 
to above), it was established that the first recorded request for funding was 
dated 6 August 2009, when the Director: PPM requested the PMBC to 
approve the amount of R27 893 067, which was granted. It soon became 
clear to the Project Team that the Nkandla project would be implemented 
over a period that would cover more than one financial year. 

6.58.5.2 By February 2010, the cost estimate submitted by R&G Consultants 
indicated that an amount of R80 836 249 would be required. 

6.58.5.3 On 10 June 2010, Mr Rindel reported in an Internal Memorandum to the 
DPW Head Office that no funding was allocated for the Nkandla Project. He 
indicated that the funding required for the 2010/201 1 financial year amounted 
to R38 920 896 and for the 201 1/2012 financial year to R38 1 82 065. 

203 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC F>EO>TE<:.TOk 
SOUTH flfPKU 



6.58.5.4 It appears from the Internal Memorandum dated 14 June 2010 that Mr 
Rindel's request was approved by the PMBC and the Acting Director-General 
approved the reallocation of R20 million from the Inner City Regeneration 
Programme and R20 million from the Dolomite Risk Management 
Programme to the Nkandla Project. 

6.58.5.5 The minutes of the DPW Central Budget Committee meeting held on 13 July 
2010 indicated that it approved the reallocation of an additional R18 million of 
the 2010/2011 Capital Works budget from the amount allocated to BCOCC 
"to fund security measures for Prestige". 

6.58.5.6 The Executive Committee of the DPW approved a further reallocation of the 
2010/2011 Capital Works budget on 16 February 2010, which resulted in a 
total budget allocation in respect of Prestige for the Durban Region for 
201 0/201 1 in the amount of R57 545 020. 

6.58.5.7 By December 2010, R&G Consultants advised the Director-General of the 
DPW in writing that the cost estimate of the Nkandla Project amounted to 
R224 344 542. 

6.58.5.8 On 16 August 2011, Mr Rindel informed the DPW Head Office in an Internal 
Memorandum that a total amount of R200 202 844.13 was required to 
complete the Nkandla Project. He further indicated that the amount of R123 
900 000 that was allocated to the project for the 2011/2012 financial year 
was sufficient, but that the balance would be required in the 2012/2013 
financial year. 

6.58.5.9 The DPW Central Budget Committee, according to the minutes of a meeting 
held on 16 September 2011, approved a reallocation of the 2011/2012 



204 



Secure In Comfort A Report of the March 2014 

Public Protector 



v ■nn ill :.■!> n 



Capital Works budget based on projected "savings" from other programmes 
that resulted in the budget allocated to the Regional Office under for Special 
and Major Projects (Prestige) amounting to R132 900 497. 



6.58.5.10 The approval of a reallocation of the 2012/2013 DPW Capital Works budget 
was recorded in the minutes of the DPW Central Budget Committee held on 
7 March 2012, in terms of which the amount allocated for Special and Major 
Projects to the Regional Office was R36 755 983. 

6.58.5.11 A further reallocation of the 2012/2013 Capital Works budget in favour of 
Prestige in respect of the Regional Office was approved by the DPW Central 
Budget Committee on 12 September 2012 (according to the minutes), taking 
the allocated budget to R39 731 029. 

6.58.5.12 It was noted that the Inner City Regeneration and Dolomite Risk projects on 
several occasions featured as programmes from which reallocation of funds 
were made. 

6.58.5.13 The total budget allocations to the Durban Regional office for Prestige for the 
financial years 201 0/201 1 to 201 2/201 3 are as follows: 



FINANCIAL YEAR 


ALLOCATED AMOUNT 


2010/2011 


R 57,545,020 


2011/2012 


R 132,900,497 


2012/2013 


R 39,731,029 


Total 





Figure 10: Prestige Budget Allocations by the Durban Regional Office of the DPW for certain 



financial years 



205 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



6.58.5.14 According to Mr Rindel's evidence, the only Prestige Project that the 
Regional Office was involved in during this period was the Nkandla Project. 



6.58.6. The Budget Projections in Respect of Prestige Projects as Reflected in the 
Strategic Plans of the DPW 

6.58.6.1 It is common cause that the accommodation of members of the Executive 
and the associated costs in respect of security measures fall under, what is 
referred to by the DPW as 'Prestige" projects or programmes. These projects 
of programmes form part of the Infrastructure (Capital Works) Budget of the 
Department. 

6.58.6.2 It was noted during the investigation that the 2010/13 Strategic Plan of the 
DPW indicated the 201 0/201 1 budget for Prestige as R283 898 000. 

6.58.6.3 The reference to "Prestige" was replaced with "Special and Major Projects" in 
the 2011/14 Strategic Plan. According to evidence presented by officials of 
the DPW during the investigation, the reason for this change was that there 
were concerns about the media's interest in the amounts spent on Prestige 
projects, as reflected in the Strategic Plan and the view that it should rather 
be referred to differently was accepted and implemented. 

6.58.6.4 The DPW Capital Infrastructure Budget for 2011/2012 stated as amount of 
R725 877 331 for Special and Major Projects. 

6.58.6.5 The 2012/2016 Strategic Plan shows a budgeted amount for 2012/2013 
under Special Projects of R323 742 000. 

6.58.7. The Inner City Regeneration and Dolomite Risk Management Programmes of 



the DPW from which Funds were Reallocated to the Security Project: 



206 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.58.7.1 The main objectives of the Inner City Regeneration programme was, 
according to the 2010/13 Strategic Plan: 



"to rejuvenate inner towns and cities through the provision of improved 

physical working environments to 40 national government 

departments/agencies in the various inner cities; 

To create a centre of excellence for project management through 

planning, execution, monitoring and training; and 

To provide built environment, procurement and contractual professional 

advice, support services, standards and risk mitigation services to the 

Department. " 



6.58.7.2 The details of the Dolomite Risk Management Programme of the DPW do not 



appear from the contents of the Strategic Plans of the Department. However, 
its importance is obvious from the substantial amounts allocated in budgets 
of the DPW to this programme. 



6.58.7.3 In a document entitled: "APPROPRIATE DEVELOPMENT OF 
INFRASTRUCTURE ON DOLOMITE: GUIDELINES FOR CONSULTANTS" 
issued by the DPW in August 2003, the importance of the Dolomite Risk 
Management Programme is referred to as follows: 

" The objective of applying a risk management strategy to infrastructure is 
to ensure the safety of personnel and visitors, protection of property and to 
avoid fruitless expenditure. Avoiding sinkholes is not only important from a 
safety point of view, rehabilitating sinkholes and repairing 
buildings/infrastructure is costly. 



207 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

In a climate of increasing awareness of individual rights, it is apparent that 
failure to proactively manage dolomite risk may constitute dereliction of duty 
and may expose the Department of Public Works, its officials, its principal 
agents and other consultants involved, to recourse through a number of 
avenues, including the Occupational Health and Safety Act of 1993. It should 
be clearly understood that principal agents and consultants are not absolved 
of their responsibilities and cannot claim ignorance in the event of damage or 
loss of life in a sinkhole. 



In terms of bona mores, the criterion of reasonableness, it is essential that 
the Department of Public Works and its consultants "act" and are seen to act 
positively in order to prevent harm. Infrastructure must be appropriately 
designed, constructed and serviced to facilitate management of dolomite risk 
to this end the Department of Public Works has adopted a Centralized 
Dolomite Risk Management Strategy for infrastructure located on all dolomitic 
land." 



6.59. The Ownership and Legal Occupation of the Land where the DPW 
Constructed Buildings and Security Installations 



6.59.1. It was established from the evidence and information obtained during the 
investigation that President Zuma's private residence is located on traditional 
land, which is owned by the Ingonyama Trust. 



6.59.2. A significant part of the Nkandla project that was implemented by the DPW 
consisted of construction and other works on land immediately adjacent to 
the land that constitutes the President's private homestead. These 
constructions included the two helipads, the Military Clinic, the Crew Pavilion 
for pilots, a guard house, a generator room, the tuck shop, the 
accommodation for the SAPS and DOD staff and associated buildings. 



208 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.59.3. The affairs of the Ingonyama Trust are administered by the KwaZulu-Natal 
Ingonyama Trust Board that was established by virtue of the provisions of 
section 2A of the KwaZulu-Natal Ingonyama Trust Act, 1994. 

6.59.4. Section 2(5) of this Act provides that the Board "shall not encumber, pledge 



lease, alienate or otherwise dispose of any of the said land or any interest or 
real right in the land, unless he (sic) has obtained the prior written consent of 
the traditional authority or the community authority concerned and otherwise 
than in accordance with accordance with the provisions of any applicable 
law." (emphasis added) 



6.59.5. The Minister of Public Works indicated in his response to my enquiries, dated 



5 December 2012, that approval was sought by the DPW from the 
Ingonyama Trust to build on the said land and that a lease agreement was to 
be concluded. From the documents attached to his further response in 
connection with the matter addressed to me on 11 March 201 1 , it was 
established that the Nxamalala Traditional Council issued a TRADITIONAL 
COUNCIL CONSENT, on 21 October 2010. 



6.59.6. This consent document states that at a meeting of the Traditional Council 



held on 21 October 2010 it was resolved that the Council had no objection to 
the "application to acquire rights to land by the National Department of Public 
Works" in respect of what appears to be the land that was required for the 
construction of buildings and other structures for the Nkandla Project. 



6.59.7. It is important to note that the consent document specifically stated the 
following: 



209 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

"The form of tenure thereof (the acquiring of the land) to be agreed between 
the applicant and the Ingonyama Trust Board as land owner -in-law in terms 
of section 3 of the Ingonyama Trust Act, Act 3 of 1994, as amended. This 
consent is given in terms of section 2(5) of that Act. 

The Traditional Council confirms that all persons occupying or having an 
interest in the land have been consulted and have no objections to the 
proposals. 



The applicant (the DPWJ has been advised and confirms that he/she/it will 
not do anything or erect any structure on the land until an appropriate tenure 
right has been granted to and the necessary documents have been signed 
with the Ingonyama Trust Board ." (emphasis added) 



6.59.8. From the information provided by the Minister of Public Works, the 
"appropriate tenure right" referred to in the consent document is a long term 
lease agreement. 

6.59.9. The contents of the written consent granted by the Nxamalala Traditional 
Council was clearly only an indication that it had no objection to the 
application of the DPW to lease the land concerned. However, the Council 
resolved that nothing could be done and no structure could be erected on the 
land before the terms of the lease had been agreed on and the relevant 
lease agreement had been signed by the parties. 

6.59.10. In his letter addressed to me on 1 1 March 2013, the Minister of Public Works 
stated that: 



210 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

"On the question of the lease agreement, I previously explained that the 
investigation found that there was an unsigned lease agreement between the 
Department of Public Works and the Ingonyama Trust that was supposed to 
be signed in 2011. However, for unknown reasons it was not signed. I 
requested my office to attend to the matter, however I was advised that the 
lease agreement needed to be re-negotiated as it was not in the interest of 
the Department." (emphasis added) 



6.59.1 1 . At the time of the conclusion of the investigation, there was no indication that 
a lease agreement had been signed by the DPW in respect of the land 
concerned. 



6.60. President Zuma's Private Residence Declared a National Key Point. 

6.60.1 . President Zuma's private residence was declared a National Key Point by the 
Minister of Police in terms of the National Key Points Act, on 8 April 2010. 
However, the acknowledgement of receipt in the Presidency is dated 7 April 
201 1 . The Director-General of the Presidency confirmed the accuracy of this 
date during the investigation. 

6.60.2. The evidence in respect of the security evaluations conducted by and the 
involvement of the Security Advisory Service of the SAPS in the Nkandla 
project. 

6.60.3. From the documents obtained during the investigation, it was established, as 
indicated above, that the Security Advisory Service of the SAPS conducted a 
security evaluation of the President's private residence on 28 May 2009, i.e. 
1 9 days after Mr Zuma took office. 



211 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



6.60.4. The security evaluation was recorded in an 11 page report that was 
presented to the DPW. 



6.60.5. Brigadier Adendorff, the Head of the Security Advisory Service of the SAPS, 
was interviewed during the investigation. She explained that Security 
Advisory Service is tasked to look after the security requirements in respect 
of the protection of, inter alia, members of the Executive as far as their official 
and private residences are concerned. It conducts security evaluations of the 
premises taking into consideration any threats to the person involved. It does 
not work together with the State Security Agency. The possible threat to the 
member of the Executive is determined by Security Advisory Service. 



6.60.6. Her evidence was confirmed during the investigation by Major-General 
(Retired) T Kulu, who at the relevant time was the Head: Government 
Security Regulator of the SAPS. Brigadier Adendorff reported to her on the 
security evaluations that were conducted. Maj. Gen. Kulu left the employ of 
the SAPS in November 201 0. 



6.60.7. The security evaluation includes a site visit of the residence concerned and 
the advice is informed by the applicable training of the security advisors in 
such matters, benchmarking exercises and research on the latest security 
measures that are available. 



6.60.8. Security Advisory Service also based its security advice on a standard that is 
contained in a document entitled: "Minimum Physical Security Standards" 
(MPSS) and its annexures relating to residences. This is the basic 
documented standard, but depending of the circumstances, deviations may 
be required. 



212 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



6.60.9. She further stated that it was not possible to benchmark the security 
measures required in respect of the President's private residence against the 
security measures that are implemented by other countries as such 
information is not readily available. 



6.60.10. The situation with regard to the President's private residence at Nkandla was 
complicated due to the fact that it consists of several dwellings and not one 
house that would be much easier and cheaper to secure. It was therefore, 
according to Brigadier Adendorff, also problematic to compare the measures 
taken at the private residences of former Presidents Mbeki and Mandela with 
the measures that had to be installed at President Zuma's private residence. 



6.60.1 1. The measures that were recommended by Brigadier Adendorff in respect of 
the President's private residence were based on the MPSS. However, the 
situation at the residence resulted in a number of deviations due to the fact 
that it consisted of several buildings, is located in a rural area and is large in 
scale. 



6.60.12. In her evidence, Brigadier Adendorff further stated that when Security 
Advisory Service visited the private residence of the President on 28 May 
2009, the officials involved found that the residence was in a very remote and 
rural area. The site consisted of a few huts surrounded by a dilapidated 
palisade fence and an ordinary guard hut. There was no running water and 
that the site was very "difficult". 

6.60.13. It was observed that the site was not secure at all and security measures 
were recommended in the evaluation report that was prepared and submitted 
to the Presidency and the DPW. In the opinion of Security Advisory Service, 
the recommended measures would have been sufficient at the time to secure 
the immediate safety of the President at his residence (i.e. before the 



213 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




construction of the three new residences). It was regarded as an "immediate 
fix for an appalling situation". 



6.60.14. At the time of this visit, the SAPS officials based at the residence stayed in a 
building that belongs to the President. Due to the fact that the living 
conditions of the SAPS officials were regarded as very poor and 
unacceptable, it was recommended that the accommodation for the officials 
should be upgraded. 

6.60.15. Brigadier Adendorff further explained that there were discussions about the 



upgrading of the Nkandla Police Station, which would have included barracks 
where the SAPS officials assigned to the President's residence could be 
accommodated. However, this plan never materialized and due to the fact 
that no alternative accommodation is available in the area, accommodation 
had to be constructed as part of the Nkandla project. 



6.60.1 6. At the time of my site visit, it was established that the closest SAPS facility to 
the President's residence is a satellite Police Station in the area with no 
accommodation facilities that is managed by the SAPS in Eshowe. 

6.60.17. Brigadier Adendorff further stated that the DPW was supposed, on receipt of 
the Security Evaluation Report, to consider its recommendations, and to 
design and cost the works accordingly. 

6.60.18. She confirmed that there was a meeting of the SAPS and the DPW with the 



President on the site in August 2009 where the planned security measures 
were explained to him. The discussion was based on the security evaluation, 
dated 28 May 2009. 



214 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.60.19. Security Advisory Services was subsequently informed of the three new 



residences that were to be constructed by the President on the site. The new 
residences had an impact on the security of the premises and a new 
evaluation had to be done. 



6.60.20. After the project commenced, Security Advisory Services became part of the 



Project Team and regularly attended progress meetings on the site. At these 
meetings, they made inputs in respect of the design of the security 
measures. 



6.60.21 . The second security evaluation conducted by Security Advisory Services was 



presented to the Director-General of the DPW on 25 September 2010. It 
contained more extensive measures that had to be implemented and the 
scale of the Nkandla project increased substantially due to the President's 
new residences and the accommodation that had to be constructed for staff 
of the SAPS and the DOD. The fact that the President's private residence is 
in a rural area also had an impact on the security measures that had to be 
implemented. 



6.60.22. I noted that the covering letter of this Security Evaluation Report, signed by 
Maj Gen Kulu and addressed to the Director-General of the DPW and the 
Presidency, under the heading: "SECURITY EVALUATION: ADDITIONAL 
SECURITY MEASURES FOR THE NEW DEVELOPMENT:PRIVATE 
RESIDENCE OF THE PRESIDENT: MR J ZUMA, NKANDLA KWA ZULU 
NATAL" stated, inter alia, that: 

"The owner/occupant is responsible for the implementation of this report to 
ensure that the minimum standard of security is maintained. This office can 
assist during the implementation phase ensuring that the correct standard is 
achieved. " 



215 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



JCjLIC F>EO>TE<:.TOk 



6.60.23. According to the security evaluation reports and Brigadier Adendorff's 
evidence, the safe haven that had to form part of the security measures, was 
a modest facility. Initially, the idea was that it would entail strengthening 
certain rooms of existing buildings. 

6.60.24. However, when the matter was discussed between her and Mr Makhanya, it 
was agreed there should be a central safe haven facility that could be 
accessed by the President from any one of the residences, at the time of an 
emergency. Eventually, it was decided that the ideal would be to put the safe 
haven where it is today. 

6.60.25. Due to the age of some members of the President's immediate family and the 
possible need to remove an injured person with a stretcher underground, it 
was, according to Brigadier Adendorff, decided to provide lifts linked to all the 
residences on the premises. Much of this input came from Mr Makhanya, 
who was designing the features of the Nkandla project. 

6.60.26. Brigadier Adendorff further stated that she was not involved in the 
specifications of the air conditioning systems that were installed in the safe 
haven, which can deal with different kinds of attacks. All that was required 
was fresh air. 

6.60.27. She conceded in her evidence that the safe haven could have been 
constructed as the original modest facility, which would have cost much less. 
She said she was surprised with the facility that was eventually constructed, 
as it amounted to much more than what was required by the SAPS. 



216 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC PISOTCCTOf? 
SOUTH flfPICfl 

6.60.28. Security Advisory Services required fire-fighting capacity on the site, but did 
not prescribe what it should consist of. During discussions with the Project 
Team, it was decided that a fire pool had to be built as a water reservoir. 

6.60.29. Brigadier Adendorff further stated that the President complained about the 
design of the bullet resistant windows that had to be installed in his dwellings. 
Due to his request, the required design was changed. The President's 
concern was confirmed by himself and other witnesses interviewed. In 
essence he did not want a place that reminded him of prison. 

6.60.30. She explained that the new Tuck Shop also had to be fitted with bullet 
resistant windows as it forms part of the outer perimeter fence of the site. 

6.60.31. The perimeter fence had to enclose the whole precinct due to the fact that 
the President could be anywhere on the site at any time. 

6.60.32. Brigadier Adendorff further stated that she was not aware of the provisions of 
the Cabinet Policy that regulates the security measures to be taken at the 
President's private residence at the time of the implementation of the 
Nkandla Project. No indication could therefore be provided whether the 
procedure prescribed by the Policy was complied with by the SAPS, the 
DPW and the Minister of Police. According to her, NIA (State Security 
Agency) was not involved in the Nkandla Project, as prescribed by the Policy. 

6.60.33. She also indicated that the Interdepartmental Security Coordinating 
Committee did not consider the measures that were implemented at the 
President's private residence. 

6.60.34. Certain aspects of the security of the premises, such as the security of the 
Tuck Shop and the fire-fighting measures, were not covered in detail by the 



217 



Secure In Comfort A Report of the March 2014 

Public Protector 



SO-UTI1 111 l.'K.II 



Security Evaluation report. According to Brigadier Adendorff, it was left to the 
designers of the Nkandla project to deal with. 



6.60.35. She also stated that as far as she is aware, the SAPS was never provided 
with a cost estimate of the Nkandla project. The SAPS did not make any 
payments in respect of the project as it was regarded as the responsibility of 
the DPW. 

6.60.36. The Acting Chief of Staff of the Ministry of Police provided me with limited 
access to the copy MPSS during the course of the investigation. 

6.60.37. I could find no indication in Brigadier Adendorff's and Maj General Kulu's 
evidence that they were aware of the fact that the President's private 
residence was declared a National Key Point by the Minister of Police on 8 
April 2010. 

6.60.38. In fact, Maj Gen Kulu stated in this regard that: 

"Whether or not the security upgrades were to be implemented and installed 
in terms of the Cabinet Policy of 2003, and whether they were implemented 
in terms of the said Cabinet Policy fell outside my scope of work, and that 
question cannot be addressed to me. The same applies to whether the 
National Key Points Act, 1980 required the President to pay for the security 
upgrades. That question must be addressed to DPW as the implementing 
agent. " 

6.60.39. Brigadier Adendorff was adamant in her evidence, that according to her, the 
SAPS did apply a proper demand management process as far as its 
requirements for the Nkandla Project was concerned. In this regard, she 



218 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

referred to the two Security Evaluation Reports prepared by her. She also 
persisted in her view that the SAPS had nothing to do with the procurement 
process and was not responsible for determining the costs of the Nkandla 
Project as it was all the responsibility of the DPW. The SAPS, according to 
her, had no role to play in determining whether the project or any part 
thereof, was affordable. In this regard she stated specifically: "It should be 
kept in mind that the security relates to the Head of State." However, she was 
aware of the fact that the DPW would recover the relevant portion of the cost 
that relate to its requirements from the SAPS. 



6.61. The Tuck Shop 



6.61.1.1 It is common cause that at the time when the SAPS conducted its first 
security evaluation at President Zuma's private residence, one of his 
immediate family members was running a small tuck shop business in a 
small rondavel structure on the premises. According to the evidence and 
information obtained during the investigation, she had owned this small 
business for many years, prior to Mr Zuma being appointed as President. 

6.61.1.2 The first SAPS Security Advisory Service Evaluation Report stated in this 
regard that: 

"In order to achieve a safe and secured environment within the premises, the 
existing tuck shop must be relocated from the present position to enable the 
police personnel to maintain proper access control. A new hut (tuck shop) 
must be built closer to the perimeter protection to enable people to buy while 
outside the premises. When this is built, the proposed security measures 
must be taken into consideration." 



219 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.61.1.3 
6.62. 

6.62.1.1 

6.63. 
6.63.1. 

6.63.2. 
6.63.3. 



Mr Rindel explained in his evidence during the investigation that, according to 
him, the person who owned the tuck shop could not be deprived of her 
business simply because the DPW had to install security measures at the 
President's private residence. Accordingly, it was decided to relocate the tuck 
shop to form part of the perimeter fencing, as required by the SAPS. 

I observed during my site visit that the new Tuck Shop consists of a small 
room, at the entrance to the premises, which forms part of a larger building 
that houses legitimate security items. From the records of the DPW, the total 
structure, including the security equipment housed in the building cost 
R956 381.16. 

According to Mr Rindel, the cost of the building only amounted to 
approximately R505 000 

The Relocation of the cattle kraal 

During my site visit on 12 August 2013, Mr Makhanya explained that the 
original kraal where the President's livestock were kept had to be relocated 
for security reasons. According to him, its original location would have 
caused interference to the intruder detection systems. However, the original 
location could not be indicated. 

When I met with the President on 11 August 2013, he indicated that he 
requested the building of the kraal as the number of his cattle had increased. 
He also stated that he would be willing to refund the state for the cost 
incurred in this regard. 

I noted that the new kraal has an elaborate design that separate facilities for 
goats, cattle and chickens. It is also linked to an area outside of the perimeter 

220 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



fence by means of an access tunnel (culvert) with a gate that is remotely 
controlled. Having been to Qunu, the rural residence of former President 
Mandela, I noticed the difference in the kraals. 



6.63.4. Mr Makhanya could not explain who was responsible for the ideas that 
resulted in his design of the new kraal. However, during the inspection in 
loco, he advised on the culvert and chicken run, that "this is how it's done in 
England." 

6.63.5. Brigadier Adendorff explained during the investigation that although it was 
not mentioned in the SAPS Security Evaluation Reports, the culvert was 
designed and constructed to "prevent cattle from causing false alarms of 
electronic systems on fence. " 

6.63.6. According to the records of the DPW, the construction of the new kraal was 
included under general site works. It was noted from the records of the DPW 
that the cost estimate of the construction amounted to R1 .2 million. 

6.64. The Swimming Pool, Visitors Centre and Amphitheatre 

6.64.1 . According to Mr Rindel's evidence, it was a requirement of the SAPS and the 
DOD that a reservoir, had to be installed as part of the Nkandla Project to 
ensure that adequate water is available in the event of a fire. Running water 
is not readily available at Nkandla and there is no nearby municipal fire 
brigade. The idea was to have a fire truck on the premises that could be 
filled from the water reservoir. Fire-fighting capability was also regarded as 
necessary due to the fact that the President is transported to his private 
residence by helicopter. The evidence shows that ultimately, the swimming 
pool in addition to the water reservoir was constructed. 



221 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

6.64.2. In her evidence, Deputy Minister Bogopane-Zulu stated that during her 
involvement, she supported the idea of the possibility of building a swimming 
pool, which could be used as a water reservoir and at the same time be 
utilised to teach children of the Nkandla community to swim. She planned to 
get Swim South Africa involved to teach and train children. However, she 
was removed from the project before her idea could be further considered. 



6.64.3. It transpired from the investigation that what initially was supposed to be a 
fire-pool (water reservoir) was converted into a swimming pool. Mr Rindel 
explained that it was decided that as it was a requirement to have a fire-pool, 
to make it aesthetically pleasant as well by building it in the form of a 
swimming pool. 



6.64.4. The Motivations and Cost Allocations Document prepared by R&G 
Consultants on 1 1 March 201 1 indicate that the costing of the fire-pool was 
combined with the cost of parking facilities that had to be built and the 
motivation for these items was stated as follows: 



"i) Fire pool is a ground water storage facility intended for dual purpose. First 
to be used for firefighting in case of emergency. The second use is 
recreational within the homestead. Note: open surface water compared 
with reservoir storage is easily accessed in case of emergency. 

ii) Parking garage is provided in limited space closer to the dwellings 
dedicated for VIP cars for the principal and first lady , "(emphasis added) 



6.64.5. The total cost of the swimming pool and parking garage referred to above 
amounted to R2 819 051.66. Mr Rindel indicated during the investigation that 
the parking garage for VIP cars was required by the SAPS. I noted that this 
was not included in the SAPS Security Evaluation Reports. 



222 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.64.6. According to the records of the DPW the Visitors' Centre also houses a 



legitimate security feature that was identified as necessary in all the security 
evaluations conducted. However, the security feature occupies a small part 
of the double story building that boasts a large visitors' lounge with a sizeable 
balcony overlooking the swimming pool and a paved terrace. One of the 
witnesses interviewed during the investigation stated that the Visitors Centre 
was a requirement of the Presidency. I approached the Director-General of 
the Presidency in this regard in writing on 26 August 2013, and when I finally 
met him in December 2013 he advised that he was not aware of any 
involvement of that nature from the Presidency. 



6.64.7. Brigadier Adendorff stated in her evidence that the Visitors' Centre was not a 
requirement of the SAPS, "but was identified to be used as a holding area to 
allow for screening and processing of a large number of visitors. ". 

6.64.8. Mr Rindel stated that he was aware that the Visitors' Centre was not required 



by the SAPS Security Evaluation Reports. However, it was indicated by the 
SAPS during the implementation of the project as a requirement "to stop 
people from moving over the site unattended." It was designed by Mr 
Makhanya. 



6.64.9. I noticed during my site visit that the swimming pool forms part of an area 



close to the Visitors' Centre that also includes an amphitheatre, which can 
easily accommodate about 100 people, and a lawn area that was flattened 
during the landscaping process to accommodate a marquee tent. My general 
impression was one of an enormous entertainment area that has very little 
connection with issues of security. The answers I got, particularly from the 
officials that participated in the inspection in loco, confirmed this conclusion 
as they kept saying they had to take into account an aesthetic fit to the 



223 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



stature of a President and the President's needs when hosting guests. They 
also kept saying the approach was not different from that taken in official 
presidential residences. 



6.64.10. Mr Makhanya explained during the site visit that the fire extinguisher 
equipment on the site was connected to the swimming pool so that its water 
could be used by the force of gravity in the event of a fire. However, he could 
not provide a satisfactory explanation why a water reservoir, similar to the 
one that was installed for household use would not have sufficed. It was also 
unclear why the same one did not suffice. 



6.64.1 1 . He further submitted that the construction of the swimming pool also required 
the building of a retaining wall as the large amount of water it holds would 
pose a risk of flooding due to the slope on which the residences are located. 
It also resulted in landscaping interventions that had to be implemented to 
deal with the risk of storm water. 



6.64.12. It was explained by Mr Makhanya and the Landscape Architects during the 
investigation that, according to them, the amphitheatre had a dual purpose. 
The lay of the land and the construction of buildings during the project 
necessitated landscaping interventions to deal with storm water and soil 
erosion. As retaining walls and other methods had to be constructed, it was 
decided to construct it in such a way that the area concerned could also be 
used as an amphitheatre for functions. 

6.64.13. However, it was obvious during the site visit that it would not be 
unreasonable to assume that less expensive and elaborate measures could 
have been taken to deal with the storm water containment. Mr Rindel 
confirmed during the investigation that no attempt was made to consider a 
comparison with less expensive landscaping methods. 



224 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



6.65. The relocation of households of neighbours 

6.65.1. Mr Rindel explained during the investigation that four traditional households 
had to be relocated due to the fact that their residential buildings were 
obstructing the new perimeter fence that had to be built as part of the 
Nkandla Project, as advised by the SAPS. Incidentally, this was never 
mentioned in the two SAPS Security Evaluations. As indicated earlier, no 
other SAPS evaluation was conducted. 

6.65.2. The legal team assisting the President during the investigation indicated in its 
presentation on the President's submissions, dated 14 February 2014, that 
these households are not part of the Zuma family and not dependent on the 
President. 

6.65.3. During my site visit, Mr Makhanya explained that the perimeter fence could 
not be built around the dwellings of the affected households as it would have 
impacted on the security of the fence and the detection systems that had to 
be installed. No answers were provided as to why the option of a National 
Key Point Precinct was not considered. In that option, the affected 
households would have remained in the enclosure. 

6.65.4. It appears though that the concern recorded in the motivation documents was 
not the meandering fence but rather a concern raised by consultants 
regarding the proximity of the households. A clue in this regard can be found 
in the cost estimate documents of R&G Consultants, which describe the 
motivation for the relocation as follows: 

"A total of 4 households were found to be too close to the principal's 
homestead when considering safety distances and necessary stand-off 



225 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




distances for potential threats. It was therefore necessary to relocate 4 
households." (emphasis added) 



6.65.5. Each of these households consisted of a number of rondavels, two small 
structures used as kitchen and toilet facilities, and a kraal for farm animals. 

6.65.6. According to the evidence and information obtained, the affected families 



were initially reluctant to move, but after Deputy Minister Bogopane-Zulu had 
discussed the matter with President Zuma, she initiated dialogue with them 
and they eventually agreed, on condition that their households were replaced 
with proper buildings. Deputy Minister Bogopane-Zulu indicated that the 
affected persons are extremely poor and was staying in dilapidated buildings. 
During the site visit we were not allowed to visit those families and were 
advised that there was unhappiness about the relocation. 



6.65.7. The said households were relocated to land outside of the new perimeter 



fences. Mr Rindel further explained, during the investigation, that due to the 
requirements of Building Regulations, which the DPW has to comply with, the 
buildings of the affected households had to be replaced with proper brick and 
mortar structures that complied with the applicable standard. No information 
was provided on the legal or policy authority to effect and fund such 
relocation. 



6.65.8. Deputy Minister Bogopane-Zulu indicated in her evidence that she suggested 



that the DPW enquire from the Department of Human Settlements whether 
the affected persons qualified for RDP Housing. The response that she 
received was affirmative, but that it would take a long time for houses for 
them to be built under that programme. Under the circumstances, the DPW 
went ahead and relocated the four households. 



226 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.65.9. It was also pointed out during my site visit that it would have been 
unreasonable to replace all the buildings of every household with one RDP 
house each. 

6.65.10. During the investigation, it was established that the floor space of a typical 



RDP house is about 40m 2 . According to the Centre for Affordable Housing 
Finance in Africa, it costs between R100 000 and R200 000 to build an RDP 
house, depending on the area and infrastructure that is available, (see: 
www.housingfinanceafrica.org) 



6.65.11. The DPW documents indicated that it was effectively three and a half 



households that had to be relocated. One of the households affected already 
had an existing building in the area where they moved to, hence it was 
regarded as half of a relocation. 



6.65.12. The total floor space of the households that had to be relocated that had to 



be constructed to put them in the same position in respect of their 
accommodation amounted on average to 306m 2 per household. It was 
therefore much larger than the average RDP house. 



6.65.13. Substantial earth and site works also had to be done to relocate these 
households due to the slope of the land. 

6.65.14. The records of the DPW show that the new structures built for the 



households included items such as electricity and water installations and 
connections, sewerage connections, built in cupboards, roads, fences paving 
and a kraal for every household. The total number of buildings that each 
household consisted of was replaced in each case. Linking the houses to the 
electrical and water infrastructure also added to the expense. 



227 



Secure In Comfort 



A Report of the 
Public Protector 




6.66. 
6.66.1. 

6.66.2. 
6.66.3. 



6.67. 
6.67.1. 



The total cost of the relocation of the four households, including the 
demolition of their old houses amounted to R7 921 517.44. 

Roads, Paving and Walkways 

From the records of the DPW it was established that roads, walkways and 
paving in the amount of R12 826 158.04 were constructed at state expense 
as part of the Nkandla Project. 

The roads included an access and patrol roads as well as the road from the 
dwellings to the helipads. 

During my site visit, I noted that the paved roads are rather wide in certain 
areas to the extent that two cars can easily pass each other. It could not be 
explained why it was necessary to build paved roads of such an elaborate 
nature at a private residence. It was also noted that the areas around the 
entrance gate and swimming pool was extensively paved, whilst the 
reasoning for such measures could not obviously be linked to issues of 
security. 

Safe Haven 

As already indicated, the SAPS required the construction of a safe haven for 
the protection of the President in an emergency. Despite the original 
recommendation by SAPS requiring a very modest structure costing about 
half a million Rand, the facility that was eventually built ended up being more 
elaborate and initially cost about R8m with DPW having paid according to the 
DPW records, R19 598 804, by the time this investigation was concluded. 



228 



Secure In Comfort 



A Report of the 
Public Protector 




6.67.2. 

6.68. 
6.68.1. 



6.68.2. 
6.68.3. 



The records also show that more essential work still needed to be done at an 
additional cost. 

Mr Rindel indicated in his evidence that the discussions relating to the 
placing of the safe haven underground instead of on the surface took place 
between the SAPS and Mr Makhanya. 

Staff Accommodation: 

Mr Rindel and Brigadier Adendorff explained during the investigation that it is 
a requirement that the President's private residence is always protected by 
members of the SAPS. When he visits the residence, the accompanying 
protectors and staff members of the DOD responsible for the transportation 
and medical care of the President also require accommodation. It was 
therefore, according to them, necessary that the bachelor flat units had to be 
constructed to accommodate these staff members as there is no alternative 
accommodation in the area, due to its remote rural location. The total cost of 
this accommodation, which included a laundry facility was R17 466 309.67. 

During our site visit, we noted that all the units were not ready for occupation 
and that some of the staff members were still staying in the park homes 
installed as temporary accommodation. Mr Makhanya said the final 
completion of the units was suspended due to the investigations on the 
Nkandla Project. 

We also noted that each of the units consists only of one room, including an 
area for a kitchen, and a small bathroom and that it is not fit even for a small 
family. 



229 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



6.68.4. When engaged about the future of the R17 million settlement, the answers 
suggested that no one had thought that far when the investment was made. 

6.69. Further Comments from the Deputy Ministers 

6.69.1. Deputy Minister Bogopane-Zulu 

6.69.1 .1 Ms H Bogopane-Zulu served as the Deputy-Minister of Public Works from 1 1 
May 2009 to 24 October 2011. Currently, she is the Deputy Minister of 
Women, Children and Persons with Disability. 

6.69.1.2 When she was interviewed during the investigation, Deputy Minister 
Bogopane-Zulu explained that at the time of her appointment as the Deputy 
Minister of Public Works, she had nothing to do with the Prestige Portfolio of 
the DPW under which the Nkandla project was implemented. 

6.69.1.3 She only got involved in the Prestige Portfolio from 15 November 2010 to 7 
March 2012 by means of a delegation of responsibility by the "new" Minister, 
Ms G Mahlangu-Nkabinde. 

6.69.1.4 Deputy Minister Bogopane-Zulu understood the delegation to mean that she 
had full authority over the Prestige Portfolio and had to brief the Minister on 
her involvement. 

6.69.1 .5 However, this was denied by former Minister Mahlangu-Nkabinde that stated 
during her interview that the Deputy Minister was actively involved in the 
Nkandla project at the time that she took office on 1 November 201 and that 
she was reporting on it directly to the Presidency. I raised this with the 
Director-General of the Presidency on 26 August 2013, but he could not 



230 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

confirm it. Deputy Minister Bogopane-Zulu also denied this and provided me 
with a copy of her delegations from former Minister Doidge, which did not 
include the Prestige Portfolio. She also denied that she reported to the 
Presidency on the Nkandla Project 



6.69.1.6 This evidence of Minister Mahlangu-Nkabinde was inconsistent with records 
of the DPW that indicate that the Deputy Minister was only introduced to the 
Project Team and her involvement explained on 30 November 2010. 



6.69.1.7 Deputy Minister Bogopane-Zulu confirmed in her evidence that she 
requested the officials of the DPW to brief her on the Nkandla Project at the 
President's private residence. She then visited the site of the project on 30 
November 2010 together with the Project Team. From the time of her 
involvement, she was chairing the Progress Meetings. 

6.69.1 .8 Her first observation was that the project was far behind schedule. One of the 
issues stalled at the time was the relocation of the households whose 
residences were obstructing the construction of the new security fence 
around the precinct. Others were the delay in the manufacturing of the 
perimeter fence and the installation of bullet resistant glass in the President's 
private dwellings. Very limited security was in place at the time and she also 
found the living conditions of the SAPS staff that were stationed at the 
residence to be very unsatisfactory. 



6.69.1.9 The Deputy Minister requested a further meeting to be held with the Project 
Team on 3 December 2010. She discussed the context of several issues, 
such as the accommodation of the SAPS, the Military Clinic and the helipads 
with the main contractors and addressed the expedition of the project. 



231 



Secure In Comfort 



A Report of the 
Public Protector 




6.69.1.10 She wanted to ensure that the helipads could be used by civil aviation after 
the President's term expired and therefore requested the involvement of the 
aviation authorities. 

6.69.1 .1 1 The next meeting that she attended was on the 7th of December 2010. The 



financial issues of the project were discussed. She also requested to be 
informed by the meeting whether the President was briefed on the Nkandla 
Project on what was happening at his private residence. The response that 
she received was that the President was supposed to be briefed by the DPW 
and Mr Makhanya. 



6.69.1.12 Deputy Minister Bogopane-Zulu stated that she raised her concern in this 



regard with the Minister of Public Works because it was her understanding 
that the implementation of the Nkandla project involved shared cost, i.e. that 
certain items would have to be paid for by the President and that he should 
be informed accordingly in advance so that he could indicate whether it was 
acceptable to him. 



6.69.1.13 When she eventually met with the President in December 2010, he 
complained about the delay in finalizing the project. 

6.69.1.14 She briefed the President on the project and he explained his unhappiness 



about a number of issues relating to the security measures. The President 
specifically complained about the nature of the bullet resistant windows, 
which reminded him of the time of his incarceration. 



6.69.1.15 Deputy Minister Bogopane-Zulu informed Brigadier Adendorff and Lt Gen 
Ramlakan, that the President wanted to discuss the matter with them. She 
did not attend the meeting, but was subsequently informed that the President 
had raised his dissatisfaction over the bullet resistant windows. 



232 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.69.1.16 Deputy Minister Bogopane-Zulu also raised the relocation of certain 



households with the President. His response was that he has known the 
people involved all his life. She arranged a discussion with the affected 
people who indicated that they were willing to move on condition that the 
State should provide them with housing. They are very poor and their 
rondavels were falling apart. 



6.69.1.17 She requested officials of the DPW to enquire from the Department of 



Human Settlements whether the persons concerned qualified for RDP 
Housing. The response was that they do qualify, but that the process would 
take long. In the mean-time, houses had to be built for them as they could not 
be left without accommodation. She was removed from the project before 
she could ensure that this initiative was taken further. 



6.69.1.18 She also considered the initial designs of the Military Clinic, which according 



to her observations was too small. As the community in the area does not 
have a clinic, she suggested to the project team that she would discuss the 
matter with the Minister of Health and the President to find out whether it 
"would be okay that the clinic also serves the community." Her idea was 
referred to a "clip-on" facility. 



6.69.1.19 Lt Gen Ramlakan was opposed to the idea. However, she discussed it with 



the President. He stated that he wanted the community to benefit. According 
to her, President Zuma said: "If they give you grief, tell them they must come 
and talk to me." 



6.69.1.20 The Deputy Minister consequently informed the Project Team that she had 
obtained approval from the President that the clinic must serve the 



233 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



community. The associated security issues had to be considered and 
designed. 



6.69.1 .21 She then discussed her idea with the Minister of Health who indicated that he 
would consider the matter. She further requested the Project Team to ensure 
that the community component of the clinic not be paid for under the security 
project of the DPW. 



6.69.1.22 As far as the supply of water for fire-fighting emergencies was concerned, 
Deputy Minister Bogopane-Zulu suggested that should a swimming pool be 
built, children in the community could be taught to swim. She requested that 
a cost comparison between a static water reservoir and a swimming pool be 
made and was informed that it amounted to R50 000. She discussed this with 
the President, and he agreed. She also said Swimming South Africa was also 
contacted in this regard. 



6.69.1.23 It was emphasized by Deputy Minister Bogopane-Zulu in her evidence that 
she also made suggestions regarding the sharing of electricity connections 
and the construction of a waste management facility with the community in 
the immediate area of the President's residence. However, none of her 
developmental ideas were eventually implemented. 



6.69.1.24 At a progress meeting with the Project Team she requested an 
apportionment of cost document to be prepared on what had already been 
implemented and also in terms of the estimated cost of what still had to be 
implemented, to enable her to discuss the matter with the President. This 
was because she was informed that it was a "shared cost project' . 

6.69.1.25 She indicated during her evidence that it took a very long time for the 
document to be compiled. Due to her removal from the project, she never 



234 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




had an opportunity to discuss the contents of the document with the 
President and does not know whether it was ever submitted to him. 



6.69.1.26 The Deputy Minister was not aware of the Internal Memorandum relating to 



the apportionment of costs, addressed to the Minister of Public Works by Mr 
Khanyile on 28 March 201 1 , as by that time she had already been removed 
from the Nkandla Project. Former Minister Mahlangu-Nkabinde denied during 
the investigation that she ever saw this document and indicated that she was 
not involved in any discussions of considerations in regard to the 
apportionment of costs. Mr Rindel could not explain why it did not reach the 
Minister or Deputy Minister as he personally hand delivered the document at 
DPW head office. 



6.69.1.27 Deputy Minister Bogopane-Zulu further explained that after the progress 



meeting in February 2011, she attended a conference in New York. On her 
return on 1 1 March 201 1 , she was informed directly and in writing by Minister 
Mahlangu-Nkabinde that she was removed from the Prestige Portfolio. She 
approached the Minister and asked her for the reasons for her removal, but 
the Minister refused to discuss the matter with her. 



6.69.1.28 When I discussed this with her during the investigation, Ms Mahlangu- 



Nkabinde only confirmed that officials of the DPW raised certain concerns 
with her about the Deputy Minister's involvement in the Nkandla Project and 
that she had discussed the matter with her. Deputy Minister Bogopane-Zulu 
denied that Ms Mahlangu-Nkabinde discussed the matter with her. However, 
she stated that rumours of discontent among officials did reach her informally 
upon her arrival from New York, "but these were understood to have been 
unhappiness that my persistent insistence on driving costs down did not sit 
comfortably with some officials." 



235 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

6.69.1 .29 During her interview, Deputy Minister Bogopane-Zulu confirmed that she also 
signed the letter of Minister Mahlangu-Nkabinde addressed to the President 
on 5 November 2010, providing him with a progress report on the Nkandla 
project. 

6.69.1 .30 When she was afforded the opportunity, in terms of section 7(9) of the Public 
Protector Act, to respond to the information and evidence obtained during the 
investigation that may appear to implicate her, Deputy Minister Bogopane- 
Zulu further explained her involvement in the Nkandla Project, inter alia, as 
follows: 

"The Department of Public Works implements infrastructural developments 
including acquisition of properties for and on behalf of various national 
departments. It happens in some instances that implementation of a prestige 
project falls behind schedule or the expenditure soars to unpredicted levels. 
The Minister may in appropriate circumstances deem it fit and imperative that 
there should be Executive intervention and oversight in order to unlock 
whatever delays there can be in the implementation of a project and to 
control an arrest escalating costs. Implementation of a security upgrade at 
the President's house in Nkandla was running behind schedule and there 
was concern over the mounting cost; hence political intervention became 
imperative. 

I participated in project team meetings (including site meetings) to familiarise 
myself with the challenges cause by the significant delays as well as cost 
escalation on the project, and which resulted in the need to strengthen 
political oversight, so as to enable me to provide leadership; 

I provided leadership in these meetings by exploring alternatives which could 
be considered to bring costs down, to accelerate implementation and to 



236 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

extract more value for money by looking at possible ways the surrounding 
communities could benefit from the public investment. I also requested an 
apportionment of cost between the state and the property owner, and raised 
concerns with regards (sic) significant challenges with the overall 
management of security on the project. 



I at no stage issued any directives with regards either (sic) 
changing/expanding the scope of work or the procurement process to be 
followed. 



I did not play a part at all in the nomination and appointment of service 
providers to provide services in the Nkandla Project at the inception or during 
its continuation. " 



6.69.1.31 Deputy Minister Bogopane-Zulu referred to the appointment of contractors 
for phase 2 of the Nkandla Project as follows: 

"/ did not influence the further appointment of the contractors to remain on 
site to carry out works in Phase 2 of the construction. I submit therefore that 
the propriety or otherwise of the retention of the service providers for Phase 2 
of the project shall be based on the first appointment and not on the 
comments I am alleged to have made. The Public Officials concerned were 
not influenced by my comments at all and they were going to retain the 
service providers on the same basis on which they appointed them in the first 
place. " 



6.69.1.32 The Deputy Minister denied that her involvement crossed the line between 
providing political leadership and interfering with administrative processes. 
She stated that: 



237 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



"In my view that the difference between political leadership and political 
interference can be explained as follows: 



Political leadership focuses on providing strategic direction, including 
intervening where processes and projects have been red-lined as in trouble, 
without interfering with administrative decision-making processes. 



Political interference in contrast occurs when an Executive Authority acts, 
hinders, obstructs, or impedes delivery, and/or issues instructions and 
directives which are administrative in nature, including the process of 
procurement. " 



6.69.1.33 The Deputy Minister also denied that she reported on the Nkandla Project 
directly to the Presidency. 



6.70. The Appointment of a Private Project Manager 



6.70.1. The minutes of a meeting of the RBAC held on the 17 September 2010 
indicate that the appointment of a private Project Manager by means of a 
nominated procurement process was approved. Ramcon Project 
Management Services was subsequently appointed. At the time, Phase 1 of 
the Nkandla Project was already underway and the design stages were 
complete. The appointment was shortly after Minister Doidge became 
involved in the project. 



6.70.2. Mr R Samuel, former Deputy Director-General of the DPW, indicated in his 
evidence that it was decided to appoint a private Project Manager as it was 
clear that the DPW Project Manager was struggling and that there were 
serious delays in finalizing the implementation of the Nkandla Project. 



238 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

6.70.3. Mr Rindel, agreed that there was a need to appoint a private Project Manager 
to manage and coordinate all the different aspects of the Nkandla Project on 
the site. He explained that due to the fact that he is based in Durban, it was 
not possible for him to manage every aspect of a project of this scale, on a 
day to day basis. 

6.70.4. During the investigation, Ramcon's manager stated that its brief was to 
manage the different phases of the implementation of the Nkandla project as 
far as construction was concerned. 

6.70.5. The role of the private Project Manager was to assist the Project Team with 
the management and coordination of the different construction processes 
that were taken place at the same time on the site. It also had to ensure the 
management of quality control and compliance with design specifications by 
the professional team involved and compliance with deadlines. 

6.70.6. Mr Rindel was providing direction and guidance as the client and taking 
major decisions in respect of the Nkandla Project. 

6.70.7. At the time when Ramcon got involved there was a substantial amount of 
coordination that had to be done as the project was fast-tracked. The project 
was not well managed and already experienced serious delays in terms of its 
set deadlines. "There were a lot of struggles" . 

6.70.8. Ramcon together with the rest of the project team provided presentations on 
the progress made to the regular progress meetings, some of which were 
chaired by the Minister or Deputy Minister of Public Works. 

6.70.9. According to the DPW records, the total amount paid to Ramcon by the DPW 
by the end of the investigation was R5 092 477.73. 

239 




Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



— i-v 



6.71. Landscaping 

6.71.1. Messrs Rindel, Makhanya and Crafford explained during the investigation 
that the construction works that had to be implemented on the premises 
resulted in a rigorous intervention of the landscape and vegetation that had to 
be rehabilitated, to bring the site back to normal. This included that attention 
had to be given to the flow of storm water due to the steep lie of the land. 

6.71.2. According to them, it was therefore necessary to employ the services of a 
Landscape Architect to design the landscaping works that were required. Uys 
and White Landscape Architects were appointed as a subcontractor to the 
Principal Agent (Mr Makhanya) during the beginning of 2010, with the 
approval of the DPW. 

6.71.3. The relevant architects of Uys and White involved in the Nkandla Project 
were interviewed during the investigation. According to Mr Uys, his firm had 
previously been involved in security projects, such as the Hoedspruit Air 
Force Base. 

6.71.4. Most of their brief in respect of the Nkandla Project was given to them 
verbally by the DPW and Mr Makhanya at briefing meetings on the site. It 
related mainly to environmental control (storm water) and the replacement of 
facilities, such as the vegetable garden and the relocation of the kraal. 

6.71.5. The visual access to the site, for example by a sniper, also had to be 
considered in respect of the kind of vegetation that was used and the landfill 
that had to be applied in the design of the landscape. 



240 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC 

SOUTH flfPICfl 

6.71.6. Initially, Mr Crafford considered and approved their designs, but as the 
project was implemented on the ground, the supervision and liaison were 
mainly done by Mr Makhanya. 

6.71 .7. At the time when the Landscape Architects got involved on the site, extensive 
construction works in terms of buildings and roads had taken place and the 
site was, according to them, extremely eroded. It required substantial land 
rehabilitation and in some cases retaining walls and banks to deal with storm 
water drainage. It also included seeding, vegetation and the planting of 
lawns. Lawns were planted as it is the cheapest way of controlling soil 
erosion. 

6.71.8. There was no environmental legislation that the Nkandla Project had to 
comply with in the process of the design of the landscaping. A professional 
opinion was obtained in this regard. 

6.71.9. The initial master plan design of the Nkandla Project in respect of 
landscaping was, according the Landscape Architects, substantially reduced 
due to the costing. However, the main footprint of what had to be done 
remained the same. The original estimated cost of the landscaping was 
about R19 million. The actual final cost was much lower. 

6.71.10. Mr Uys and his colleagues indicated during their evidence that much of what 
was originally designed in terms of the landscaping, was not implemented, 
such as the pergolas, light fittings, and feature elements. They expressed the 
view that all those things that would have made the site "special" and created 
an ambiance of being "stately" were excluded. 



241 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



6.71.11. According to Uys and White Landscape Architects, the following table 
represents a comparison between the planned landscaping and what was 
actually implemented: 



242 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 










Forecast based on costing 
Revision no 7 


Actual certified to date ■ 
Phase 1 - Bonelena 


Actual certified to date - Phase 
2 Money Mine 





Preliminary & General 




R 430 000.00 


R 139 120.00 


1 


Zone A: Arrival Node 


R 532 250.00 




R 120 488 30 


2 


VISITORS CENTRE 


R 1 315 425.00 




R 330 670.14 


3 


SOCIAL NODE 


R 2 063 340.00 




R249 157.01 


4 


RESIDENTIAL ARRIVAL 


R 1 232 820.00 




R 114 670.16 


5 


ZONEC: DWELLINGS 


R 4 466 400.00 




R 437 551.06 


6 


EXISTING HOMESTEAD 


R 398 400.00 






7 


FACILITIES - Military Clinic 
etc 


R 283 850.00 




R 16764.00 


8 


RING ROAD 


R 585 400.00 


R 480 601.00 




9 


REHABILITATION 


R 2 475 875.00 




R 216 680.87 








Forecast based on costing 
Revision no 7 


Actual certified to date - 
Phase 1 ■ Bonelena 


Actual certified to date • Phase 
2 Money Mine 


10 


HELIPADS 


R 135 000.00 






11 


CEREMONIAL ROUTE 


R0.O0 






12 


POLICE RESIDENCE 


R1 312 546.00 


R 1 758 769.78 




13 


OTHER 


R 3 872 010.00 






14 


MAINTENANCE 




R227 681.25 


R 208 769.00 


15 


IRRIGATION 






R44 971.04 


16 


EXTRAS & REPLACEMENTS 






R 51 3 728.36 


17 


Extra from Bonelena 
contract completed by 
Money mine 




R 67 662.22 






Total Prolect 


R 18 673 316.00 


R 2 964 714.25 


R 2 392 569.94 




Total Prolect 


Planned 
R 18 673 316.00 


Actual 
R 5 357 284.19 


UYS & White - Total certified 
to date 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

6.71.12. As far as the apportionment of costs for landscaping perspective is 
concerned, there were in the view of the Landscape Architects no "nice to 
have's" that had to be paid for by the State. Where such items were included 
it came about because of the view that it was a prestige project and the 
President's house. 

6.71.13. However, Ms Pasley, the DPW's Chief Quantity Surveyor and other officials 
of the DPW interviewed during the investigation, held the view that the nice to 
have's had to be paid for by the President if he wanted them. The Landscape 
Architects indicated during the investigation that they accepted that the 
President would be consulted on this, but were never informed whether the 
President actually wanted those items and consequently, it was taken out of 
the implementation. It should be noted that there was initially no discussion 
on the separation of the costs of the Nkandla Project. 

6.71.14. As far as the contents of the letter from Mr Khanyile addressed to the 
Minister of Public Works on 28 March 201 1 referred to above are concerned, 
the Landscape Architects explained during the investigation that their master 
plan was broken down into zones. 

6.71.15. The reference to the "social node" in the said letter related to an area that 
was flattened to a space that could be utilized for a marquee tent. 

6.71.16. The documents obtained from the Landscape Architects in this regard 
indicate that the brief in respect of the social node was to: "create function 
area linked to swimming pool terrace." Mr Rindel explained that the 
discussions that took place among the officials in this regard indicated that 
the amphitheatre and terraced pavilion could be used for functions "for which 
the NDPW (National DPW) would also be responsible." 



244 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.71.17. According to the Landscape Architects, there was a very negative level 
difference between the social node and the visitor's area. A terrace seated 
zone was created as the best way to connect the spaces. It was their 
suggestion to create the so called "amphitheatre", which was actually a 
series of retaining walls, to break up the level differences. 

6.71 .1 8. Throughout their involvement in the project, the Landscape Architects got the 
sense that Mr Makhanya was keeping the President informed of 
developments and that he submitted their drawings to him. Mr Rindel 
confirmed that Mr Makhanya and Deputy Minister Bogopane-Zulu reported to 
the Project Team that they had discussed the landscaping with the President. 

6.71.19. They further explained that their landscape designs were implemented by 
two contractors, i.e. Moneymine and Bonelena. 

6.71.20. According to their explanation, the total measurement of the site that had to 
be subjected to landscaping interventions was 6.1 hectares, which can be 
converted into 8.6 international soccer pitches. 

6.71 .21 . The total amount of Uys and White's professional fees was R1 974 457.37. It 
was based on the professional fee guideline of the South African Council for 
the Landscape Architectural Profession and calculated on drawings in 
respect of the original project value of R18 673 316, and not on what was 
actually implemented. 



6.71 .22. The actual total cost of the landscaping was as follows: 







R 5,357,289.96 


R 1,974,457.37 


TOTAL 


R 7,331,747.33 



Figure 1 1: Total Cost of Landscaping in the Nkandla Project 

245 



Secure In Comfort 



A Report of the 
Public Protector 




6.71.23. 



6.72. 
6.72.1. 

6.72.2. 

6.72.3. 
6.72.4. 



During my site visit on 12 August 2013, I noted that substantial landscaping 
works had been performed on the premises. As indicated above, the amount 
of paving, retaining walls and the so called social node or entertainment area 
specifically stood out as items that probably required better consideration in 
terms of alternative and more cost effective measures. It was also noted that 
the kraal that was constructed included separate areas for goats and cattle 
and even chicken nests and a culvert with a remote controlled gate. As I 
have already stated, Mr Makhanya could not explain whose idea the design 
was and whether alternatives were considered. 

The Apportionment of Costs 

As indicated earlier in this report, Deputy Minister Bogopane-Zulu stated in 
her evidence during the investigation that shortly after she got involved in the 
Nkandla Project, she requested the Project Team to prepare cost 
apportionment documents to be submitted to her. 

The reason for her instruction in this regard was that she was told right from 
the start that the Nkandla Project was "cost-shared", which, to her 
understanding, meant that the President would be responsible for some of 
the cost incurred during the project, due to the fact that it was implemented at 
his private residence and that some items did not relate to security. 

She explained that her intention was to discuss the apportionment of the 
estimated costs with the President so that he was not later surprised by it and 
could indicate whether or not he agreed with certain items. 

Mr Rindel and other witnesses interviewed during the investigation confirmed 
that a cost apportionment exercise was done with the inputs of the 
professional team of consultants. They further stated that every item was 



246 



Secure In Comfort A Report of the March 2014 

Public Protector 



v - 1 1 1 I I III :.■!'. II 



debated and a decision then taken as to whether the estimated cost would be 
for the DPW or the President or whether it should be shared and, if so, to 
what extent. 



6.72.5. From the records of the Department of Public Works obtained during the 
investigation, it was found that R&G Consultants was requested to record the 
cost allocations as agreed upon by the professional team in a document. This 
document is titled: "DURBAN PRESTIGE PROJECT A: MOTIVATIONS AND 
COST ALLOCATIONS" and dated 1 1 March 201 1 . It tabled the appropriation 
of the estimated costs as follows: 



247 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 , 




1 












Safe Haven and Related Installations* 


1 & 2 


R 14,033,701.30 


R 14,033,701.30 




2 


20 Residential Staff Houses and Laundry Facility 


2 


R 17,055,543.00 


R 17,055,543.00 




3 


Relocation of Households 


1 


R 7,983,735.62 


R 7,983,735.62 




4 


Military Clinic and Service area, Clip On & SAPS Garages 


2 


R 11,316,167.25 


R 11,316,167.25 




5 


Visitors Centre with space for a Security Service* 


2 


R 7,562,141.06 


R 7,562,141.06 




6 


Multipurpose security room also housing a Tuckshop 


1 


R 494,893.80 


R 494,893.80 




7 


Guard House 1 


1 


R 2,293,801.31 


R 2,293,801.31 




8 


Guard House 2 & 3 


2 


R 1,068,080.30 


R 1,068,080.30 




9 


Crew Pavilion 


2 


R 1,633,298.00 


R 1,633,298.00 




10 


Sewer Pump Station 


2 


R 616,138.00 


R 616,138.00 




11 


Fire Pool and Parking 


2 


R 2,640,679.60 


R 2,380,011.56 


R 260,668.04 


12 


Sewer Treatment Plant 


1 


R 756,409.48 


R 756,409.48 




13 


Booster Pump Station 


1 


R 382,337.13 


R 382,337.13 




14 


Key installations to Private Residences 


1 


R 4,225,820.00 


R 4,225,820.00 




15 


Key installations to existing Residences 


2 


R 315,000.00 


R 315,000.00 


- 


16 


Refuse area 


2 


R 1,715,000.00 


R 1,715,000.00 




17 


Fire Truck Garage 


2 


R 365,000.00 


R 365,000.00 




19 


Cattle Culvert 


1 


R 1,200,000.00 


R 1,200,000.00 




20 


Temporary Mobile park homes 


1 


R 2,137,190.00 


R 2,137,190.00 




21 


Stabilisation of existing SAPS park homes 


1 


R 37,158.00 


R 37,158.00 




22 


Incoming Supply Power Upgrade and overhead Lines 
Relocations 


1 


R 773,624.00 


R 773,624.00 




23 


Reticulation during negotiated contract 


1 


R 55,000.00 


R 10,000.00 


R 45,000.00 


24 


Reticulation during Emergency Contract 


1 


R 701,621.60 


R 701,621.60 




25 


Reticulation during Phase 2 contract 


2 


R 900,000 


R 890,000.00 


R 10,000.00 


26 


Standby Generator and Fuel Tank 


2 


R 661,219.00 


R 661,219.00 





248 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 J 



P 















27 


Security and Area Lighting 


2 


R 490,835.00 


R 490,835.00 




28 


Lightning Protection 


2 


R 450,000.00 


R 300,000.00 


R 150,000.00 


29 


Temporary Generator 


1 


R 267,250.00 


R 267,250.00 




30 


Outer Perimeter Fence 


1 


R 5,994,724.59 


R 5,994,724.59 




31 


Inner High Security Core Fence 


1 


R 8,303,045.18 


R 8,303,045.18 




32 


CCTV Camera Installation 


2 


R 1,885,000.00 


R 1,885,000.00 




33 


Kinematic Fence Detection System 


2 


R 910,000.00 


R 910,000.00 




34 


Fire detection 


2 


R 1,800,000.00 


R 1,800,000.00 




35 


Fuel Trailer 


2 


R 460,000.00 


R 460,000.00 




36 


Road 1 


1 & 2 


R 2,717,017.60 


R 2,717,017.60 




37 


Road 2 


1 & 2 


R 622,810.18 


R 622,810.18 




38 


Road 3 


1 & 2 


R 585,955.28 


R 585,955.28 




39 


Road 4 


1 & 2 


R 455,616.30 


R 455,616.30 




40 


Road 5 


1 & 2 


R 1,467,397.72 


R 1,467,397.72 




41 


Road 6 


1&2 


R 710,595.58 


R 710,595.58 


_ 


42 


Reticulation (Sewer, Water, Domestic, Fire Protection) 


1 & 2 


R 3,451,543.05 


R 3,451,543.05 


- 


43 


Steel Reservoir 


1 


R 290,894.45 


R 290,894.45 


- 


44 


Helipads 


1 & 2 


R 4,855,090.24 


R 4,855,090.24 


- 


45 


General landscaping around helipad 


1&2 


R 1,102,100.00 


R 1,102,100.00 


- 


46 


Builders work 


1 & 2 


R 1,200,000.00 


R 1,190,000.00 


R 10,000.00 




Detailed Landscaping: 










47 


Zone A - Arrival Node 


2 


R 532,250.00 


R 489,750.00 


R 42,500.00 


48 


Visitors' Centre with space for Security Services 


2 


R 1,315,425.00 


R 1,235,425.00 


R 80,000.00 


49 


Social Node 


2 


R 2,063,340.00 


R 884,655.00 


R 1,178,685.00 


50 


Residential arrival 


2 


R 1,232,820.00 


R 670,100.00 


R 562,720.00 


51 


Zone C - Dwellings 


2 


R 4,466,400.00 


R 1,166,236.00 


R 3,300,164.00 


52 


Existing Homestead 


2 


R 398,400.00 


R 231,400.00 


R 167,000.00 



249 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 J 



P 



iOuni Hi men" 















53 


Facilities - Military Clinic etc. 


2 


R 283,850.00 


R 283,850.00 




54 


Ring Road 


2 


R 585,400.00 


R 585,400.00 


_ 


55 


Rehabilitation 


2 


R 2,475,875.00 


R 1,975,875.00 


R 500,000.00 


56 


Helipads 


2 


R 135,000.00 


R 135,000.00 


- 


57 


Ceremonial Route 










58 


Staff houses 


2 


R 1,312,546.00 


R 1,312,546.00 


- 


59 


Other 


2 


R 1,280,010.00 


R 1,104,500.00 


R 175,510.00 




SUBTOTAL 




R 135,024,749.62 


R 128,542,502.58 


R 6,482,247.04 


ADD 


Preliminaries 




R 14,325,703.75 


R 13,353,366.69 


R 972,337.06 




SUBTOTAL 




R 149,350,453.37 


R 141,895,869.27 


R 7,454,584.10 




Contingencies 




2,423,637.52 


2,200,000.00 


223,637.52 




SUBTOTAL 




R 151,774,090.89 


R 144,095,869.27 


R 7,678,221.62 




Pre Tender Escalation (3months @3.8% p. a) Applicable to 
Lift and Security Values Only 




R 2,293,115.02 


R 2 293 115 02 

1 1 C— j i— —J j -i- -I- — ' m \J t— 






SUBTOTAL 




R 154,067,205.91 


R 146,388,984.29 


R 7,678,221.62 




Post Escalation (9 months @ 6.5% p. a) 




R 4,506,465.77 


R 4,281,877.79 


R 224,587.98 




SUBTOTAL 




R 158,573,671.68 


R 150,670,862.08 


R 7,902,809.60 




Professional fees calculated on pro Rata basis (18.23%) 




R 28,907,980.35 


R 27,467,298.16 


R 1,440,682.19 




SUBTOTAL 




R 187,481,652.03 


R 178,138,160.24 


R 9,343,491.79 




VAT @ 14% 




R 26,247,431.28 


R 24,939,342.43 


R 1,308,088.85 




TOTAL ESTIMATED CONSTRUCTION COST 




R 213,729,083.31 


R 203,077,502.67 


R 10,651,580.64 



Figure 12: Cost Apportionment for the Nkandla Project 
*Wording modified to address security concerns 



250 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.72.6. According to Deputy Minister Bogopane-Zulu, she never received this 



document due to the fact that she was removed from the Nkandla Project 
subsequent to her request for it to be compiled. It appears the document has 
disappeared without trace. 



6.72.7. The findings contained in this document were conveyed to the Minister of 
Public Works by Mr Khanyile in an Internal Memorandum addressed to her 
on 28 March 2011, under the heading: "DISCUSSION OF 
APPORTIONMENT OF COSTS BETWEEN STATE AND PRINCIPAL". The 
aim of the memorandum was stated as: 



"...to provide all the applicable information to Top Management in line with 
the apportionment of cost between the State's responsibility and Private (cost 
to the owner). " 



6.72.8. The Memorandum indicated that the estimated scope of works was divided 
as follows: 



"Public (State) portion: R203 079 677. 18 
Private (Owner) portion R10 651 580.64 

The scope of the works included in the Public (sic) is approved and agreed in 
the meeting held in HO on 10 March 2011 and is in the process of being 
implemented and shall be concluded in line with the mandate given to the 
NDPW. 

The portion included under "Private" required additional attention before this 
can be implemented as it falls outside the scope of security measures. 
Please note that the implementation of some of these issues was 
unavoidable and some had already been completed. 



251 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




It was agreed at that meeting that the Department cannot implement any of 
the works included in the indicated above without the written instructions from 
Top management to do the same. This is a precaution that must be taken as 
the works falls outside the mandate given to the Department. 

It is proposed that the works included herein be discussed between Top 
Management and Ministry and guidance be given to the way forward with 
these issues. It may be necessary to discuss these issues with the Principal 
as the financial implication directly affects him (He may want to implement 
these issues himself without the interference of the Department or else he 
may want to opt to reimburse the Department after we complete the same .) 



6.72.9. Mr Khanyile recommended in his memorandum to the Minister: 



"• That the scope of works falling within the mandate of the Department 
continues as previously instructed. 
• That the scope of works apportioned to the Principal (the President) be 
discussed and guidance be given to the Team pertaining on (sic) the 
implementation thereof before construction will continue." 



6.72.10. Minister Mahlangu-Nkabinde denied during the investigation that she ever 



received this document or discussed the matter of apportionment of cost with 
the President. While the document appears to have disappeared without 
trace, virtually all members of the executive met or interviewed intermittently 
alluded to some of its contents. 



252 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.72.11. Messrs Rindel and Khanyile stated that they never received a response to 
this Internal Memorandum and that they do not know whether it was ever 
presented to the President. 

6.72.12. During the investigation, Mr Rindel and R&G Consultants stated that the 



works that were identified as "private" in the said document, dated 1 1 March 
201 1 , were not implemented, due to the fact that no response in this regard 
was received from the Minister. It should be noted that the biggest portion of 
the estimated costs identified as "private" related to landscaping. 



6.72.13. The evidence obtained during the investigation further indicated that 



members of the DPW professional services team specifically questioned the 
cost apportionment in respect of landscaping and the swimming pool. The 
view was expressed that the scope of landscaping went wider than was 
necessary and that the difference in the cost between the construction of a 
swimming pool and that of an ordinary water reservoir should be paid by the 
President. 

PART E: EVIDENCE ON THE INVOLVEMENT OF THE INDUSTRIAL 
DEVELOPMENT CORPORATION AND ALLEGATIONS OF IMPROPER 
BENEFITS AFFORDED TO THE PRESIDENT'S BROTHERS 



6.73. The Granting of Financial Assistance by the Industrial Development 
Corporation to Bonelena 

6.73.1. As indicated above, Bonelena Construction Enterprise and Projects CC 
(Bonelena) was awarded construction contracts by the DPW for the Nkandla 
project in the amount of R98 292 299. It submitted its first proposal for the 



253 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.73.2. 

6.73.3. 

6.73.3.1 
6.73.3.2 

6.73.4. 
6.73.5. 



project in terms of a nominated procurement procedure to the Regional 
Office of the DPW, on 23 March 2010. 

The contract for the emergency works was awarded to it by the Regional 
Manager on 15 June 2010, in the amount of R19 174 478.52. A further 
contract was awarded to Bonelena for Phase 2 of the Nkandla Project. At the 
conclusion of the investigation it had been paid a total of R78 167 742 of the 
contracted amount. 

The selection criteria applied in the case of Bonelena was whether the 
contractor: 

Had passed the "required NIA clearance" and 

Was registered "at the minimum CIDB grading, being 7GB, 7CE OR 6 GBPE, 
6 CEPE or higher." 

The Internal Memorandum submitted by Mr Rindel to the RBAC, 
recommending that Bonelena be approved as one of the nominated 
contractors stated that it passed the NIA clearance and that it had a CIBD 
grading of 7GBPE. 

The grading process applied by the Construction Industry Development 
Board (CIDB) is prescribed by the Construction Industry Development 
Regulations, made in terms of the Construction Industry Development Board 
Act, 2000. It includes detailed scrutiny of the contractor's financial viability 
and ability to successfully complete construction projects within specified 
ranges. 



254 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.73.6. It was confirmed from the database of the CIDB during the investigation that 
Bonelena was registered from 16 February 2009 and had a grading of 7GB 
PE. The grading of 7GB PE qualified Bonalena, also in terms of the DPW 
SCM Policy, to undertake general building construction projects up to a value 
of R100 million. 

6.73.7. During the investigation, it transpired that Bonelena applied to the Industrial 
Development Corporation (IDC) for financial assistance in the amount of R5 
million on 28 May 2010, i.e. after it had submitted an offer to the DPW for the 
first phase of the Nkandla project. 

6.73.8. Ms Nena, the sole member of Bonelena at the time, explained in her 



6.73.9. According to Ms Nena, Bonelena applied for financial assistance before it 
was even aware that the contract in respect of Phase 1 of the Nkandla 
project would be awarded to it. 

6.73.10. The IDC required comprehensive documents from Bonelena in order to 
consider its application, including the: 

6.73.10.1 Business profile; 

6.73.10.2 Financial statements; 

6.73.10.3 Bank statements; 



evidence that Bonelena was experiencing cash flow problems at the time 
when the contract in respect of the Nkandla Project was awarded to it, due to 
its involvement in other projects. Bonelena was growing and required 
funding. This was the reason why it decided to approach the IDC. 



255 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.73.10.4 Tax Clearance Certificate; 

6.73.10.5 Contracts with the DPW and the relevant scope of works in respect thereof; 
and 

6.73.1 0.6 Personal profile and resume of the sole member of the entity, Ms T M Nene. 
6.73.11. It appeared from the documents obtained from the IDC during the 



investigation that the application took quite some time to be considered and 
that further supporting documents were requested during the evaluation 
process. 



6.73.12. The contracts that were awarded to Bonelena by the DPW in respect of the 
Nkandla Project were included to support its application. 

6.73.13. The information and documents provided by the IDC also indicated that 
Bonelena's application was put through its internal processes and detailed 
financial and other diligence tests and investigations. 

6.73.14. The General Counsel & Divisional Executive: Legal & Post Investment 
Monitoring of the IDC explained during the investigation that: 



"At the conclusion of its investigations set out above, the IDC's findings, 
summarized below, were inter alia that the business demonstrated economic 
merit and commercial viability, particularly in that amongst others the 
Applicant: 

• was 100% black female owned and managed business (sic) which 
started its operations from home 5 years prior and thus fitted within the 



256 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




IDC's mandate and strategy to develop and support emerging black 

owned businesses within the industry and the province; 

has thus far already managed to grow its Construction Industry 

Development Board (CIDB) grading from 1 to 7 GB PE; 

operated primarily in the KwaZulu-Natal Province and had already 

completed a number of contracts for the provincial government 

departments over the years and built a good reputation for itself which is 

evidenced by an Award of Excellence it received from Dr Ina Cronje 

(erstwhile MEC for Education in the province) for outperforming all 

emerging contractors; 

had grown its business into a sizeable operation handling projects for 
the South African Government inter alia schools; community halls; 
cultural centres; police stations; hospitals and as at the date of 
application it handled projects valued at circa R200 million within the 
province; 

had applied for and was awaiting the outcome of tenders for contracts 
worth R50 million; 

had recently been awarded contracts for a school construction project in 
Waterloo Verulam for R23 million and phase2 of Project A security 
measures for R61 million (the Nkandla project.); 
had forecasted income statements and balance sheet indicating that it 
would be able to service the IDC loan in accordance with the agreed 
terms and conditions. . ." 



6.73.15. On 7 February 2011 (almost 10 months after it was submitted), the IDC 



approved Bonelena's application for funding amounting, to R40 295 000. 



257 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.73.16. 
6.73.17. 



6.73.18. 

6.74. 
6.74.1. 

6.74.2. 
6.74.3. 



The records of the IDC further indicate that one year and 5 months later, on 
1 8 July 201 2, Bonelena was placed under final liquidation at the insistence of 
one of its unpaid suppliers. 

On 25 February 2013, the KwaZulu-Natal High Court sanctioned the offer of 
compromise proposed between Bonelena and its creditors and accepted by 
them at a meeting held on 15 February 2013, in terms of section 155(7)(b) of 
the Companies Act, 2008, read with section 66(1 A) of the Close Corporations 
Act, 1984. Bonelena was discharged from liquidation and the final winding-up 
order issued by the Court on 1 8 July 201 2 was set aside. 

According to the IDC, its exposure due to the liquidation (by March 2013) 
amounted to R19,7 million. At the time of the conclusion of the investigation, 
the offer of compromise was still in the process of being implemented. 

The Cancellation of Bonelena's Contract 

The records of the DPW indicate that Bonelena was informed in writing on 15 
March 2012 that it failed to comply with the relevant Principal Building 
Agreement in respect of Phase 2 of the Nkandla project and that further 
failure would result in cancellation of the contract. 

On 10 April 2012, Mr Khanyile informed Bonelena that its contract was 
cancelled. 

Several of the DPW officials and consultants interviewed during the 
investigation confirmed that Bonelena was underperforming during Phase 2 
of the Nkandla project and caused substantial delays. It was also indicated 
that Bonelena appeared to have had serious financial problems at the time. 
Some of the witnesses expressed the view that the company had the 



258 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




capacity to perform the works in terms of the contract, but that the business 
was badly managed. 



6.74.4. However, according to Bonalena's Ms Nene, she had no idea why the 



contract was cancelled. She complained that her business experienced 
several frustrations during the implementation of the Nkandla project, 
including payment delays. She is of the view that negative publicity relating to 
the Nkandla project, the payment and other delays were the main causes 
that the business was liquidated. 



6.74.5. A contract for the outstanding works estimated at a cost of R5 million at the 
time, was subsequently awarded to Moneymine by means of an approved 
negotiated procurement process. 

6.75. The Allegation that the President's Brothers Benefitted from the 
Nkandla Project 

6.75.1. On 2 December 2012, the Sunday Times published an article under the 



heading "OH, BROTHER" stating that public funds allocated for the Nkandla 
Project had been used to pay for renovations to the homes of two of his 
brothers. 



"In documents seen by the Sunday Times, Michael and Joseph Zuma are 
listed as having had supplies by electrical company Voltex delivered to their 
homes as part of the 'prestige project'-as the Department of Public Works 
has dubbed the Nkandla upgrade. 



6.75.2. According to the article: 



259 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




Invoices for the work by the Durban-based company were submitted to a 
building contractor involved in the Nkandla project and have been laid bare in 
papers before the High Court in Durban. 

Voltex went to court to recoup R545 249 it says was owed by contractor 
Pamela Mfeka. She was awarded a reported R47.6 million contract by the 
Department of Public Works to construct six buildings in Nkandla. 

According to the court papers, Mfeka, 46, defaulted on the payments for 
electrical cables and other goods supplied for Zuma's luxury compound and 
his brothers' modest homestead in Nxamalala village. 

Michael denied that any work had been done to his or his brother's home. 

The court papers contain numerous invoices, dated between November 3 
2011 and November 3 2012 in which Voltex billed Mfeka's company, 
Moneymine Enterprises, for electrical products bought for Michael's and 
Joseph's homes as well as the upgrade of Zuma's homestead. 

Several of the invoices refer to the prestige project, while some list the name 
of the village, Nxamalala, where all three homesteads are situated. 

One of the bills dated November 30 201 1, showed an amount of R 3915 for 
electrical goods for Michael's home. 

The matter was scheduled to be heard of Friday, but a settlement agreement 
was reached early in the day between the parties' lawyers." 



260 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.75.3. In its response to the allegations which were raised with Voltex during the 



investigation, Voltex expressed its outrage at what it regarded as inaccurate 
reporting by the Sunday Times. The Legal General Manager of the company 
stated in his response to my enquiries, dated 26 March 2013, that: 

" The Voltex Group is a wholly owned subsidiary of one of the most prominent 
industrial companies in the Republic of South Africa and it is common cause 
that Voltex' relationship with Moneymine 310 CC trading as Moneymine 
Enterprises ("Moneymine") is simply that of a supplier/customer relationship. 

Voltex' involvement in this matter was purely as a supplier of electrical 
products, in the ordinary course of its business, to a customer who had been 
trading with it since 2008 being Moneymine). On or about October 2012, 
Voltex proceeded to institute legal action against Moneymine for the recovery 
of amounts which were due and owing to it for goods sold and delivered to 
Moneymine in the ordinary course of its business. " 



6.75.4. The relevant court papers obtained during the investigation confirmed that 



Voltex instituted legal action against Moneymine in the KwaZulu-Natal High 
Court on 6 August 2012. The basis for the action was Voltex' claim that 
Moneymine owed it R545 294.12 in respect of goods purchased. 



6.75.5. Attached to the Particulars of Claim were several supporting documents, 
including statements reflecting goods purchased from Voltex by Moneymine. 

6.75.6. It was noted that the items in the Moneymine statements included references 
to "nxamalala", "dbn prestige", "Nkandla" "Dundee court", "vuleka" ,"highflats" 
and a number of others. 



261 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.75.7. Next to the date "30/11/2011" appeared the reference "Mike Zuma" and the 
amount reflected is R3915.33. 

6.75.8. The statements also contained a reference to "Joseph" dated 19 March 2012 
for an amount of R2249.22 and "Joseph Zuma" dated the same day for an 
amount of R1 14.00. 

6.75.9. When approached, Voltex explained that the goods supplied under these 
three references were general electrical items such as cabling, switches and 
sockets which are ordinarily used in domestic installations. 

6.75.10. As far as the items related to "joseph" and "joseph zuma" were concerned, 
Voltex were requested to deliver it to: 9A Hangerberger Road Newlands 
East. The request was marked: "ATT MELVIN". 

6.75.1 1 . The items in respect of "mike zuma" were delivered, at Moneymine's request, 
to: 19 Russell Steet, Pinetown. 

6.75.12. Mr and Ms Mfeka of Moneymine explained when interviewed, that 



Moneymine was involved in a number of projects at the same time when it 
was involved in the Nkandla project. As a long standing and well known 
construction company, Moneymine has a number of clients to whom it 
supplies building materials and for whom it does work from time to time and 
that Voltex one of its regular suppliers. 



6.75.1 3. They explained that Moneymine was building houses for Mr Mike Zuma in his 
private capacity and confirmed that Messrs Mike and Joseph Zuma are 
related to the President. 



262 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.75.14. They advised that Moneymine ordered certain items from Voltex for the 



private development relating to Mr Mike Zuma. It was ordered separately 
from items ordered for the Nkandla Project and therefore invoiced and 
recorded accordingly on the statement documents. 



6.75.15. As far as Mr Joseph Zuma is concerned, Moneymine was involved in a small 
project that related to the installation of electricity at his house. 

6.75.16. They further explained that the items ordered in respect of Mr J Zuma were 



delivered to Melvin, Moneymine's electrician, at his address in Newlands. 
The submitted that orders placed in respect of Messrs Mike and J Zuma had 
nothing to do with the DPW project and were paid for separately as was the 
case of other clients of Moneymine reflected on the Voltex statements. No 
claim was ever submitted to the DPW for the items reflected in the said 
statements. 



6.75.17. The dispute between Voltex and Moneymine has been resolved and the 
outstanding amounts paid. 

PART F: THE INTERNAL TASK TEAM REPORT 
6.76. The Investigation of the Internal Task Team 

6.76.1. The Minister of Public Works, in conjunction with the Ministers of State 



Security and Police, appointed a Task Team of officials, from the 
Departments responsible for the Nkandla Project, to investigate allegations of 
impropriety relating to its implementation, around November 2012. 



263 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.76.2. The findings of the Task Team Report were announced by the Minister of 
Public Works in a media statement, issued on 27 January 2013 and the 
report was finally declassified and made public on 1 9 December 201 3. 

6.76.3. It is important to note that by then the Presidency and Security Cluster were 
well aware of my investigation, with some having already responded to the 
standard document and information request from my office. 

6.76.4. As part of my investigation, I requested on several occasions to be provided 



with a copy of the Task Team Report and was only eventually granted limited 
access by the Minister of Public Works on 2 July 2013. The report was 
classified by him as a "Top Secret" document. I was only allowed to peek into 
the document without copying it or keeping it beyond a few hours. 



6.76.5. It was reported in the media that the Democratic Alliance brought an 
application in the High Court for access to the Task Team Report, in terms of 
the provisions of the Promotion of Access to Information Act, 2000. 

6.76.6. After the report was declassified for no apparent reason, as the 



circumstances under which it was regarded as classified did not change from 
January 2013 to December 2013, the Special Advisor to the Minister of 
Public Works reportedly filed an affidavit in the court application stating that 
there was no difference between the report that was classified and the report 
that was released in December 2013. 



6.76.7. Media reports on 18 February 2014 indicate that the Minister of Public Works 



agreed to pay the wasted legal costs of the Democratic Alliance. More public 
funds were therefore spent to protect information that clearly did not qualify to 
have been classified in terms of the MISS. 



264 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.76.8. The report is now freely available to the public and I therefore do not intend 



to refer to all of its contents here. Suffice to say that the Task Team's terms 
of reference were much narrower than what was covered by my 
investigation. 



6.76.9. However, I have noted the following statements made in the Explanatory 
Note to the report, which are of particular relevance: 



The DPW as the implementing agent in respect of the security requirements 
of the DOD and SAPS was supposed to have ensured that the funding 
required was available and budgeted for, the source of the funding identified 
and the procurement prescripts and requirements complied with. 

"The major challenge identified by the Task Team was that there was no 
coordination between various departments that ought to have been involved 
in the security upgrades in order to determine the appropriate budget for the 
project and the costing. For instance, DPW estimated the project at R27 
million before assessments were conducted by SAPS and SANDF. 
Notwithstanding the fact that DPW had managed projects of a similar nature 
in the past, poor management of the project led to the incorrect estimation of 
the project." 

"The assessment of the SANDF indicated a lack of the required level of 
medical facility in the immediate vicinity as prescribed in the Standard 
Operating Procedures (SOP). The 140 000 population of Nkandla 
Municipality shares among itself the services of ten primary health care 
facilities (inclusive of mobile clinics) and two tertiary-level services (Nkandla 
and Khombe hospitals) for health care. Nkandla Hospital has six permanent 
doctors and four seasonal medical practitioners". To augment the services 
are private doctors and traditional healers. The facilities are too far away and 



265 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




unable to meet the standards or the nature of health care required for the 
President and his household. At the time the nearest facility with the required 
standard was two hours away in Durban." 



6.76.10. The explanation provided in regard to the Visitors' Centre is that due to the 
large number of people that visit the President at his private residence there 
was a security challenge to control them. 

6.76.11. The Task Team made a preliminary finding that there is a possibility of 
inflated prices and overcharging. 

6.76.12. I have also taken cognizance of the following findings of the Task Team 
Report : 

6.76.12.1 The Nkandla project was not included in the DPW Medium Term Expenditure 
Framework for the financial periods 201 0-201 3; 

6.76.12.2 The DPW did not pay any contractor for the construction of the private 



dwellings of the President. I noted that this aspect did not form part of the 
Task Team's terms of reference. There is also no indication in the report 
whether and how this was investigated; 



6.76.12.3 The report further stated that "it was also found that the then Minister of 



Public Works, Minister Doidge and Deputy Minister Bogopane-Zulu attended 
and presided over site meetings and in some instances interacted with 
contractors involved in the project. This was reflected in the minutes, memos 
generated by officials of the DPW and from evidence of the three officials and 
one contractor who raised uneasiness with the involvement of the executive 
in the project. " 



266 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 ^^^^ 

PUBLIC PEO>TE<TOE? 
SOUTH flfPIOl 



6.76.12.4 Despite the fact that the object of Nkandla Project was to secure the 
President and that most information relating thereto was classified as "Top 
Secret" the following service providers that were intimately involved in its 
implementation had no security clearance: 





SERVICE 


Minenhle Makhanya Architects 


Principal Agent and Architect 


C A Du Toit 


Security Equipment 


IbonghoConsultants 


Civil Engineeri 


llangalethu Consulting 


Quantity Surveyor 


Mustapha and Cachalia 


Mechanical Engineer 


IGODA 


Electrical Engineer 


E Magubane Information Systems* 


Electronic Detection Systems 



Figure 13: Consultants Appointed without Security Clearance 

* This service provider who was contracted for the installation of intruder detection systems was 
denied security clearance in 2008 and was not subsequently issued with any such clearance for 
the Nkandla Project 



6.76.13. The findings of the Task Team Report in respect of the procurement 
processes followed and the payments made to service providers are mostly 
in line with the findings contained in this report, albeit less detailed and not 
fully supported by evidence. It should also be noted that the investigation of 
the Task Team was initiated by Ministers responsible for Department s who 
were involved with the implementation of the Nkandla Project, as opposed to 
my investigation as an independent Constitutional institution. 

6.76.14. The report of the Task Team was noted to have made the following 
recommendations: 

6.76.14.1 Parliament to review the National Key Points Act; 



267 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.76.14.2 A departmental policy to be developed for Prestige Projects; 

6.76.14.3 A cost apportionment to be done to determine which cost should be allocated 
to which stake holder; 

6.76.14.4 The justification for the delegation of authority to the RBAC to procure goods 
and services above R20 million in respect of the security project has to be 
investigated; 

6.76.14.5 The "surety" made by the DPW to the IDC on behalf of Bonelena to be 
investigated further; 

6.76.14.6 Irregularities identified be further investigated and any professionals who 
might be found to have acted unethically be reported to the relevant 
professional bodies and/or institutions; 

6.76.14.7 Immediate disciplinary measures be instituted against any government 
officials who might be implicated in any kind of wrongdoing, including the 
flouting of policies and procurement procedures 

6.76.14.8 The SSA to conduct a comprehensive information security risk assessment 
of the project; 

6.76.14.9 The role of the former Minister and Deputy Minister of Public Works in the 
project to be clarified and investigated. 

6.76.1 4.1 All DPW Supply Chain Management personnel to be security vetted; 



268 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.76.14.1 1 The Ministerial Handbook to be reviewed to bring it in line with the National 
Key Points Act and the Cabinet Policy regulating security measures at the 
private residence of the President; and 

6.76.1 4.1 2 Any breach of the law to be reported to the appropriate authorities. 

PART G: THE RESPONSES SUBMITTED BY THE PRESIDENT IN REPLY 
TO QUESTIONS PUT TO HIM DURING THE INVESTIGATION 

6.77. On 29 January 2013, I wrote to the President to inform him of my 
investigation of the complaints referred to in paragraph 2 above. I specifically 
stated the details of the complaint lodged by Prof De Vos in connection with 
the statement that the President allegedly made to the National Assembly on 
15 November 2012 that the development of the first phase of his private 
residence was financed by a commercial bank that secured a mortgage bond 
in respect of the property. 

6.78. My letter also stated that: 



"You will be afforded an opportunity to respond in full to the allegations, once 
I am in a position to provide you with more detailed information regarding the 
matters concerned. 

It would be of assistance to me to consider the merits of the complaint lodged 
by Prof De Vos, if you could request the Presidency to provide me with a 
copy of the registered bond relating to your private residence and any other 
relevant documentation and/or information pertaining to the funding thereof. 
Such documentation and information will, due to the nature thereof, be kept 
secure and handled with the appropriate discretion and confidence. " 



269 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 ^^^^ 

PUMJG PCOIEOOI? 
SOUTH flfPICfl 



6.79. I received no response from the Presidency in respect of my request for 
information, despite having approached it again in this regard on 1 1 April 
2013, 21 June 2013 and 19 August 2013. I also wrote to the President 
directly in this regard again on 29 July 2013, but received no response. 

6.80. Eventually, I personally met with the President in connection with my 
investigation on 11 August 2013, a day before my inspection of the works 
implemented by the DPW at his private residence at Nkandla. I have made 
reference to my discussions with the President on certain aspects of the 
Nkandla Project under different headings in this report. 

6.81. During our meeting, I also provided the President with a set of written 
questions that related to my investigation and in respect of which I required 
his response. The President undertook to provide me with a written 
response. 

6.82. As no response to my questions was forthcoming, I approached Dr Lubisi, 
the Director-General in the Presidency, again requesting his assistance in 
this regard, on 26 August 2013. 

6.83. A copy of my written questions with annexures had to be provided to the 
Presidency, at its request, on 27 August 2013. 

6.84. Eventually, I had to write to the President directly on 16 September 2013 to 
again request his response to my set of questions. 



270 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 ^^^^ 

PUfctK PROIEOOI? 
SOUTH flfPICfl 



6.85. My questions were as follows: 



1. "Did you or the Presidency request that security measures be installed 
at your private residence at Nkandla after you were appointed as the 
President in May 2009, as provided for in the Cabinet Policy on Security 
Measures at the Private Residences of the President, Deputy President 
and former Presidents and Deputy Presidents, dated 20 August 2003? 
If so, kindly indicate who made the request, when and how. 



2. Were the measures that the Department of Public Works intended to 
implement at your private residence communicated to you by the 
Minister of Police, as contemplated by the Cabinet Policy? If so, what 
were your impressions of the proposed measures and did you formally 
consent thereto? 



3. Where you at any stage informed of the cost of the proposed security 
measures? If so, who presented the cost to you, what was the amount, 
and how did you respond to it? 

4. Your private residence was declared a National Key Point by the 
Minister of Police, in terms of the National Key Points Act, on 8 April 
2010. According to the evidence obtained during the investigation you 
were notified accordingly by means of a notice (Annexure A) signed by 
the Minister of Police. Can you kindly confirm that this notice was 
served on you? 

5. What was you understanding of the declaration of your private 
residence as a National Key Point in terms as your responsibilities as 
the owner? 



271 



A Report of the 
Public Protector 



March 2014 ££Jt-! 




7. 



8. 



9. 



10. 



Did you at any stage respond in terms of the notice by taking measures 
to secure your private residence, as required by the National Key Points 
Act and the notice? If so, what measures were taken? 

From the evidence it appears that the Minister of Police acted on your 
behalf, as contemplated by section 3A of the National Key Points Act, 
when he had your private residence secured. Were you notified of this, 
as is required by the Act and if so how? 

Were you ever advised by the Minister of Police that any part of the cost 
of securing your private residence as a National Key Point would be 
recovered from you? If so, when and how? 

According to the evidence, you met with representatives of the 
Department of Public Works and the South African Police Service at 
you private residence on 12 August 2009, where you were briefed on 
the security measures that were to be installed in the three new 
dwellings that you were constructing. Is this correct, and if so can you 
kindly explained what transpired at this meeting. 

The evidence obtained during the investigation also indicates that you 
complained on several occasions about the slow progress made with 
the implementation of the security project. Is this correct, and if so can 
you kindly explain the reasons for your concerns and how it was 
addressed? 

According to the evidence, you requested the former Minister of Public 
Works, Mr G Doidge, to look into the delay. Is that correct? If so, did he 
report back to you and what were the nature of his reports? 



272 



Secure In Comfort A Report of the March 2014 

Public Protector 

e>eo>te<toe? 

SOUTH flfPICfl 

12. Mr M Makhanya, the architect that you appointed in respect of your 
private construction on the premises, was also appointed by the 
Department of Public Works as the Principal Agent for the security 
project. Did he present you with the designs of the Department of Public 
Works' security project? If so, can you recall which designs were 
presented to you and how you responded to it? 

13. According to the documentation obtained during the investigation, 
former Minister of Public Works, Ms G Mahlangu-Nkabinde, informed 
you in writing of the progress made with the implementation of the 
security project, shortly after she was appointed, on 5 November 2010. 
(Annexure B) Can you kindly look at the copy of this letter and indicate 
whether you received it and how you responded to it. 

14. Former Deputy Minister of Public Works, Ms H Bogopane-Zulu 
indicated during the investigation that she discussed the security 
measures with you. She also raised the possible apportionment of costs 
of the security measures between you and the state with you and 
requested a document to be prepared by the project team in this regard. 
The document was prepared and delivered to the Ministry of Public 
Works. (Annexure C) Can you please look at this document and 
indicate whether it was presented to you, and if so what your response 
was? 

15. If the document was not presented to you, was the apportionment of 
costs ever discussed with you? If so when and by whom? 

16. Did you ever enquire into it, and if so what was the response that you 
received? 



273 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC e>eo>te<toe? 

SOUTH flfPICfl 

17. Deputy Minister Bogopane-Zulu also indicated that she discussed the 
conversion of the fire-pool on the premises into a swimming pool with 
you and that you supported the idea that it could be used to teach 
children of the village to swim. Is this correct? 



18. Kindly indicate whether you are aware of the reasons why the fire -pool 
was converted into a swimming pool and whether the additional and 
apportionment of such costs were discussed with you. If so, who 
discussed it with you, and what was your response? 



19. The implementation of the security project resulted in the relocation of 
four households that were living on the site. Were you consulted in 
connection with the relocation and, if so, what was your response? Did 
you issue any instructions in this regard? 

20. According to the evidence, you apparently indicated that you were 
opposed to more contractors working on the site when Phase 2 of the 
project commenced, that is the construction of staff housing, etc. Is this 
correct and if so why were you opposed to more contractors? Did you 
issue any instructions in this regard? 

21. Deputy Minister Bogopane-Zulu further indicated during the 
investigation that you supported her idea that the military clinic should 
be designed in such a way that it could also be used by members of the 
community. What is your response to that? 



22. It was also indicated during the investigation that you raised concerns 
about the bullet resistant glass that was installed in your houses. Is this 
correct and if so, can you kindly explain ? 



274 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 ^^^^ 

PUBLIC PEO>TE<TOE? 
SOUTH flfPIOl 



23. A newspaper report alleged that two of your brothers, Messrs Joseph 
and Mike Zuma improperly benefitted from the security project when 
items that were destined for it were delivered at their houses. What is 
you comment on this allegation? 

24. As indicated in my letter addressed to you on 29 January 2013 
(Annexure D), I have also received a complaint in connection with a 
statement that you made to Parliament about the bond on the property 
concerned. I have repeatedly requested to be provided with the relevant 
documents to enable me to deal with this complaint. Are you now in a 
position to provide these documents? 

25. Would you be willing to disclose the amount that you paid for the 
construction of the three new dwellings? 

26. How often do you use your private residence at Nkandla for official 
purposes? 

27. Is there any particular reason why you would prefer to use your private 
residence for official business rather than any one of the official 
residences that are available to you? 

28. Did you at any stage enquire into the cost of the security project, which 
was obviously extensive? If not, did you not feel obliged to do so as the 
head of state and as a substantial amount of public money was 
obviously being spent? 

29. How would you describe your involvement in the security project that 
was implemented by the Department of Public Works at your private 
residence?" 



275 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 ^^^^ 

PUMJG PCOIEOOI? 
SOUTH flfPICfl 



6.86. The President provided me with a response under a covering letter from the 
Acting Secretary of the Cabinet, dated 1 October 2013. His response was in 
the form of a statement, signed by him on 30 September 2013. 

6.87. In the opening paragraphs of his statement, the President denied that he was 
ever apprised of the fact that his conduct formed part of my investigation. 



6.88. He proceeded by explaining the location of his family homestead at Nkandla 
and the history of his occupation of the property. Of particular significance to 
the subject of my investigation, is the following extract of the President's 
statement: 

12 

"As the political environment stabilized in the coming years with the advent of 
our new democracy, I now felt more confident to effect improvements to the 
family homestead in order that it could cater for our needs more adequately. 



13 

I proceeded to engage a building contractor to effect the improvements to my 
homestead. Several new rondavels, each self-contained, were constructed. 



14 

These improvements were financed by a home loan obtained from one of the 
four largest commercial banking institutions in the Republic upon satisfaction 
of their collateral requirements. The property is still subject to a mortgage and 
I continue to meet my financial commitments in terms thereof. 



15 

In the ensuing years and as I began to play a leading role in government, I 
had to submit to the security protocols which senior government officials are 



276 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




subjected to. Static security was provided from the South African Police 
Services (SAPS), (sic) Ulundi, while protection services were provided from 
SAPS Eshowe. 



This meant that additional rondavels were constructed on my homestead in 
order to cater for the accommodation of those police officials assigned for my 
protection, given the lack of infrastructure in Nkandla. In addition, a car port 
and storerooms were also constructed. 



In 1999 I was appointed as the Deputy President of the Republic. As a 
consequence of my increased responsibilities in government I received a 
higher volume of frequent guests at my home in Nkandla. This, coupled with 
the fact that my family had grown over the years, my family and I decided to 
embark on fairly extensive and modern improvements to the property. 



To this end we engaged contractors and commissioned the building of three 
new houses which would be developed in phases over additional 
neighbouring land which we acquired with the consent of the local chief. 

19 

The construction of the houses commenced under the direction of Minenhle 
Makhanya Architects. 



In 2009 I was appointed as President of the Republic. Immediately upon my 
inauguration, members of the security cluster informed me regarding the 



16 



17 



18 



20 



277 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




results of the security assessment which attached to the office that I now 
hold, including my residence at Nkandla. 



As President of the Republic I have the benefit of residences at 
Mahlambhandlophu in Pretoria, Genadendal in Cape Town and John Dube 
House in Durban, all of which I make extensive use of. Equally, I maintain my 
private residence at Nkandla. 



Like most South Africans, I am particularly proud of my community and never 
miss an opportunity to go home to Nkandla-the demands of my work 
schedule permitting. I sometimes wish it otherwise, but I do not shed my 
status as President when I am at home in Nkandla. People continually visit 
me, seek my advice, support and counsel on a whole range of matters. 
Similarly, matters of government do not grind to a halt during these all too in- 
frequent visits to my homestead. 



In the course of the engagements with the security cluster, I initially met with 
then Minister Doidge, senior SAPS officials and other government officials at 
my homestead in a consultative process regarding improved security due to 
my occupying the office of President of the Republic. 



I thereafter facilitated a meeting between the same grouping of persons and 
Minenhle Makhanya Architects, the consultant who was already engaged 
with building work at my home so that there would be as little disruption as 
possible to the work already commissioned. 



21 



22 



23 



24 



278 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




25 



From time to time I received briefings both formally and informally from the 
various Ministers engaged with the security enhancements although I was 
not intimately involved with the finer details. 



At these briefings I expressed concern with what appeared to be inordinately 
lengthy delays which impacted on my family. Equally, I found some of the 
security features like the bullets-proof (sic) windows an excessive 
encroachment on my use and enjoyment of my property. 



Regarding the rationale for the adoption of particular security features, I 
deem it neither prudent nor proper for me to comment, particularly where the 
Public Protector has had access to a range of Ministers and officials properly 
tasked with this responsibility. 



The security upgrades are to be distinguished from the construction of 
buildings which provide infrastructural support for security personal (sic). 



I take exception to the continued conflation of the security upgrades with the 
construction of buildings for the benefit of security personnel. Whilst neither 
were at my behest, the latter is directly attributable to the fact of my 
residence being located in a rural area with all the attendant challenges. 
Even people drawn from rural communities can play a role in the 
development of our constitutional democracy. 



26 



27 



28 



29 



279 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

30 

With regard to my address to parliament, I submit with respect, that insofar 
as it is alleged that I have misled parliament on the existence of my bond 
over the Nkandla Property, parliament is best placed to enquire into this 
matter should it so desire. 

31 

Likewise, it is not proper for me to account for alleged conduct of members of 
my family who are not dependents of mine. Transgressions of the law by 
whomsoever should be reported to the appropriate authorities. " 

6.89. As the President's statement did not provide answers to most of my written 
questions listed above I replied to him on 8 October 2013, listing the 
outstanding responses that were required and stated that: 

7 regarded it as prudent to provide you with an opportunity to respond to 
these matters as part of my investigation and it would be appreciated if you 
could still consider doing so, to enable me to include your version of the 
events in my report" 

As far as your response in respect of my investigation into the complaint 
relating to the statement that you reportedly made to Parliament pertaining to 
the existence or not of a bond over your property is concerned, you will recall 
that I raised this with you when I informed you of my investigation, in my 
letter dated 29 January 2013. 

I indicated in my said letter that the concern raised by the complainant is the 
impression that you might have violated the provisions of the Executive 
Ethics Code by misleading Parliament. I also referred you to the public 
statement of the Presidency of 20 November 2012 that the information 



280 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




pertaining to your bond would be made available to "an authorized agency 
or institution empowered by the law of the land". You will respectfully 
agree with me that this includes the Public Protector. 

In addition to the normal manner in which I approach investigations, I relied 
on the commitment in the Presidency's statement when I approached you 
with the request on this aspect of my investigation. 

I accordingly wish to appeal to you to provide me with the relevant 
documents pertaining to the bond that you referred to. The information 
contained in these documents will be handled discreetly as it relates to your 
private affairs. All that I really need to verify in this regard is that the bond 
exists and that it relates to your private residence at Nkandla. Providing me 
access to the documents in the presence of your legal advisors or the 
Secretary to the Cabinet will also suffice in this regard. " 



6.90. In his reply, dated 24 October 2013, the President indicated that he required 
copies or excerpts of evidence, reports and documents that were referred to 
in my questions, before he could respond. He further stated that: 



"Regarding your request that I make available my personal bond documents 
for your perusal, I attach hereto the relevant transcript extracted from 
Hansard which bears out the following: 

• The Zuma family has built their own home; 

• The home has been there for a long time; 

• / engaged the banks and am still paying a bond on the first phase of my 
home; 

• / am still paying a bond this day. 



281 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

Having regard to the content and context, it becomes abundantly clear that 
such bond relates to the first phase of the development and well before I 
assumed the office of President. As I understand, it does not relate to the 
period of your investigation nor does it shed light on any aspect thereof. 

Accordingly, I hold the view that the disclosure you seek would be 
unnecessary. " 

6.91. I again regarded it as necessary to respond to the President to clarify my 
earlier requests. In my letter addressed to him on 29 October 2013, I 
reiterated that the complaint that I received in respect of the bond does not 
relate to the security measures that were installed and implemented at his 
private residence, but to the statement that he made in the National 
Assembly on 15 November 2012, the contents of which are contested. I 
explained that: 

"It was in order to clarify this issue that I requested you to provide me with 
access to the bond documents. As matters stand at the moment, I am not in 
any position to make a finding on the merit of this complaint and would 
therefore urge you to reconsider my request in this regard." 

6.92. The President was also referred to the fact that a number of my questions do 
not refer to any evidence, reports or documents. In respect of questions that 
did relate to documents, I provided him with copies of such, which were also 
attached to my original questions and later resubmitted to his office. As far as 
the references to "evidence" were concerned, which only related to three of 
my questions, I indicated that it would be covered extensively in this 
Provisional Report, a copy of which will be presented to him for his 
comments. The President's reply is still awaited. 



282 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




6.93. The following excerpt of the Hansard that I was referred to by the President 



in his letter of 24 October 2013 is of particular significance to the matters 
considered during the investigation: 

"When I became the President, all of us in the family agreed to extend our 
home, as I was extending it. Then government came and said that it had to 
install security features at my residence. By the time government came, the 
contractors were on site that had been enlisted by the family and not by the 
government or Public Works. Government had a plan regarding what it 
wanted to do. Government wanted to improve the fence, etc. I told 
government that I had my own plan-which was a comprehensive plan- to 
extend my home. What then happened was that I allowed government to 
meet with the contractors who were already on site because government, 
from a security point of view, insisted that they needed to participate. 

So, even the manner in which the question was asked-the question being: 
have you instructed the Minister to tell the contractors to stop working- 
suggests that the contractors were brought by Public Works. Public Works 
found those contractors constructing my home. 

They had to agree to what government wanted them to do at my home. The 
government had specific things they wanted to do to my houses, not build 
houses for me. A wrong impression has been created in the country, that the 
government has built a home for me. That is not true" 



6.94. 



I never received a further response from the President to the questions 
posed to him. 



283 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.1. 



7.1.2. 



7.1.3. 



7.1.4. 



7.1.5. 



7.1.6. 



EVALUATION OF THE EVIDENCE AND INFORMATION OBTAINED 
DURING THE INVESTIGATION 

PART A: SEQUENCE OF EVENTS 

The Initial Steps Taken and the Recommendations of the SAPS and the 
DOD in Respect of the Security Measures that Needed to be 
Implemented 

The evidence and information obtained during the investigation shows that 
the security measures at the President's private residence were completely 
inadequate at the time when he took office. It basically consisted of a 
dilapidated palisade fence with a gate and a guard hut. 

The Security Advisory Service of the SAPS and the DOD assessed the 
security situation and presented the DPW with its requirements for the 
measures that had to be taken, during May and early August 2009, 
respectively. 

When the Director of the DPW responsible for Prestige Accommodation 
requested funding for the recommended security measures to be 
implemented, the amount indicated was approximately R27 million. 

At that stage, the DPW was of the view that the measures to be taken could 
be afforded from savings on its Capital Works budget. 

However, in August 2009, the private construction of the President's three 
new dwellings on the premises commenced. Security measures also had to 
be installed in the three new buildings and due to its location, the scale of the 
area that had to be secured increased accordingly. 



284 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.1.7. Officials of the DPW involved in the Nkandla Project were told that the 



President preferred that the contractors and consultants appointed by him for 
his private construction should also be appointed for the Nkandla Project. 
This clearly had an impact on the decisions that were taken in respect of the 
appointment of service providers. I refer to this in more detail below. 



7.1.8. The evidence also indicates that due to the direct involvement of the Acting 



Director-General of the DPW, Mr Malebye, when the Nkandla Project 
commenced and the later involvement of a Deputy Director-General, the 
Deputy Minister and the Minister, the officials at the Regional Office that were 
mainly responsible for the implementation of the project, were convinced that 
it was driven from the Ministry and the DPW Head Office and that they had to 
do as they were told. 



7.1.9. After the professional consultants, such as Minenhle Makhanya Architects 



and R&G Consultants (Quantity Surveyors) were appointed by the DPW for 
the Nkandla Project, it transpired that the full scope of the security 
requirements of the SAPS and the DOD was not properly taken into account 
by the DPW when the cost estimate of R27 million was presented to the 
PMBC. 



7.1.10. When R&G Consultants prepared its first cost estimate for the Nkandla 



project in September 2009, it amounted to almost double the original 
estimation of R27 million, i.e. R47.3 million. At this stage the main focus of 
the designs and cost estimations in respect of the Nkandla Project was 
Phase 1, which consisted of what was referred to as the emergency 
measures that had to be taken to secure the President and his family at his 
private residence. 



285 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.1.11. The evidence of Mr Malebye, that he was under the impression that the 



Nkandla Project would not cost more than R27 million is inconsistent with the 
first cost estimate prepared by R&G Consultants, which was addressed to 
him as the Acting Director General and accounting officer. 



7.1 .12. Mr Khanyile's evidence indicated that from the time that the Nkandla Project 



commenced, the procurement procedures followed were different from the 
norm and failed to comply with the prescribed standards of proper demand 
management and budgeting. The officials involved clearly thought that due to 
the fact that the Nkandla Project related to the security of the President, 
which was why it was regarded as urgent, and as it was driven from the DPW 
Head Office and the Ministry of Public Works, the deviation from the norms 
were justified and not to be questioned. 



7.1 .13. The following statements by Mr Khanyile in his response to the evidence and 
information obtained during the investigation, are of particular significance in 
this regard: 



"What was abnormal is that: 

Head office was running the project directly interfering with the duties of the 
project manager and Region (Durban Regional Office). DG being the 
accounting officer was directly involved in operational issues of the project by 
coming to site, met the professionals, the project manager and gave 
instructions that were contrary to policies of the state. 

The Minister being political head of the Department was supervising the 
project every two weeks by, 

• Chairing the project site meetings, 



286 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




• Give (sic) instructions to the consultants, contractors, and the project 
manager, 

• Visiting the suppliers in Johannesburg to discuss materials to be used 
on windows, interfering with the supply chain process of the department 
and the functioning of the project manager. 

They took and approve (sic) the decisions that were contrary to the policies 
of the state. They became the referee and the player; they took decisions, 
gave instructions, approved them and went to project site to implement their 
decisions, overruling the project manager and the Region. 

It is clear even from (sic) a man on the street that the project manager and 
the Region: 

• Were overruled, 

• Intimidated 

• Hand tied, 

• Undermined, 

• Compelled. 

There is no tail that can wag the head on such a high profile project of the 
first citizen of the country. The decisions and the instructions of the 
commander of war are not to be blamed on the soldiers. " 



7 AAA. Mr Malebye even went so far as to allow a deviation from the internal 
directive that all procurements above R20 million had to be approved by the 
SNBAC and delegated unlimited and unconditional authority to the RBAC. 



287 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.1 .1 5. He also approved the appointment of consultants and contractors for millions 



of rand by means of nominated and negotiated procurement strategies, 
which do not cater for the ordinary processes of proper competition and 
selection, on the basis that the Nkandla Project had to be fast tracked. 



7.1.16. The cost estimates prepared by R&G Consultants gradually started to 
escalate from February 2010, as items relating to the project, and specifically 
Phase 2 thereof were added. 



7.2.2. The DPW Regional Office clearly experienced challenges to manage the 



implementation of the Nkandla Project, from its inception. By March 2010, the 
SAPS started complaining about the slow progress, as did the President from 
May 2010. By then, not much had been achieved and the project was already 
a year old. 



7.2.3. The failure of the DPW to pay proper attention to the Nkandla Project and 



plan for its implementation was also evident from the fact that by June 2010 
no funding had been allocated to it for the applicable financial year, resulting 
in reallocation of the DPW Capital Works budget. 



7.2.4. There was a substantial increase in the estimated cost of the Nkandla Project 



by July 2010, to approximately R130 million after the report of the consultant 
involved in the detailed security measures and the additional earth works that 
had to be done, were added to the list. This should clearly have been taken 
into consideration and planned for by the departments involved when the 
Nkandla Project started more than a year earlier, in May 2009. 



7.2. 



The lack of planning and proper budgeting continued 



288 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.2.5. The scale of the Nkandla Project and its impact on the premises where it was 



implemented grew to such an extent due to all the measures being added 
and implemented, that by August 2010 the Project Team regarded it as 
necessary to employ the services of a Landscape Architect to advise on 
rehabilitation of the land. 



7.2.6. At this stage, additional requirements were added by the client departments, 



which resulted in an extended size of the safe haven, additional guard 
houses and a stronger perimeter fence. The estimated cost of the Nkandla 
Project increased to approximately R145 million. 



7.2.7. The evidence shows that due to a combination of poor planning , budgetary 



lapses and a lack of controls the scale and cost of the Nkandla appear to 
have been without boundaries. As more requirements were raised, designs 
were added, cost estimates prepared accordingly and funds within the DPW 
budget reallocated. It is therefore not surprising that the Director: 
Architectural Services raised his concern to the Deputy Director-General of 
the DPW by the end of August 201 0, stating that: 

"Given the very humble beginnings of this project, nothing short of a full 
township establishment is now required..." 



7.2.8. A former Minister of Public Works (Mr G Doidge) became personally involved 



in the Nkandla project from September 2010. Shortly thereafter, a private 
Project Manager was appointed to expedite the process, resulting in an 
additional cost of approximately R 5 million. 



7.2.9. From the evidence stated above it was clear that the appointment of the 
private Project Manager was the result of the pressure from the Ministry of 



289 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




Public Works for the Nkandla Project to be completed and the fact that the 
Regional Office was struggling to manage it, due to its scale. All of this could 
have been avoided if the project was properly planned when it commenced 
16 months before. 



7.2.10. Further additions to the safe haven and landscaping, inter alia^ pushed the 
estimated cost to more than R190 million by mid-September 2010. 

7.2.11. The Minutes of Progress meetings and the evidence of Brigadier Adendorff 



and other officials that were involved in the Nkandla Project show that the 
SAPS Security Advisory Service did not play a significant role in the design of 
the Nkandla Project. It submitted certain proposals, but the ultimate design 
details were left in the hands of especially Mr Makhanya, irrespective of the 
costs involved. 



7.2.12. I could find no indication that the ever escalating cost and lack of planning of 
the project were ever attended to as serious issues by the respective DPW, 
SAPS and DOD accounting officers during the implementation of thereof. 

7.2.13. The concerns that were raised in this regard by members of the DPW 
Professional Team seem to have been ignored as no action was taken and 
they were eventually side-lined, as referred to below. 

7.2.14. One of them, Mr Crafford, expressed his amazement during the investigation 



that the scale of the Nkandla Project was just allowed to grow as and when 
Mr Makhanya submitted new designs and suggestions. To him, the Nkandla 
Project was like "working with a moving target". 



7.2.15. The following statement by one of the other DPW officials during the 
investigation was also of particular significance in this regard: 



290 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 ^^^^ 

PUMJG PCOIEOOI? 
SOUTH flfPICfl 



"Further, the project manager and regional manager was in a further 
disadvantage, as the architect appointed (Mr Makhanya) was having direct 
access to the President, taking instructions from him and incorporating this 
into the design works. This turned out to be counterproductive in some 
instances, as the architect then instructed the project manager as to what to 
do!" 



7.2.16. Although there was some understanding amongst most of the witnesses 
interviewed that part of the expenditure relating to the Nkandla Project would 
be recovered from the President, his prior consultation and approval of the 
measures concerned do not appear to have been material or a prerequisite 
as far as continuing with the implementation thereof was concerned. 



7.3. The Exclusion of Professional Services of the DPW during the 
Implementation of the Security Project 

7.3.1. The evidence obtained during the investigation indicates that the staff 
members of the Chief Directorate: Professional Services, who were involved 
in the Nkandla Project from the beginning, started to feel excluded and 
complained accordingly to Mr Rindel, from March 2011. This was confirmed 
in writing by Ms Pasley, the Chief Quantity Surveyor of the DPW. 



7.3.2. If Ms Pasley's request for a scale and cost containment had been heeded, 
scope creep and the escalation of costs could have been arrested as early as 
December 2010, when she wrote a memo indicating her concerns and 
suggested action. 



291 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 ^^^^ 

PUBLIC PEO>TE<TOE? 
SOUTH flfPIOl 



7.3.3. In his evidence, Mr Rindel conceded that the professional team had been 
side-lined towards the latter part of the project. However, according to him, 
the reason for leaving them out was that the President had indicated that he 
did not want so many people involved in the project. This is difficult to 
understand given that these professionals had been included earlier. 

7.3.4. Mr Rindel also stated that he received instructions from the DPW Head Office 
in the beginning of March 201 1 that persons not directly responsible for the 
Nkandla Project had to be removed from it. 

7.4. How Much Did the Nkandla Project Cost the DPW? 

7.4.1 . The evidence indicated that by the time that the investigation was concluded, 
the total expenditure of the Nkandla Project for the DPW amounted to R 
215 444 415.68. The estimated cost of Phase 3 of the project that has not 
been implemented is R 31 186 887.36, which would bring the total estimated 
cost of the project to R 246 631 303.00. 

PART B: THE GOODS AND SERVICES PROCURED BY THE DPW 

7.5. The Contracts Awarded by the DPW 

7.5.1. It was established from the evidence and information obtained during the 
investigation that the DPW awarded twelve contracts to contractors and 
employed seven consultants for the implementation of the Nkandla project. 



292 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.6. 



Buildings Constructed 



7.6.1. Besides the helipads, safe haven, security fences and other security 
installations more than two dozen new buildings were constructed by the 
DPW in the implementation of the Nkandla project. 

7.6.2. In addition, new buildings costing approximately R8 million were built for the 
relocation of households. 

7.7. General site works 

7.7.1. According to the evidence, the implementation of the Nkandla project also 
involved the installation of lighting, monitoring equipment, access control 
facilities, bulk earth works and landscaping. 

7.7.2. Mobile accommodation for the SAPS staff and mobile generators were also 
required during implementation. 

7.7.3. The general site works amounted to more than R67 million. 



7.8.1. None of the parties have disputed the amount of money spent by DPW on 



PART C: THE SUPPLY CHAIN MANAGEMENT PROCESS 



7.8. 



The Procurement of the Services of Consultants and Contractors 



security and related upgrades to the President's private residence at 
Nkandla, which by the time of concluding the investigation stood at about 
R215 million. It was also not disputed that the prescribed open tender 



293 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




process was not utilized for the procurement of the goods and services 
required at any stage of the implementation thereof. 



7.8.2. It is also common cause that only nominated and negotiated procurement 
strategies were utilised, and in some cases there were direct contractual 
appointments of service providers. 

7.8.3. The evidence of members of the RBAC also revealed that they regarded the 
Committee merely as a rubber stamp of decisions that were taken at the 
DPW Head Office and at Ministerial level. 

7.8.4. The implementation of the Nkandla project to date consisted of two phases. 



Phase 1 was referred to as "Emergency Works" and described as the 
measures that had to be taken immediately after Mr Zuma was appointed as 
the President, to secure his private residence. Phase 2 consisted of the 
additional measures that had to be implemented to establish security, 
medical and logistical support on a long term basis at the President's private 
residence. 



7.8.5. The evidence shows that the consultants Ibhongo Consulting, Igoda Projects, 
R&G Consultants and Minenhle Makhanya Architects were direct 
appointments by the DPW, and approved by Mr Malebye. 

7.8.6. The main motivation for these direct appointments was that the consultants 



had already been appointed by the President for the private works that he 
planned on the site and that there was a need to integrate the scope of works 
of the Nkandla Project with the private works. A closer look at the process 
does though, does not support this as the legitimate basis for the 
appointment. 



294 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.8.7. Mr Malebye explained during the investigation that he regarded the security 



of the President, the indication that the cost of the project would be in the 
region of R27 million (which to him was not exorbitant) as factors to consider. 
He was of the view that it would have been impractical to introduce a "new" 
team of consultants to implement the Nkandla Project. Again, given the 
different tasks to be performed it is unclear why these had to do everything. 
The question becomes more relevant given that no evidence was presented 
indicating that these consultants had been undertaken similar work to the 
DPW brief on Nkandla before. 



7.8.8. Bonelena was appointed by the DPW for "emergency works" in Phase 1 of 



the of the Nkandla Project by means of a nominated procurement strategy, 
which was approved by the RBAC on 2 March 2010, i.e. almost 10 months 
after Mr Zuma was appointed as the President and the Nkandla Project had 
commenced. 



7.8.9. The motivation for the nominated strategy was that the contractors who 
qualified to be considered had been approved by NIA (SSA) to work on the 
Nkandla Project and that they qualified in terms of the required CIDB grading. 

7.8.10. As indicated earlier, we now know that most of these did not have security 



clearance. The RBAC approved the recommendation by Mr Rindel that 
Moneymine be appointed as a contractor for certain selected works during 
Phase 1 of the implementation of the Nkandla Project, by means of a 
negotiated procedure. The request was motivated on the basis that 
Moneymine had been appointed by the President to construct private 
dwellings on the site and that the scope of the selected works would intrude 
on the private construction. 



295 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.8.11. Furthermore, it was stated that the selected works could not be done by 



another contractor as all guarantees that Moneymine would provide would be 
null and void. In addition, that Moneymine had been cleared by NIA for the 
Nkandla Project and was trusted by the President. 



7.8.12. It should be noted that the scope of selected works, as presented to the 



RBAC, included new SAPS guard rooms, a new "hospital", helicopter landing 
pads and parameter security fence, which clearly did not intrude on the 
construction works performed by Moneymine in respect of the President's 
private buildings. 



7.8.13. When confronted with evidence on irregularities, Mr Rindel indicated, that the 



DPW "top management" started to become more actively involved in the 
Nkandla Project from May/June 2010. He said that other officials of the 
Regional Office got the impression that the top management of the 
department had a different expectation of the implementation of the project 
and the following was the result of instructions given to them that they could 
not question: 



7.8.13.1 To remove the installation of the bullet resistant glass from the contracts 
awarded to Moneymine and Bonelena and to enter into a direct contract with 
BRG; 

7.8.13.2 To change the original idea of constructing a safe haven inside the new 
residences and place it where it is today; 

7.8.13.3 To remove the installation of the high security fence from the contract 
awarded to Bonelena and to enter into a direct contract with Beta Fence SA; 

7.8.1 3.4 To upgrade the specification of the low security fence; and 



296 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 ^^^^ 

PUMJG PCOIEOOI? 
SOUTH flfPICfl 



7.8.13.5 To procure park homes, an emergency generator and air-conditioning by 
means of a direct contracts. 

7.8.14. The evidence further shows that the appointment of the private Project 
Manager was made shortly after former Minister Doidge became involved in 
the project, due to the concerns about the delay raised with him by the 
President. By that time, the project had already been running for one year 
and four months. 

7.8.15. The evidence also shows that Mr Doidge became personally involved in 
discussions with the selected supplier, SA BRG Glass. According to Mr 
Rindel's Internal Memorandum submitted to the RBAC in this regard, the 
order for the bullet resistant glass in the amount of R3 035 694.60 was 
issued on the instructions of "Top Management". 

7.8.16. On 23 September 2010, Mr Khanyile approved a request from Mr Rindel to 
utilize "the urgent/emergency delegation" to directly procure bullet resistant 
glass for installation as part of the implementation of the Nkandla project. 

7.8.17. It was noted that this request was also made shortly after former Minister 
Doidge became involved in the Nkandla project. The request stated that the 
emergency installation had to be implemented as per instructions given by 
the Minister, the Director-General, the SAPS and the DOD. 

7.8.18. The evidence further shows that it was decided in September 2010 to 
procure park homes for officials of the DOD and the SAPS that had to be 
accommodated on the site, as an interim measure until Phase 2 of the 
Nkandla Project was completed. Park homes in the amount of R2 436 396.60 



297 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




were directly procured from the only supplier in KwaZulu- Natal, Natal Park 
Homes (Pty) Ltd. 

7.8.19. According to Mr Rindel's evidence and that of R&G Consultants, the extent of 
the Nkandla Project was better defined by December 2010. The designs 
were at an advanced stage and the costing had been done by the quantity 
surveyors. Phase 1 of the Nkandla Project was underway and Phase 2 could 
commence. 

7.8.20. On 10 January 2011, the RBAC approved the appointment of Bonelena for 
the construction of 25 new buildings and related works as part of Phase 2, by 
means of a negotiated procurement process. 

7.8.21 . The RBAC's decision was clearly directly influenced by what was regarded 
as instructions from the Deputy Minister. 

7.8.22. Similarly, the RBAC approved a negotiated procurement strategy for the 
appointment of Moneymine for the construction of 6 new buildings as part of 
Phase 2 of the Nkandla project, on 17 January 2011. The motivation 
provided by the Mr Rindel and accepted by the RBAC was exactly the same 
as in the case of the appointment of Bonelena, referred to above. 

7.8.23. The installation of the bullet resistant glass resulted in a lack of ventilation in 
the affected buildings, which caused serious discomfort to its occupants. In 
an Internal Memorandum addressed to the RBAC on 3 March 2011, Mr 
Rindel stated in this regard: 



"The scope of works included in phase did not include the installation of the 
air conditioning units, as this was originally planned to be part of phase II. 



298 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




Meetings were held with the previous Honourable Minister G Doidge and 
later with the Honourable Deputy Minister Bogopane-Zulu and DDG: ICR on 
a 2 monthly/weekly basis. 

It was identified during November 2011 that the installation of the air 
conditioning units had become critical, as the BRG windows had been 
installed and the houses became operational. This resulted in a possibility 
that the air circulation was not sufficient and the air-conditioners was (sic) 
then required to improve the situation. 

The meeting agreed that the Durban Regional office must issue an 
instruction to a (sic) acceptable service provider within 24 hours to proceed 
with the works. The delegation was granted by the Regional Manager and 
the Project Manager actioned this by instructing the contractor to continue 
with the works. 

An order had also been issued to the contractor on 30 November 2010 to the 
value ofR 1 528 904.16." 



7.8.24. The deviation in this case was therefore the direct result of poor planning on 
the part of the DPW that caused the discomfort. 

7.8.25. From the evidence it was further established that the direct appointment of 



Betafence Projects SA for the installation of the perimeter fence for the 
Nkandla Project was due to the fact that it is the only supplier in the country 
that specializes in the product, which is required by the SAPS. 



7.8.26. I could find no indication in the documents that was obtained and accessed 



during the investigation that the reasons why the RBAC approved a 
nominated procurement procedure in respect of the installation of lifts in the 
amount of R2 069 607.70 was approved. 



299 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.8.27. According to the evidence the Acting Director-General of DPW directed that 



the procurement process in respect of electronic security systems should be 
limited to a negotiated process with one service provider, due to security 
reasons. Messrs E Magubane was appointed as the service provider for the 
amount of R1 1 .2 million. It was not clear from the evidence who identified the 
service provider. However, it did transpire during the investigation that the 
service provider did not comply with NIA's (SSA's) security screening 
standard. The contractor that installed some of the most sensitive security 
equipment for the safeguarding of the President at a cost of more than R1 1 
million did not comply with the prescribed vetting standards. It is not clear to 
what extent the security of the President could be compromised as a result of 
this. 



7.9.1 . In the case of the Nkandla Project two variation orders exceeding 20% of the 



contract amount were approved by the RBAC. In the first case, a variation 
order of 52.7% was approved on 10 January 2011 and in the second case 
the RBAC approved a variation order of 58.6% on 24 January 201 1 . 



7.9.2. Both variation orders related to Phase 1 of the Nkandla Project and the high 
percentages are indicative of the absence of proper planning on the part of 
the DPW. 



7.9. 



Variation Orders 



300 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




PART D: SPECIFIC ISSUES CONSIDERED DURING THE 
INVESTIGATION 



7.1 0. The Budget for the Security Project 

7.1 0.1 . It is not in dispute that the DPW paid for every aspect of the implementation 
of the Nkandla Project despite the fact that the client departments were the 
SAPS, DOD and the Presidency. 

7.1 0.2. In his response in this regard to the evidence and information obtained during 



the investigation, the former National Commissioner of the SAPS, Gen B 
Cele, stated that in his view the only role of the SAPS was to identify the 
operational requirements and that it was for the DPW to fund "any structural 
additions and amendments to President Jacob Zuma's residence necessary 
to opitmise the execution of the SAPS mandate. I submit that it is precisely 
for this reason that the SAPS never funded the Nkandla Project. .." 



7.10.3. However, Mr Malebye who was the Acting Director-General of the DPW 
when the Nkandla project commenced does not agree. He stated that: 



"It was always contemplated that the DOD and SAPS would contribute to the 
expenditure to be incurred. That contribution would be determined once the 
procurement strategy had been developed and budget and funds had to be 
allocated to the project. The allocation of funds would therefore include and 
require a prior agreement with the SAPS and DOD in respect of their 
respective contributions to the project. " 



7.10.4. He further explained that the DPW, as the department responsible for the 
implementation of the Nkandla Project, would incur the costs initially and 



301 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




would recover the appropriate portions thereof from the DOD and the SAPS. 
Brigadier Adendorff was also of the same understanding. 



7.10.5. It is not disputed that the DPW to date has not recovered any amount spent 
on the Nkandla Project from the other departments involved. 

7.10.6. The current Director-General of the DPW conceded during the investigation 
that there was no specific budget allocated for the Nkandla Project and that 
the approach was to fund it from the savings made on other capital projects. 

7.10.7. From the evidence and information obtained during the investigation, it was 



established that the implementation of the Nkandla project spread over three 
financial years. When it commenced in May 2009, the amount requested by 
the Regional Office was in the region of R27 million. It was indeed approved 
on the basis that it would be sourced from savings made from other projects. 



7.10.8. Mr Malebye, who was the Acting Director-General of the DPW when the 
Nkandla Project commenced until the end of March 2010 stated that he was 
of the firm belief that the cost would not exceed R27 million. As indicated 
above, the cost of the Nkandla Project by February 2010 was estimated to be 
more than R80 million. He denied having been aware of this. 

7.10.9. However, Mr Malebye could not explain how it was possible that he, as the 



accounting officer of the DPW, was not informed by the officials responsible 
for the implementation of the Nkandla Project when the estimated costs 
rocketed from R27 million to more than R80 million, especially as systems to 
do so were in place. He further contended that: "The client departments 
would obviously also at this stage, have to be involved prior to final approval 
and allocation of budget. " 



302 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.10.10. It was also established that the Nkandla Project was not budgeted for in the 
next financial year, i.e. 2010/201 1 . When Mr Rindel requested funding for it in 
the amount of R38.9 million, the (new) Acting Director-General, Mr Vukela, 
directed that R40 million should be reallocated to it from the Inner City 
Regeneration and Dolomite Risk Programmes of the DPW. A further R18 
million was reallocated to the Nkandla Project from the Border Control 
Operation Coordinating Committee Programme. 

7.10.11. Although the evidence indicates that the 2011/2012 DPW budget allocated 
an amount of R123 900 million to the Nkandla Project, it was again 
insufficient and a further R9 million had to be sourced from other 
programmes of the DPW. 

7.10.12. The same happened in the 2012/2013 when reallocation of the budget from 
other programmes of the DPW to the Nkandla project resulted in an allocated 
amount of R39.7 million. 

7.10.13. The Inner City Regeneration and Dolomite Risk programmes of the DPW, 



which were specifically affected by the reallocation of substantial amounts of 
the budget allocated to it to the Nkandla Project, are important as both relate 
to service delivery and safety issues. It is not clear from the evidence that the 
reallocation related to funds that could be regarded as "savings", as indicated 
by the Acting Director-General and contemplated by the relevant provisions 
of the PFMA referred to below. 



7.11. The Construction of Buildings and Other Structures on Land that 
Belongs to the Ingonyama Trust 

7.11.1. It is not in dispute that at the time of the conclusion of the investigation 
referred to in this Provisional Report, the DPW had no lease agreement with 



303 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




the Ingonyama Trust in terms of which it could legally occupy the land on 
which it constructed buildings and other structures as part of the Nkandla 
Project (i.e. excluding the land privately occupied by the President). 



7.11.2. In terms of the provisions of the KwaZulu-Natal Ingonyama Trust Act, 1994, 



the Kwazulu-Natal Ingonyama Trust Board required the written consent of the 
relevant traditional authority or community before it could enter into a lease 
agreement with the DPW. 



7.1 1.3. According to the information obtained during the investigation, the Nxamalala 



Traditional Council only resolved that it had no objection to the application of 
the DPW to acquire rights to the land concerned. However, it was specifically 
recorded that the DPW would not erect any structure on the land until such 
time as an appropriate lease agreement had been concluded. 



7.1 2. Measures Taken Under the Provisions of the National Key Points Act 

7.12.1. As I have indicated above, the President's private residence was declared a 
National Key Point by the Minister of Police on 8 April 2010. 

7.12.2. In his response to the evidence and information obtained during the 



investigation, the Minister of Police furnished me with a copy of an SAPS 
Information Note that he approved on 8 April 2010. The purpose of the 
Information Note is stated to recommend to the Minister of Police to approve 
the declaration of the President's private residence at Nkandla "to the status 
of a National Key Point". 



7.1 2.3. It further states that the SAPS Division: Protection and Security Services had 
conducted a physical security assessment at the President's private 
residence (no date provided) and that "with the recent spade of security 



304 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

transgressions of private individuals at the residence occupied by the 
President, maintenance and improvement of the security of the President as 
well as security stability of the Country (sic), it is imperative to ensure that his 
residence is upgraded to the level of a National Key Point." 



7.1 2.4. Surprisingly though, the Information Note then states the following: 

"In the absence of the National Key Point Committee, the Government 
Security Regulator would like to recommend that the private residence of 
the President of South Africa at 8 Epping Road, Forest Town be classified 
as a National Key Point." (emphasis added) 

7.12.5. The Information Note makes no recommendation in respect of the 
President's private residence at Nkandla. 

7.1 2.6. It was recommended by the then National Commissioner of the SAPS, Gen B 
Cele on 6 April 2010. 

7.1 2.7. Gen Cele indicated during the investigation that his signing of the Information 
Note did not impose any obligation on him as the National Commissioner, to 
assist the Minister of Police in the performance of his functions in terms of 
the National Key Points Act. 

7.1 2.8. I was not provided with a copy of the "physical security assessment" referred 
to in the Information Note, despite having requested it several times. 

7.1 2.9. The relevant Declaration Certificate issued by the Minister of Police on 8 April 
2010 in respect of the President's private residence at Nkandla informed him 
that he was obliged to take measures at his own cost and to the satisfaction 



305 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




of the Minister "to prevent or counter subversion, espionage and sabotage 
and/or to apply emergency measures in a situation of emergency and 
disaster. " 

"it is trusted that you will implement your security obligations as defined in 
Section 3(1) of the National Key Points Act, Act 102 of 1980, at your National 
Key Point." (emphasis added) 



7.12.10. No evidence was presented to me or could be found during the investigation 



that the President complied with this obligation. All the security measures that 
were subsequently installed and implemented at his private residence were 
procured and paid for by the DPW. 



7.12.1 1. The Declaration Certificate further informed the President that his "protecting 
unit"\s the local "SAPS Station". It further stated that: 

"The total safeguarding of a National Key Pont (NKP) comprises not only the 
security measures which you as owner are obliged to implement in terms of 
section 3(1) of the National Key Points Act, but also the effective protection of 
the NKP which must be implemented by the protecting unit. It is therefore of 
the utmost importance that either you, or a person appointed by you, liaise 
with the protecting unit of this National Key Point and the Provincial NKP 
Officer to activate a Joint Planning Committee (JPC) for this National Key 
Point in order to draw up a joint plan to counter an incident." (emphases 
added) I could find no indication during the investigation that the local Police 
Station in the area where the President's residence is located was involved in 
any security or protection measures, as contemplated by the Certificate . 



306 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




There is also no evidence that a Joint Planning Committee was ever 
established. 



7.12.12. That the Declaration Certificate expected of the President to pay for the 
security measures that had to be installed at his private residence also 
appears from the following statement: 



"In terms of Section 24 D of the Income Tax Act, you can submit a claim for 
tax deduction in respect of expenditure incurred on security measures 
implemented at you National Key Points. 

It is trusted that you will implement your security obligations as defined in 
Section 3(1) of the National Key Points Act, 102 of 1980, at you National Key 
Point." 



7.1 2.1 3. I have noted from the copy of the Declaration Certificate that was provided to 



me by the Minister of Police that it was received by Dr Lubisi, the Director- 
General of the Presidency, on behalf of the President. For reasons unknown 
to me, the acknowledgement of receipt was dated 7 April 2011. It was 
established that Dr Lubisi was appointed as the Director-General on 1 
November 2010. 



7.1 2.1 4. In the absence of a denial by the President, it can be safely assumed that the 
Declaration was forwarded to him between April 201 and April 201 1 . 

7.1 2.1 5. If so it can also be safely assumed that he knew that the contents asked him 



to pay. There is no evidence of him protesting nor of the Minister of Police 
revoking the decision that the security upgrades be on the President's 
account. 



307 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.12.16. I also could find no indication that the DPW Regional Office was informed 



that the President's residence had been declared a National Key Point and of 
the implications thereof. Mr Rindel indicated during the investigation that if 
the officials of the Regional Office had been informed, they would probably 
have recommended that the project be stopped as very little of the planned 
works had been implemented at the time. 



7.13. The security measures taken in terms of the Cabinet Policy: Security 
Measures at the Private Residences of the President, Deputy President 
and former Presidents and Deputy Presidents 

7.13.1. During the investigation, the Minister of Public Works indicated that the 
Nkandla Project was based on this Policy and the provisions of the National 
Key Points Act. 

7.13.2. The witnesses involved in the implementation of the Nkandla Project that 



were interviewed during the investigation, had no knowledge of the 
provisions of this Policy or that the Nkandla Project was based thereon. This 
is apparent in the evidence of Lt Gen Ramlakan and Brig Adendorff among 
others. 



7.13.3. It is also clear from the interviews conducted and the documents perused 



during the investigation that there was a general understanding and/or 
acceptance among the officials that the security measures were installed at 
the President's private residence by virtue of the provisions of the Ministerial 
Handbook. 



7.13.4. For example, the initial public statements made by the Minister of Public 
Works, Mr T Nxesi, in connection with this matter, it was evident that he also 



308 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




held such view. In his public statement issued on 27 January 2013, the 
Minister stated in this regard that: 

"In May 2009 after the inauguration of President Zuma, the Department of 
Public Works in line with its obligation to effect security measures at the 
President's private residence which is regularly used by the President, 
became involved in the Nkandla residence. 

The responsibility of Public Works in this regard is contained in the Ministerial 
Handbook and the Cabinet Decision of 20 August 2003 which is now known 
as the Policy on Security Measures at Private Residences of the President, 
Deputy President and former Presidents and Deputy Presidents." (emphasis 
added) 



7.1 3.5. As indicated below, the Ministerial Handbook does not apply to the President. 

7.14. The Security Evaluations Conducted by the Security Advisory Service 
of the SAPS and the Security Measures Installed 

7.14.1. The table below represents a comparison between the security measures 



recommended by the Security Advisory Service of the SAPS after its first visit 
to the President's private residence (Mr Zuma had already taken office at the 
time), the recommendations contained in the second security evaluation 
report, which was conducted approximately 16 months later and the 
measures that were actually installed by the DPW. The DPW list differs 
significantly. Worth noting are the items that are on neither of the security 
evaluation lists. This begs the question regarding their origin. It must be 
further noted that the items in question are primarily the ones that were 
constantly mentioned in conversation alluding to the owners account, or 



309 



Secure In Comfort A Report of the March 2014 

Public Protector 



matters discussed between Mr Makhanya and the President or to be 
discussed between the two, according to the minutes. 



310 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 , 










RECOMMENDED IN 28 MAY 2009 
SAPS EVALUATION 


RECOMMENDED IN 25 SEPTEMBER 
2010 SAPS EVALUATION 


INSTALLATIONS IMPLEMENTED 
BY THE DPW 


COST OF INSTALLATION 










Perimeter protection: 

Brick and mortar wall on a height of 
2,4 m fitted with six strand electric 
fence and CCTV camera system 


Perimeter protection: 

"Green fence" around the entire 
homestead with a minimum height 
of 3m, supported with intrusion 
detection and single/double welded 
mesh fence with deterrent 
capability. "Due to the size of the 
property there is a need for a path 
between the fences that will be used 
for patrol purposes." 


External High Security Fence 


R 6,238,892.57 


Internal High Security Fence 


R 8,103,045.18 


Patrol roads paving and walkways 


R 12,826,158.04 


rxclULdUUM Ul [lUUbcMUlUb 

obstructing construction of 
perimeter fence 


R 7 Q91 R1 7 AA 


Entrance gates: 

Three gates. First gate next to guard 
hut for access control 


Entrance gates: 

Main entrance to the premises to 
consist of a sliding steel gate, 
motorized and remote controlled. 
Other gates for internal use. 


Included in perimeter protection 




Second gate for live stock 


Third gate for emergencies 











311 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 , 




H3Ta91 i" J i T i I 3l VI 1 1 :T3^H H3Ta91 1 : J I t' J I * i VI 1 1 T3^H 






RECOMMENDED IN 28 MAY 2009 
SAPS EVALUATION 


RECOMMENDED IN 25 SEPTEMBER 
2010 SAPS EVALUATION 


INSTALLATIONS IMPLEMENTED 
BY THE DPW 


COST OF INSTALLATION 










Security control room: 

The unused guard hut at the 
emergency entrance to be used for the 
monitoring of all security systems. 
Guard hut to be strengthened and 
secured. 


Security control room: 

New security control room to be 
constructed, highly secured with 
bullet resistant glass, security door 
and installation of all monitoring 
systems. 


Visitors Centre and Control Room 


R 6,720,852.95 


Illumination: 

Security illumination to be installed 
around the premises to illuminate all 
dark areas. 


Illumination: 

Security illumination to be installed 
around the residence to illuminate 
all dark areas without illuminating 
the residence itself. Illumination also 
to be installed at the vehicle 
entrance to assist CCTV camera 
system 


Street and area lighting 


R 914,002.75 


Glazing: 

The glazing of the three main houses 
and study room to be replaced with 
bullet resistant glass. The rest of the 
glazing on the premises to be replaced 
with laminated glass 


Glazing: 

All ■ 1 | • • , 1 • 

All the glazing in the sensitive areas 
to be replaced with bullet resistant 
glass. The rest of the glazing on the 
premises to be replaced with high 
impact laminated glass. 


Security measures and air 
conditioning at residences 


R 5,038,036.33 


External doors: 

All the external doors of the three 
main huts to be replaced with solid 
wooden doors with security locks and 
security gates 


External doors: 

All external doors within the 
premises to be replaced with 
wooden doors of good quality with 
security locks and security gates. 


Part of security measures referred 
to above 





312 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 J 



P 









RECOMMENDED IN 28 MAY 2009 
SAPS EVALUATION 


RECOMMENDED IN 25 SEPTEMBER 
2010 SAPS EVALUATION 


INSTALLATIONS IMPLEMENTED 
BY THE DPW 


COST OF INSTALLATION 










Burglar proofing: 

All windows to be fitted with burglar 
proofing secured into the walls. 


Burglar proofing: 

All windows to be fitted with burglar 
proofing secured into the walls 


Part of security measures referred 
to above 




Fire Fighting Equipment: 

a special Tire aeiecnon ana 
suppression system to be installed in 
all the huts on the premises. At least 
two water hydrant pipes to be 
installed for emergency use 


Fire Fighting Equipment: 

A fire detection system linked to the 
control room and proper fire-fighting 
equipment approved in terms of the 
National Fire Regulations to be 
installed 


rire pool ana parKing 


D T Q1Q nC 1 CC 

k z,o±y,Lo±.oo 


Intruder alarm system: 

To be installed at the premises to 
cover all sensitive areas within the 
premises. 


Intruder alarm system: 

To be installed at the premises to 
cover all sensitive areas within the 
premises. 






Security work consisting of: 




Data network 


R 1,786,890.00 


Access control 


R 220,449.50 


Builders work 


R 1 274 419 13 


CCTV Camera System: 

To be installed to cover all entry 
points, the entire perimeter and 
parking areas 


CCTV Camera System: 

To be installed to cover all entry 
points, the entire perimeter and 
parking areas. The system to be 
linked to the control room and guard 
hut 


CCTV Camera system 


R 3,389,690.02 











313 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 , 










RECOMMENDED IN 28 MAY 2009 
SAPS EVALUATION 


RECOMMENDED IN 25 SEPTEMBER 
2010 SAPS EVALUATION 


INSTALLATIONS IMPLEMENTED 
BY THE DPW 


COST OF INSTALLATION 










Safe haven: 

All three main bedrooms of the 
huts/houses to be protected by means 
of a double brick and mortar wall, 
reinforced roof, fire suppression 
system, fire-fighting equipment, bullet 
proof glass, doors with security locks 
and panic buttons 


Safe haven: 

The high risk option proposed was a 
secure room that cannot be 
surveyed or reached from outside 
the house. It was to consist of 
enforced brick walls and ceiling, 
bullet resistant windows and a bullet 
resistant door 


Safe haven (underground), 
corridor link, walkway and 
emergency exit 


R 19,598,804.10 


Police Barracks: 

"The existing police barracks must be 
upgraded to be suitable for human 
occupation. Ablution facilities to be 
used by the SAPS members performing 
static guard duties must be also be 
upgraded. " 


Police Barracks: 

14 Bachelor flats, 12 lock up garages, 
14 carports and. 2 offices and 2 
guard huts (This was not mentioned 
in the SAPS Security Evaluation 
Report, but was submitted by the 
SAPS to the DPW as a separate 
needs analysis on 15 October 2009. 


20 Residential staff houses (40 
units) 

Laundry facility 


R 17,466,309.67 


Water supply: 

A new borehole to be sunk to improve 
the water supply to the premises. 


Water supply: 

A new borehole to be sunk to 
improve the water supply to the 
premises. Alternatively, a mini sewer 
treatment plant to be built on site 






Site reticulation ( fire water, storm 
water and waste) 


R 2,961,936.01 






Booster pump station and steel 
reservoir tank 


R 571,278.25 






Sewer treatment plant 


R 1,030,673.68 






Sewer Pump Station 


R 807,782.16 



314 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 , 










RECOMMENDED IN 28 MAY 2009 
SAPS EVALUATION 


RECOMMENDED IN 25 SEPTEMBER 
2010 SAPS EVALUATION 


INSTALLATIONS IMPLEMENTED 
BY THE DPW 


COST OF INSTALLATION 










Guard hut: 

The existing guard hut to be upgraded 
and secured to serve as a control 
room. 


Guard hut: 

A new secured and security 
equipped guard hut to be built at the 
new main gate to replace the 
existing one 






Guard House 1 


R 1,205,827.49 






Guard Houses 2 & 3 


R 1,367,770.87 


Tuck shop: 

"In order to achieve a safe and secured 
environment within the premises, the 

CAIjLI I ly LULlK JilUfJ IiIUjL Uc i cIULULcU 

from the present position to enable the 
police personnel to maintain proper 
access control. A new hut (tuck shop) 
must be built closer to the perimeter 
protection to enable people to buy 
while outside the premises." 


No reference 


A building consisting of the Tuck 
Shop, Transformer and LV Room, 
Genset Room & Refuse Area 


R 956 381 16 


Parking area: 

As the existing parking area was open, 
the entire area had to be monitored by 
the CCTV camera system 


No reference 


Included in CCTV installation 




Stud v/Off ice: 

The existing study/office to be 
secured, including the installation of 
security doors, panic buttons, bullet 
resistant glass, CCTV camera system 
and reinforcement of the roof 


No specific reference 


Included in security measures 
referred to above 





315 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 










RECOMMENDED IN 28 MAY 2009 
SAPS EVALUATION 


RECOMMENDED IN 25 SEPTEMBER 
2010 SAPS EVALUATION 


INSTALLATIONS IMPLEMENTED 
BY THE DPW 


COST OF INSTALLATION 










General recommendations: 


General recommendations: 






The existing generator to be serviced 
and maintained 


The existing generator to be serviced 
and maintained. A new standby 
generator to be installed at the 
premises to cater for domestic and 
security requirements. 


Electronic security equipment to be 
connected to uninterrupted power 
supply/backup 


Electronic security equipment to be 
connected to uninterrupted power 
supply/backup 



Figure 14: Comparison between the initial and subsequent SAPS recommendations and the actual installations conducted by DPW 



316 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH ftfEIOl 



7.1 4.2. More than a year lapsed from May 2009 before the Security Advisory Service 
of the SAPS submitted its second security evaluation report in respect of the 
President's private residence, in September 2010, despite the fact that it was 
represented on the Project Team throughout. A number of the security 
measures recommended in the second security evaluation report, and more, 
had by then already been included in the designs and estimated costing of 
the Nkandla project. The report of the security consultant on the detailed 
security measures was already presented to the DPW in July 2010. The 
elaborate safe haven in a location different from the first Security Evaluation 
Report was already in design, while the second Security Evaluation Report of 
the SAPS still recommended a modest safe haven on the surface of the site. 



7.14.3. I noted that the estimated costs of the Nkandla Project escalated from an 
initial approximately R27 million in May 2009 to approximately R224 million in 
December 2010 as a result of significant changes and additions. 

7.14.4. The table below indicates the respective escalations over the period and 
items added that were not reasonably directly related to the President's 
security as recommended by the SAPS Security Evaluation Report. 











LEGEND 




A: May 2009 


R 27,893,068 


R 47,323,102 


• Lift installation for safe haven 
■ Visitors Centre 

• Relocation of three households 


B: Sep 2009 


A: Sep 2009 


R 47,323,102 


R 80,836,249 


• Increase in number of staff accommodation 

• Increase in size and location of safe haven 


B: Feb 2010 



317 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC f>e«oi 

SOUTH flfl 











A: Feb 2010 
B: July 2010 


R 80,836,249 


R 

130,604,267 


• Increase in earthworks- roads, paving specification 
changed 


A: July 2010 
B: Aug 2010 


R 

130,604,267 


R 

145,086,964 


• Increase in staff accommodation 

• Safe haven further extended 

• Landscaping 


A: Aug 2010 
B: Oct 2010 


R 

145,086,964 


R 

193,533,845 


• Additions to safe haven 

• Landscaping 


A: Oct 2010 
B: Nov 2010 


R 

193,533,845 


R 

196,864,037 


• Additional staff houses 


A: Nov 2010 


R 

196,864,037 


R 

224,344,542 


• Additional staff houses 

• Laundry facility for staff houses 


B: Dec 2010 


• Additions to the relocation of households 



Figure 15: Escalations and Significant Changes between various stages of the Nkandla Project 



7.15. The Tuck Shop 

7.15.1. From the security evaluation reports of the Security Advisory Service of the 
SAPS obtained during the investigation and the observations made during 
my site visit to the premises, it was obvious that it would not have been ideal, 
from a security point of view, to have allowed the owner of the business to 
continue with it at its original location. The business was relocated during the 
implementation of the Nkandla Project. The new location of the small tuck 
shop is at the entrance gate to the premises and consists only of a very small 

318 




Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



room that forms part of a larger building, which relates to the security 
measures that were implemented. 



7.16. The Military Clinic 



7.16.1. The documentary evidence and that of Lt Gen Ramlakan show that SAMHS 
is obliged, in terms of the Defence Review, that translated into a national 
policy for the SANDF to provide medical care to the President 

7.16.2. However, Lt Gen Ramlakan could not shed any light on the specific legal 
authority for installation of stationary and permanent medical facilities at the 
private residence of the President. The legal and policy frameworks he 
referred me to, are generic and normative in nature. Counsel assisting Lt 
Gen Ramlakan during his evidence conceded that there is no law, regulation, 
policy or any other provision that authorizes the Surgeon General or the 
SAMHS to request the construction of a permanent health care facility for the 
President and his dependents at his private residence. He submitted that Lt 
Gen Ramlakan's decision in respect of the request for the construction of the 
Military Clinic at President's Zuma's private residence was a discretionary 
one. However, I was not referred to any instrument that afforded Lt Gen 
Ramlakan with such discretionary powers. Incidentally, DPW internal 
memoranda seemed to note with concern that norms were not submitted by 
the DOD. A document submitted by Gen Ramlakan as an assessment on 
their part, indicates that relevant DOD Doctrines and Treasury prescripts will 
suffice, where the legal framework was required. 



7.1 6.3. The appraisal of what was required to enable the SAMHS to provide medical 
care to President Zuma at his private residence, focused, according to Lt 
Gen Ramlakan on the "worst case scenario" 



7.16.4. I noted that at the time when Lt Gen Ramlakan requested the DPW to 
provide a permanent health care facility at the President's private residence 



319 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



(in May 2009, shortly after President Zuma was appointed), he had a clinic 
costing between R15 to R18 million in mind. 



7.16.5. The appraisal considered the medical care that could be provided by the 
District Hospitals in the area and found it to be inadequate. However, there is 
no indication that it considered improving the facilities at these hospitals so 
that it could serve the SAMHS requirements for medical care and the 
community at large. 



7.16.6. I could find no indication that the decision seriously considered the more 
economic and sustainable option of the provision of a mobile medical facility, 
as was stationed at former President Mandela's private residence, instead of 
constructing a permanent structure at state expense that would be adjacent 
to the President's private residence forever. According to Lt Gen Ramlakan's 
evidence, medical care has been provided to the President by the SAMHS 
from a temporary park home since his appointment 5 years ago. There is no 
evidence that this caused any difficulty, except for the storage of drugs that 
could have been accommodated in one of the many other buildings that were 
constructed as part of the Nkandla Project. 

7.16.7. I was referred by counsel assisting Lt Gen Ramlakan in his evidence to the 
provisions of section 41 of the Constitution, providing for cooperative 
governance, and specifically subsection (1)(h) that requires of all organs of 
state and all spheres of government to cooperate with one another in mutual 
trust and good faith by, inter alia, assisting and supporting one another and 
coordinating action. The submission was that it was on the basis of this 
constitutional imperative that the SAMHS cooperated with the DPW in the 
Nkandla Project. 



7.16.8. The evidence of Deputy Minister Bogopane-Zulu indicates that the possibility 
of also utilizing the clinic for the medical and health care of the community 
where the President's private residence is located was suggested by her 



320 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



when she got involved in the Nkandla Project. She believed that she was 
supported in her views by the President, as she had discussed it with him. It 
is worth noting that the Project Team's progress minutes indicate that soon 
after the Deputy Minister left the project, Lt Gen Ramlakan reported that the 
DOD had decided not to use the Military Clinic for the public. 



7.16.9. In his submission, Lt Gen Ramlakan objected on the basis that it would have 
been illegal to do so. He argued that the provisions of section 18 of the 
Defence Act were not complied with. His explanation on why no attempt was 
made to approach the President or the Minister of Defence to authorize the 
sharing of the medical facilities in the interest of the community of Nkandla, in 
compliance with the Act, was that it was not his responsibility to do the work 
of the Minister of Health. This was in contrast with his legal counsel's opening 
remarks who had said that all was done in pursuit of cooperative governance 
as envisaged in section 41 of the Constitution. 



7.16.10. I found Lt Gen Ramlakan's attitude in this regard astonishing, especially in 
the light of his counsel's submissions on the constitutional imperative of 
cooperative governance. Cooperative governance apparently never came to 
Lt Gen Ramlakan's mind when he requested the construction of a medical 
facility at a cost of between R15 to R20 million, for the exclusive use of the 
President, his dependents and the staff looking after him, in an area where 
the majority of people are impoverished and have to be satisfied with a lack 
of proper medical facilities. 



7.1 6.1 1 . Curiously, the Minister of Defence and Military Veterans was reported on the 
DOD website on 19 February 2013 as having assessed the location and size 
of the Military Clinic, it is the DOD's view that save for minor adjustments, the 
clinic has adequate capacity to serve both requirements of the President as 
well as to provide services to the community of Nkandla. No mention was 
made of this reported view of the Minister in Lt Gen Ramlakan's evidence. 



321 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH flfEICfl 



7.16.12. Lt Gen Ramlakan also raised the issue of the security risk to the President 
should the Military Clinic be utilized for the benefit of the community. 
However, his contentions in this regard do not indicate why the same security 
measures that apply to the President during his daily travels, locally and 
abroad, could not be implemented by all the security personnel that have 
houses on the site. 



7.1 6.1 3. I also could find no evidence that the possibility of building the medical facility 
required in respect of the President in the vicinity of his residence, but in an 
area that would be accessible to ordinary members of the community, with a 
view of using it also as a community health facility, in consultation and with 
the assistance of the KwaZulu-Natal Department of Health, was properly 
considered and explored. Deputy Minister Bogopane-Zulu's ideas were 
clearly not allowed to gain any momentum. 



7.1 6.1 4. Lt Gen Ramlakan's evidence that there was no community facility available at 
the time when the Nkandla Project commenced where the requested medical 
facilities could be placed cannot be accepted. A report of the KwaZulu-Natal 
Department of Health, provided to me by Lt Gen Ramlakan and relied on by 
him to show that lack of medical facilities in the Nkandla area, state that in 
2009, there were at least 14 such community facilities that could have been 
considered. 



7.1 6.1 5. The following reference in this report, dated 5 November 201 3, is of particular 
significance: 



"Nkandla remains one of the most undeserved areas requiring greater effort 
for the improvement of service delivery to the community at large. The 
funding constraints have led to the curtailment of certain infrastructure 
development projects and this exacerbates the health challenges in the area 
whilst basic services have improved marginally, so too has health service 
delivery. Some gains have been made with the introduction of family health 



322 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



teams, planned patient transport vehicles which persist with referrals to high 
levels of care, maternity obstetric unit as well as school health promotion 
teams. The response time for ambulance services is well below the norm 
(less than 60 minutes in rural areas) and this is compounded by the fact that 
there are no advanced life support personnel in the sub-district. .." 



7.1 6.1 6. During the President's tenure and thereafter, the medical personnel deployed 
to the clinic will be idle most of the time. Their services could just as well 
have been utilised in the interest of the community of Nkandla, without 
jeopardizing the medical care that has to be provided to the President and 
staff members of the DOD and the SAPS. Additional security arrangements 
could obviously have been made whenever the President had to attend at the 
clinic. 



7.16.17. The issue of the poor road infrastructure is also not convincing as the 
President and his security entourage has access to all kinds of vehicles 
provided by the state and he travels by helicopter. 

7.16.18. I am also not convinced that the option of utilizing mobile structures, such as 
park homes or the mobile facilities provided for Mr Mandela's medical care, 
was properly considered by the SAMHS. According to Lt Gen Ramlakan, the 
main consideration why park homes could not be used, was that it would be 
illegal to store drugs in such a structure. I could find no confirmation for his 
contentions in this regard. The Good Pharmacy Practice in South Africa, a 
policy document setting minimum standards for pharmacy premises facilities 
and equipment, of the South Africa Pharmacy Council, provides for the 
storing of medicine in mobile facilities. The only conditions stated relate to 
ventilation, insulation and hygiene standards. 



7.16.19. However, even if it is undesirable, I could find no indication in the evidence 
that any cheaper option than to build a clinic was considered. There is also 
no evidence that the President, his dependents or the staff treated with 

323 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH flfEICfl 



medical care from park home structures on the site for the past five years 
were prejudiced or worse off than they would have been, had the care been 
provided from the permanent Military Clinic that was built at a cost of millions 
of rand. 



7.16.20. Counsel assisting Lt Gen Ramlakan in his submissions opted to draw an 
analogy between the Medical Clinic that was built for the exclusive use of the 
President, his dependents and the staff supporting him and the airport that 
was built by the former government in George in the Western Cape, allegedly 
for the late President P W Botha, whose private residence was in Wilderness, 
some 23 km away. I found the logic in this argument difficult to follow. The 
airport referred to is a public and not a military facility, used by several 
airlines and thousands of patrons annually. It was not built on the doorstep of 
where former President Botha's private residence was situated and it was not 
used exclusively by him and his dependents. 



7.1 6.21 . According to Lt Gen Ramlakan's evidence it was accepted from the start that 
that the DPW would be responsible for the cost of the Military Clinic and that 
the DOD was not regarded as a client department, is inconsistent with that of 
the Acting Director General of the DPW, Mr Malebye, who indicated that it 
was expected of the DOD and the SAPS to refund the DPW for the 
procurement of their requests and that the DPW was therefore only regarded 
as implementing agent. It is also inconsistent with the information provided by 
Mr Doidge, who was the Minister of Public Works at the time when the 
project started, stating that the DOD and the SAPS were of the DPW "client 
departments". 



7.16.22. The documentary evidence show that the Nkandla Project was paid for from 
the Prestige Programme in the DPW Capital Works budget, which regularly 
had to be augmented by means of reallocation from other necessary service 
delivery programmes. Mr Malebye and the current Director-General of the 
DPW stated during the investigation that initially, the Nkandla Project was 



324 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JC>LK C?CO>TCCTOf? 
SOUTH flfEIOl 



supposed to have been funded by savings made on other programmes of the 
Capital Works budget. 



7.16.23. Lt Gen Ramlakan's version that the Military Clinic was supposed to have 
been funded from a special category in the DPW budget, is therefore not 
supported by the evidence of other witnesses and the documentary evidence 
obtained during the investigation 

7.16.24. I noted during my site visit that due to the fact that the R11 million double 
storey building is located on a steep slope, substantial earth works had to be 
performed in the construction of the military clinic. It also includes garages for 
vehicles. I also observed that the clinic was not commissioned and the 
parking garage not utilized. 

7.1 7. The Helicopter Landing Pads and Crew Pavilion 

7.1 7.1 . The evidence and information obtained during the investigation indicated that 
the South African Air Force is responsible for the air transportation of the 
President during his tenure. 

7.17.2. Due to the decision taken that the President has to be transported to his 
private residence by air, adequate and safe landing facilities had to be 
constructed. It was also necessary to provide the helicopter pilots with 
adequate rest and nutrition facilities that comply with international aviation 
standards. 

7.1 7.3. It was noted during the investigation that the helicopter landing pads could be 
used for civil aviation purposes, once the President's term of office expired. 
However, it could not be indicated with certainty who would be interested in 
using a helicopter landing pad in such a rural area or that placing it closer to 
community facilities where it could serve a dual purpose, was considered. 



325 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.18. 
7.18.1. 

7.18.2. 
7.18.3. 
7.18.4. 

7.18.5. 

7.18.6. 



The Park Homes 

The evidence indicated that the procurement of park homes as temporary 
accommodation for staff was only done in March 201 1 , i.e. one year and ten 
months after the Nkandla Project commenced and Mr Zuma was elected as 
the President. 

It could not be determined with certainty where all the affected staff stayed 
from May 2009 to March 201 1 , except that a private dwelling of the President 
was utilized for SAPS members. 

The records of the DPW and the evidence of witnesses clearly indicated that 
the decision to provide temporary accommodation was as a result of 
instructions given by the Minister or Deputy Minister of Public Works 

Although it is not in dispute that temporary accommodation was required for 
the staff assigned to look after the security of the President, it could not be 
established why this obvious need was not planned for by the DPW when the 
Nkandla Project commenced. 

The fact that permanent accommodation has been constructed at huge cost 
to the state for the staff and that it is currently not used, is disconcerting. The 
continued occupation of the park homes also deprives other state institutions 
of temporary accommodation that is required by it. 

The park homes belong to the state and should be utilized in a manner that 
constitutes value for money. 



326 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



7.1 9. The relocation of the kraal and culvert 

7.19.1. It was explained by the officials and consultants involved in the Nkandla 
Project that the President's kraal for his farm animals had to be relocated for 
security reasons. 

7.19.2. However, during my site visit, I noted that the new kraal has an elaborate 
design and that it is linked to a culvert that allows animals to exit and enter 
under the fence. It was also not clear why the animals could not use a normal 
gate. 

7.19.3. The construction of the kraal, incorporating a chicken run and culvert, was 
included in the general site works, at an estimated cost of R1 .2 million. 

7.1 9.4. Although reference was made during the investigation to the relocation of the 
kraal, the position of the original kraal could not be indicated to me during my 
site visit. There was still a kraal at the centre of the original homestead that is 
clearly being used. It was explained to me that it is only used for ceremonial 
purposes. 

7.19.5. During my meeting with the President in regard to the investigation on 11 
August 2013, he indicated that when the movement of the kraal was 
discussed, he had engaged "government on a relocated larger kraal to 
accommodate his increased livestock, while keeping the existing one as a 
ceremonial kraal. He further indicated that he would be amenable to 
refunding the state for the cost incurred. 

7.20. The Swimming Pool, Amphitheatre and Visitors' Centre 

7.20.1 . The evidence indicated that the idea of a fire-pool was at some stage of the 
Nkandla Project combined with the idea of building a swimming pool for the 
occupants of the President's private residence. 



327 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.20.2. The amphitheatre was clearly designed and constructed with a view of open 
air functions. 

7.20.3. The Visitors' Centre forms an integral part of the entrance to the President's 



private residence. It could not be established why visitors could not be 
accommodated at the adjacent clinic or the guard house at the entrance 
gate. At the time of my site visit, I noted that the Visitors' Centre had recently 
just been used for a private function, which confirmed the impression that it 
has little, if anything to do with the security of the President. 



7.20.4. In the absence of clear justification for the costly choices, it is difficult not to 



conclude that the designers of the project decided to create a recreational 
area close to the President's dwellings, under the auspices of combining the 
facilities with the need for a fire-fighting capability in terms of a water 
reservoir and landscaping to rehabilitate soil. The Visitors' Centre was added 
to complete the picture. There is no indication in the evidence that 
alternatives, such as the installation of a water reservoir similar to the one 
that was installed for household purposes, other landscaping methods and 
alternative facilities for visitors were seriously considered. 



7.20.5. The lack of explanation regarding why more economic options were ignored, 



and the snippets regarding minutes regarding aesthetic fit (for the President) 
leave a distinct impression that this was again a situation of designing the 
ideal stately environment, because it is the President's residence, rather than 
focusing on what was necessary and affordable. 



7.21 . Relocation of Adjacent Households 

7.21.1. Two different justifications can be gleaned from the evidence of why the 
neighbours were moved. 



328 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



7.21.2. Mr Makhanya said it was to ensure a straight fence, while the motivation in 
the relevant internal memo was "too close for security". I could find no 
evidence that the possibility of keeping the households where they were and 
finding alternatives for the security installations that could save the expense 
of relocation, were properly investigated and considered. There was also no 
indication that any comparison of the cost to adapt the security detection 
systems and the fence to accommodate the households was ever made and 
evaluated. 

7.21 .3. It was pointed out earlier that neither of the two security evaluation reports of 
the Security Advisory Service of the SAPS recommended the relocation of 
the households or identified their presence as a risk to the security of the 
President. 

7.21 .4. It is common cause that the modest rondavels were replaced with 1 5 modern 
rondavels, at a cost to the state of almost R8 million (R2 million per 
household), which equates to the construction of at least 40 RDP houses. 

7.21 .5. As in the case of other items referred to in this report , the only inference that 
I can draw from the evidence relating to the relocation of the households is 
that the DPW allowed the consultants to decide what should be done and to 
design accordingly. I got the impression from the observations made during 
my site visit that it was probably rather the aesthetic impact of leaving the 
dilapidated structures where they were that bothered the designers of the 
Nkandla project, than the impact it could have had on security. 

7.22. Roads, Paving and Walkways 

7.22.1. It was very obvious during my site visit that the implementation of paving at 
the premises was elaborate. 



329 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH flfEICfl 



7.22.2. Although the evidence indicated that paved roads and walkways were 
required in certain areas as part of the Nkandla Project, such as the patrol 
roads, the construction of the swimming pool and amphitheatre included a 
large area of paving, which could clearly have been avoided, if reasonable 
care had been taken. 

7.22.3. The impression also in this case was unavoidable that the DPW allowed the 
consultants to design as they pleased and that very little, if any, consideration 
was given to alternatives and the quantity of roads and paving that was really 
necessary for the effective protection of the President. 

7.23. The Safe Haven 

7.23.1. The first Security Evaluation Report of the Security Advisory Service of the 
SAPS dated 28 May 2009, recommended reinforcement of one room of the 
President's dwelling with various security features identified in the Minimum 
Physical Security Standards. Brigadier Adendorff stated in her evidence that 
these measures were sufficient to protect the President in case of an 
emergency. 

7.23.2. The estimated cost of creating a safe haven as determined by R&G 
Consultants in February 2010 was R457 971 . There was no indication at that 
time that the more elaborate facility that was eventually built was envisaged. 

7.23.3. However, by July 2010 there was already a plan to construct a security 
services safe area and the estimated cost increased to more than R3 million. 

7.23.4. Cost Estimate 5 prepared by R&G Consultants on 16 August 2010 clearly 
indicate that a more elaborate and differently located safe haven was 
designed, which was initially estimated at R8.3 million but had escalated to 
about R19 million by the time this investigation was concluded. 



330 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.23.5. I was surprised to note that despite the fact that the more extensive facility 



was already designed and costed by August 2010, the second Security 
Evaluation Report of the SAPS issued in September 2010 still recommended 
a modest facility on the surface. Even more disconcerting is that Brigadier 
Adendorff appears to have been aware of the intention to jettison the plan for 
a modest safe haven in favour of the extensive and expensive design as she 
was part of the Project Team and had discussed the idea with Mr Makhanya. 
As a result, the original approach on the safe haven changed substantially. 



7.23.6. No reasonable explanation could be provided by the officials involved in the 



Nkandla Project as to why it was decided to build the extensive and 
expensive safe haven. Mr Rindel regarded it as an instruction from DPW "top 
management". 



7.23.7. From the evidence it appeared that the idea originated from Mr Makhanya 



and that it was supported by the SAPS, despite its formal recommendation of 
a far less elaborate and much cheaper option. Again, the ideal situation was 
pursued rather than the necessary and affordable one. 



7.23.8. At the time of the conclusion of the investigation the cost of the safe haven 



had escalated to more that R19 million. The scope of this part of the Nkandla 
Project started at a cost of about half a million Rand and was allowed to 
increase to about R19 million, i.e. with approximately R18.5 million. The 
reality is that at R19 million the safe haven still needed some work at 
additional cost at the time when the investigation was concluded. 



7.24. The Staff Accommodation 

7.24.1 . The location of the President's private residence in a rural area about 47 km 



from the nearest small town and the fact that his security involves several 
staff members of the SAPS and the DOD necessitated the provision of 
accommodation for them. 



331 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



7.24.2. However, there was no prescript in respect of the design of the 
accommodation units nor was there any justification for anything more than a 
small block of flats or barracks, instead of individual units. 

7.24.3. During the site visit, I noted that the buildings constructed in this regard were 
clearly designed to blend in with the thatched roof designs of the other 
structures that conformed to the design of the President's houses. 

7.24.4. The bachelor rondavels that were built consist of one bedroom with a kitchen 
facility and a very small bathroom, which would clearly not be suitable for the 
accommodation of a small family. Yet, the accommodation was built at a cost 
of R17,5 million, which equates to R437 500 for a unit that is smaller than an 
RDP house. 

7.24.5. Lt Gen Ramlakan indicated to me that as these buildings belong to the state 
and do not form part of the President's residence, it would be possible to 
utilize some of it for community purposes when the President's term expires. 

7.24.6. However, on questioning, it was clear that there was no plan on what the 
state could use these buildings for in the future. The houses built for the staff 
are not in the immediate vicinity of any community facility and it would 
therefore be problematic to utilize the precinct effectively. I could find no 
evidence that the possibility of locating the staff houses closer to community 
facilities or to base them at the satellite police station in the Nkandla area 
with a view of effective and economic utilization in the interest of the 
community when the President's tenure expires, was interrogated and 
considered. 

7.24.7. I could also not find any reasonable indication why the possibility of 
temporary accommodation in the form of park homes was not considered, 
due to the fact that the accommodation would not be required indefinitely. 



332 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.24.8. During my site visit I noted that that some of the staff already based at the 



President's private residence was in any event still living in the temporary 
park homes as some of the flats had not been completed. Officials of the 
DPW and the SAPS indicated that all works stopped when investigations into 
the project were launched. The impact of this is that the state already paid for 
buildings that are not being used, whilst temporary accommodation that could 
be moved and utilized elsewhere is still being occupied. 



7.25. The Private Project Manager 

7.25.1. The appointment of the private Project Manager at an additional cost of R5 



million was only considered when there were already substantial delays in 
the completion of the Nkandla Project and after a former Minister of Public 
Works started, to intervene due to the complaints of the President. 



7.25.2. The evidence indicated that this could have been avoided if the DPW 



planned the implementation of the Nkandla Project properly and capacitated 
the Regional Office to enable it to manage the project when its scale was 
known and construction commenced. 



7.25.3. Mr Rindel indicated in his evidence that he realized early in the process that 



the scale of the project was too large for him to handle alone. However, I 
could find no indication during the investigation that he complained or 
requested assistance. It should also have been obvious to Mr Khanyile, who 
was directly involved, and to the DPW and other officials that formed part of 
the Project Team. 



333 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



7.26. Landscaping 

7.26.1. The fact that the Nkandla Project was implemented on what was previously 
largely indigenous veld on a steep slope, required considerations of storm 
water management and resettlement of vegetation that had to be removed. 

7.26.2. However, it is the scale of the landscaping that was implemented that I found 
disconcerting. 

7.26.3. The evidence indicated that the Landscape Architects were subcontracted 
under Mr Makhanya and that he was mainly responsible for their designs. 

7.26.4. It was clear from the evidence and original designs of the Landscape 
Architects that they understood their brief to create a stately residence and 
the fact that it was a private residence and that the landscaping interventions 
had to be paid for by public funds, had no impact on their original ideas. This 
was evident from their original designs that were costed at R18.6 million, 
excluding their professional fee. 

7.26.5. The consideration of alternatives that were really necessary in respect of 
landscaping and reasonably affordable does not seem to have been their 
brief when they were appointed. They obviously designed the ideal and then 
scaled down instead of looking at the real need and cost to the tax payer. 

7.26.6. Despite the fact that the original design was scaled down quite dramatically, 
the landscaping in the end still amounted to more than R7 million. 

7.26.7. Reference is made in this report to elaborate paving of walkways, patrol 
roads and the entrance area. The construction of an amphitheatre, a terrace 
around the swimming pool and an area where a marquee tent can be erected 
(the so called "social node") was elaborate and do not appear to relate in any 
manner to the security of the President. One of the officials involved in the 



334 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.26.8. 

7.27. 
7.27.1. 

7.27.2. 

7.27.3. 
7.27.4. 
7.27.5. 



project confirmed in a response to the evidence and information obtained 
during the investigation that discussions relating to the areas including the 
amphitheatre and the terraced pavilion that, at the time it was designed, 
related to expected future functions for which the DPW would be responsible. 

The unavoidable impression from my investigation is that a substantial 
amount of public funds could have been saved in respect of the expenditure 
incurred for landscaping, if more care had been taken by the DPW. 

The Apportionment of Costs 

When Deputy Minister Bogopane-Zulu became involved in the Nkandla 
Project she got the impression that some of the planned expenditure might 
have to be for the account of the President, as it did not relate directly to 
security issues. 

The document indicating an apportionment of the estimated costs between 
the DPW and the President was only prepared in March 2011, i.e. one year 
after the appointment of the contractors was approved and 22 months after 
the Nkandla Project commenced. 

I noted from the contents of the apportionment document that the majority of 
items listed under "private" related to landscaping, some of which, according 
to the evidence of Mr Rindel, was not implemented. 

Other items that were listed for the account of the President included 
"builders work", "lightning protection", "reticulation", and a portion of the "fire 
pool and parking". 

I could find no evidence that the President, Minister or Deputy Minister of 
Public Works ever responded to the submission of the apportionment of cost 
estimates. 



335 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.27.6. 



7.27.7. 



7.28. 
7.28.1. 

7.28.2. 
7.28.3. 



However, during my meetings with the Ministers of Public Works, State 
Security and Police, they indicated that they were aware of the document, but 
did not agree with its contents and were making further enquiries. It was not 
clear to me how the document got to the Ministers as there was uncertainty 
in the evidence whether it ever reached the former Minister of Public Works 
and the President. 

The fact that the DPW did not ensure from the time that the project 
commenced that the President was informed and that his response was 
obtained in respect of any planned interventions on the land that he occupied 
that he might have to pay for, is a further indication of the lack of planning 
and management. 

PART E: THE INVOLVEMENT OF THE IDC AND ALLEGATIONS OF 
IMPROPER BENEFITS AFFORDED TO THE PRESIDENT'S BROTHERS 

The Financial Assistance Provided to Bonelena by the IDC 

The evidence in this regard indicates that although Bonelena applied for 
financial assistance from the IDC shortly before the first contract for the 
Nkandla project was awarded to it by the DPW, the later awarding of the 
contract was part of the information that was considered in its application. 

However, the records of the IDC also contain information about other projects 
that Bonelena were involved in and other contracts awarded to it. 

The investigation by the IDC into the financial affairs of Bonelena was 
extensive and conducted over a period of months. The fact that Bonelena 
was registered at the CIDB at the time that it conducted its own due diligence 
into Bonelena's affairs before it awarded it a grading of 7GB PE, was also 
considered by the ICD. 



336 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.28.4. I found no indication in the information that could be obtained during the 



investigation that the decision by the ICD to approve Bonelena's application 
for financial assistance was improperly influenced or that it was not properly 
considered in terms of its mandate, powers and functions. 



7.28.5. The financial exposure of the IDC due to Bonelena's liquidation was 



mitigated by its offer of compromise that was accepted and its discharge from 
liquidation in February 2013. At the time of the conclusion of the 
investigation, the ICD was in a position to continue with the recovery of the 
financial assistance that it provided to Bonelena in February 201 1 . 



7.29. The Allegation that the President's Brothers Benefitted from the 
Security Project 

7.29.1 . The allegation that two brothers of the President, Messrs Micheal and Joseph 



Zuma received electrical equipment that was destined for or ordered under 
the Nkandla Project and paid for by the state, was based only on the 
contents of invoices that were attached to court papers relating to a civil 
proceedings between a supplier (Voltex) and a contractor involved in the 
Nkandla Project (Moneymine). 



7.29.2. The civil claim related to a dispute about payment for certain items supplied 



by Voltex to Moneymine for its different projects, including the Nkandla 
Project. No other evidence or information was provided supporting the 
allegations that Messrs Zuma received electrical equipment that was paid for 
by the state. 



7.29.3. From the investigation, it was established that the said invoices contained 



references to the supply of goods to Moneymine in connection with a number 
of its clients, including Messrs Zuma, "Nkandla", "dbnprestige", "vulekela", 
"highflats" and others. The items that were ordered from Voltex for Messrs 



337 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.29.4. 



7.29.5. 
7.29.6. 

7.29.7. 

7.30. 
7.30.1. 



Mike and Joseph Zuma were of a general electrical nature and included 
cabling, switches and sockets. The total amount of these items was 
R6 278.55. It was invoiced under their names and there is no indication on 
the invoices that it formed part of orders that related to the Nkandla project. 

The evidence obtained during the investigation confirmed that Moneymine 
had a number of other clients during the period that it was involved in the 
Nkandla Project. It is an established construction company and has been 
doing business in the KwaZulu-Natal Province for years. The address and 
references that appeared on the invoices were also not related to the 
Nkandla Project or the President's private residence. 

I could find no evidence in the payment certificates and other procurement 
documents of the DPW relating to the Nkandla Project or from the witnesses 
interviewed that Moneymine or Voltex was paid by the DPW for items that 
Messrs Joseph and Mike Zuma purchased. 

The explanation provided by Mr and Mrs Mfeka of Moneymine that Messrs 
Mike and Joseph Zuma ordered the items concerned as separate clients in 
terms of their own small projects, was supported by the contents of the 
invoices and also the information provided by Voltex. 

Accordingly, I could find no substance during the investigation for the 
allegations in this regard which could have warranted further investigation. 

The Evidence in Respect of the President's Involvement in the Project 

The evidence indicates that officials of the DPW and the SAPS met with the 
President at his private residence on 12 August 2009 to inform him of the 
security measures that were to be installed at his three new dwellings, the 
construction of which commenced on 24 August 2009. The minutes of a 
Progress Meeting held shortly after the Deputy Minister was taken off the 



338 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEIOl 



project seem to suggest that the matters she raised with the President were 
resolved. 



7.30.2. In his submissions on the evidence and information obtained during the 
investigation, dated 14 February 2014, the President stated that at this 
meeting he introduced Mr Makhanya as his architect to senior government 
officials "and to appraise each other of their respective plans." He denied 
influencing Makhanya's appointment as Principal Agent. 

7.30.3. By May/June 2010 the President complained about the slow progress made 
with the implementation of the Nkandla Project, which was impacting on his 
private and family life. 

7.30.4. The President stated in his submissions in this regard that "my request to 
expedite the construction was a genuine attempt to address the delays and 
not to otherwise influence the process. " 



7.30.5. According to the evidence Mr Makhanya supposedly had discussions with 
the President about the landscaping of the premises in August 201 and May 
201 1 . He also presented the President with the design of the swimming pool. 
In fact there are numerous references to reported or contemplated design 
meetings between the two in the project progress minutes alluded to in the 
evidence. 

7.30.6. Deputy Minister Bogopane-Zulu stated in her evidence that the President 
supported her idea that the fire pool should converted into a swimming pool 
to be used by the children of the village. She labelled this a developmental 
approach. The evidence further indicates that Mr Makhanya apparently 
discussed the possibility of private costing in respect of the conversion of the 
fire-pool to a swimming pool with the President as well as "infrastructure 
requirements. " 



339 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH flfEICfl 



7.30.7. It is common cause that the President requested a former Minister of Public 
Works, Mr G Doidge, to look into the delay of the project, as a result of which 
the latter got directly involved in order to expedite the process. 

7.30.8. The evidence further show that the former Minister of Public Works, Ms 
Mahlangu-Nkabinde, informed the President in writing, on 5 November 2010, 
of the details of the progress made with the implementation of the Nkandla 
Project. According to the evidence of officials of the DPW, it was their 
impression that the President indicated that he was satisfied with the 
progress report presented to him. 

7.30.9. When Deputy Minister Bogopane-Zulu became involved in the Nkandla 
project, she, according to her evidence, discussed the details thereof with the 
President. According to her, he raised concerns about the relocation of the 
households as he has known them all his life and he did not want them to be 
prejudiced. The President also told her that he did not want new contractors 
on the site. He indicated that he was opposed to more contractors being 
involved during phase 2 of the project than those that were implementing 
phase 1 . 

7.30.10. Deputy Minister Bogopane-Zulu further indicated in her evidence that the 
President supported her idea that the Military Clinic should also be used for 
community purposes. The minutes corroborate anticipated discussions 
between these two in this regard. 

7.30.11. The minutes of a Progress Meeting held on 28 September 2011 recorded 
that Mr Makhanya stated that the President had raised his concern about the 
slow progress of the Nkandla Project and that the premises might not be 
available for him to use during December 201 1 . 

7.30.12. The evidence of Brigadier Adendorff and Mr Rindel also indicated that the 
President raised his concern about the design of the bullet resistant windows 



340 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.30.13. 

7.30.14. 

7.31. 
7.31.1. 

7.31.1.1 

7.31.1.2 

7.31.1.3 
7.31.1.4 
7.31.1.5 



that had to be installed. This resulted in a change of the design that was 
implemented. 

As already alluded to above, the President indicated to me during the 
investigation that he was involved in the decision to build a new kraal. In his 
response to the Provisional Report, the President did not deny this. 

I could find no evidence or indication that the President ever enquired into the 
scale of the Nkandla Project that was being implemented at his private 
residence or the cost thereof. 

The President's Reply to My Questions: 

The statement that the President provided to me in response to written 
questions put to him relating to the matters investigated confirmed that he: 

Initiated private improvements of his private residence at Nkandla and 
appointed Minenhle Makhanya Architects in this regard; 

Was briefed by former Minister Doidge and senior officials of the SAPS and 
other government departments on the security requirements that had to be 
implemented at his private residence, shortly after he took office; 

Was present at a meeting between these officials and Mr Makhanya where 
the impact of the security measures on his private dwellings was discussed; 

Received briefings on the project from time to time from various Ministers 
and Mr Makhanya; 

Expressed his concern about the delay in the implementation of the project; 
and 



341 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.31.1.6 



7.31.2. 



7.31.3. 



7.31.4. 



7.31.4.1 



7.31.4.2 



7.31.4.3 



7.31.4.4 



7.31.4.5 



Complained about the initial design of the bullet resistant windows that was 
installed. 

The President declined the opportunity to respond to the allegation that he 
misled Parliament by making a false statement about the financing of the 
private development at his private residence and referred me to Parliament in 
this regard. He also declined me the opportunity to have access to his bond 
documents. 

However, with the assistance of the Director-General of the Presidency, I 
established on 17 December 2013 from the Register of Financial Interests 
that the President has declared a mortgage bond in respect of his private 
residence at Nkandla since 2009. I was also given the assurance by the 
President's legal team that the mortgage bond is still in place 

The President furthermore did not respond to my questions in connection 
with: 

Whether he or the Presidency requested that security measures be installed 
at his private residence; 

Whether he was at any stage informed of the cost of the proposed security 
measures; 

Whether a notice declaring his private residence a National Key Point was 
served on him; 

What he understood to be his responsibilities as the owner of a National Key 
Point; 

What measures he took to secure his private residence as required by the 
National Key Points Act; 



342 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



7.31.4.6 Whether he was advised that some of the cost of securing his private 
residence as a National Key Point would be recovered from him; 

7.31 .4.7 Whether he was presented by Mr Makhanya with the designs of the project; 

7.31 .4.8 Whether he received the letter consisting of a detailed report on the progress 
made with the project that was addressed to him by former Minister 
Mahlangu-Nkabinde on 5 November 2010; 

7.31.4.9 Whether he received the document setting out the apportionment of cost for 
the project that was prepared by the DPW; 

7.31.4.10 Whether Deputy Minister Bogopane-Zulu discussed the conversion of the 
fire-pool to a swimming pool with him and whether he was aware of the 
reasons for this conversion; 

7.31.4.1 1 Whether he was consulted about the relocation of the households that were 
affected by the implementation of the project; 

7.31.4.12 Whether he was opposed to more contractors working on the site during 
phase 2 of the project; 

7.31.4.13 Whether Deputy-Minister Bogopane-Zulu discussed the design of the Military 
Clinic with him; 

7.31.4.14 Whether he would be willing to disclose the amount that he paid for the 
construction of the new dwellings on his property; 

7.31 .4.1 5 How often he uses his private residence for official business; 



343 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.31.4.16 Why he would prefer using his private residence for official business rather 
than one of the official residences available to him; 

7.31 .4.1 7 Whether he at any stage enquired into the cost of the project; and 

7.31.4.18 If not, whether he as the head of state did not feel obliged to do so as a 
substantial amount of public money was obviously being spent. 

7.31.5. On 13 January 2014, I provided the President with a copy of my Provisional 
Report on the investigation and afforded him the opportunity to respond to 
any information or evidence that appeared to implicate him. 

7.31.6. The President provided me with submissions on the contents of the 
Provisional Report on 14 February 2014, which were presented to me by the 
legal team assisting him, on 21 February 2014. 

7.31.7. In his submissions, the President referred to my compliance with the 
Executive Members Ethics Act and my views on the application of the 
National Key Points Act. 

7.31 .8. Referring to how the contents of the Provisional Report, in his view, related to 
him as a person, the President stated, inter alia, that: 



"At no stage have I been appraised of the fact that my conduct forms part of 
any investigation either by the Public Protector or any other institution and my 
statement is framed in the light of this appreciation. 

It now appears apparent that unbeknown to me, my conduct, ethical and 
otherwise in fact forms part of the Public Protector's investigation. 

Had I in fact known that my conduct was under investigation by the Public 
Protector, I most probably would have elected to approach the matter 



344 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




differently, not least of which would have been to persist in my request by all 
means possible for access to the documents and statements upon which 
certain assertions were based. 

I consider this to be unfair and a breach of my constitutional right to be made 
aware of my role in the investigation and the case that I have to meet. 
Consequently, this impacts on the findings and evaluations contained in the 
report insofar as they relate to me. I have no way, notwithstanding the 
opportunity to comment on this provisional report, to address this apparent 
procedural unfairness. 

The Public Protector is aware that I have made repeated requests to be 
furnished with copies of documents which are the bases for certain 
averments and allegations in order that I may better understand the context 
and import of such. 

These requests have been consistently denied under the blanket approach of 
protecting the identity of the complainants/witnesses, notwithstanding that 
fact that some of these persons are known to me, others government 
officials, others still political leaders and oft quoted academics. " 



7.31.9. I was quite astonished by these submissions of the President, for the 
following reasons: 

7.31.9.1 Shortly after I received the first complaint in connection with the security 



upgrades at the President's private residence on 13 December 2011, I 
informed the Director-General of the Presidency of the complaint and met 
with him in regard thereto in January 2012. I believe that it was reasonable to 
accept that Dr Lubisi informed the President accordingly. 



7.31.9.2 On 15 February 2012, I wrote to the President directly, informing him of the 
complaint that I received from a member of the public that was based on the 



345 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH flfEICfl 



article published by the Mail & Guardian newspaper on 11 November 2011 
(referred to in paragraph 2.1 above) and that I would be investigating the 
matter. 



7.31 .1 0. I informed Dr Lubisi accordingly in writing on the same day. 



7.31.1 1. On 20 February 2012, I received an acknowledgement of receipt of my letter 
addressed to the President from the Administrative Secretary: Presidential 
Support Services that stated that it was received and would be brought to his 
attention. 



7.31 .1 2. I received further complaints in December 201 2. 



7.31.13. In my letter addressed to the President dated 29 January 2013, I informed 
him of the further complaints and stated inter alia that: 



"The Parliamentary Leader of the Democratic Alliance, Ms L Mazibuko, 
lodged a further complaint against you in terms of the provisions of the 
Executive Members' Ethics Act, 1998. Her complaint is based on allegations 
published by the media on 2 December 2012, allegeing that Messrs Michael 
and Joseph Zuma, members of your family, benefitted improperly from the 
development project at your private residence when they received supplies 
destined for it, delivered to their komes. Ms Mazibuko requested that I 
establish whether these allegations are true, and if so whether or not it 
constituted conduct in violation of the Executive Ethics Code on your part. 

Prof P De Vos of the University of Cape Town lodged a complaint with me 
relating to a statement that you made in the National Assembly on 15 
November 2012, when you reportedly indicated that the development of the 
first phase of your private residence was financed by a commercial bank that 
secured a mortgage bond in respect of the property." 



346 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEIOl 



7.31 .1 4. I further explained to the President that subsequent media reports suggested 
that no such bond was registered and that, according to Prof De Vos there is 
no clarity whether the non-security related construction works at his private 
residence was indeed financed by him. I stated that: 

"He (Prof De Vos) contends that it is in the public interest for the Public 
Protector to determine whether you 'willfully mislead' the National Assembly 
in regard to this matter, which in his view, would constitute a violation of the 
Executive Ethics Code. " 

7.31.15. In addition, I requested the President to provide me with a copy of the 
registered bond and other relevant documents relating to his financing of his 
private residence. 

7.31.16. On 11 March 2013, I informed the President that my investigation was 
progressing and requested him to provide me with the documents previously 
requested. My office received an acknowledgement of receipt from the Chief 
of Staff in the Private Office of the President, on 12 March 2013. 

7.31.17. Mr J S Mabelane, the Acting Head: Legal and Executive Services of the 
Presidency wrote to me on 4 April 2013, requesting copies of the complaints 
referred to in my letters addressed to President on 29 January 2013 and 13 
March 2013. 

7.31.18. In my response on 11 April 2013, I explained the reasons why the Public 
Protector, as a matter of principle, does not provide interested and affected 
parties with copies of letters of complaint. However, I provided him with a 
detailed outline of the complaints, which I also included in the Provisional 
Report that was provided to the President on 14 January 2014. 



347 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




7.31.19. On 29 July 2013, I wrote to the President, informing him of my intended visit 
to the Nkandla Project and again requested the information previously 
requested that was still not provided. 

7.31.20. I met with the President on 11 August 2013 in connection with my 
investigation and presented him with a set of written questions with the 
relevant documents, which he agreed to respond to. 

7.31.21. The Director-General in the Presidency addressed a letter to me on 10 
September 2013 requesting information to enable the President to respond to 
the questions presented to him on 1 1 August 2013. 

7.31.22. The President responded to me on 30 September 2013 as indicated in 
paragraph 6.86 above. 

7.31 .23. Due to fact that I was concerned that the President had not responded fully to 
all my questions, I provided a further opportunity in my letter addressed to 
him on 8 October 2013. 

7.31.24. In his response, dated 24 October 2013, the President, requested more 



information, to which I responded in detail on 29 October 2013. I attached to 
my response copies of documents that had already been provided to him 
earlier, which included: 



7.31.24.1 The Declaration Certificate declaring his private residence a National Key 
Point signed by the Minister of Police on 8 April 201 0; 

7.31.24.2 The Internal Memorandum signed by the former Minister of Public Works on 
5 November 2010 informing the President in detail of the progress made with 
the implementation of the Nkandla Project; and 



348 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC f>e«oi 

SOUTH flfl 



7.31.24.3 A document dated 11 March 2011 prepared by R&G Consultants and the 
DPW setting out the apportionment of costs of the Nkandla Project. 

7.31.25. The correspondence with the President and the Presidency referred to 
above, my personal meeting with him and the fact that the President was 
provided with a copy of my Provisional Report of more than 300 pages 
setting out in detail the complaints that I received and the issues that were 
investigated, in my respectful view, provided the President with sufficient and 
detailed information to enable him to respond to areas of the evidence and 
information that appeared to implicate him. 

7.31 .26. I therefore could not find any merit in his submissions that he was unaware of 
my investigation and the complaints lodged against him and that he was not 
provided with sufficient evidence and information to enable him to respond 
thereto. I informed the President accordingly in a letter addressed to him on 4 
March 2014 in response to his submissions, setting out the sequence of my 
interactions with him and the Presidency relating to my investigation, 
attaching copies of the relevant correspondence. 

7.31.27. In concluding his submissions of 14 February 2014, the President expressed 
the views that the investigation was "allowed to drag on for a lengthy period 
with all manner of comments and judgments by all and sundry." He also 
referred to the leaking of what purported to be versions of my Provisional 
Report to the media and the impact that it, in his view, had on the 
investigation and the integrity of the office of the Public Protector. 

7.31.28. In summary, the President submitted that my Provisional Report: 
"Is tainted by lack of proper procedure; 

Has not applied the rules of natural justice; 



349 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



Suffers from a lack of integrity in that this has been compromised by 
persistent leaks and public pronouncements; 

Has adopted the incorrect legal framework in assessing the implementation 
of the security upgrades. " 



7.31.29. As I have already indicated, all the affected and interested parties were 
afforded a full opportunity to engage me on the evidence and information 
obtained during the investigation that appeared to implicate them. I have 
considered every comment and submission, including that of the President 
for the purpose of this final report and made changes and corrections, where 
applicable to my provisional views, conclusions and findings. I have also 
alluded in detail to compliance with the relevant legislation and legal 
processes, after having considered the submissions made in this regard by 
the different parties, including the President. 

7.31.30. Earlier in the report I have addressed the concerns regarding leaks and 
delays. I have also addressed the procedural fairness. In my respectful view, 
the President's concerns have no basis in fact or law. 

8. THE LEGAL AND REGULATORY FRAMEWORK 

8.1 . The Legal Framework Regulating the Ethical Conduct of the President 
and Other Members of the Cabinet and that of Deputy Ministers 

8.1.1. The Constitution 

8.1.1.1 Section 83 provides that the President is the Head of State and that he/she 
must uphold, defend and respect the Constitution as the supreme law of the 
Republic. 



350 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JC>LK C?CO>TCCTOf? 
SOUTH flfEIOl 



8.1 .1 .2 The Cabinet consists, in terms of section 91 , of the President, as head of the 
Cabinet, a Deputy President and Ministers. 



8.1.1.3 Members of the Cabinet are, by virtue of the provisions of section 92(2), 
collectively and individually accountable to Parliament for the exercise of their 
powers and the performance of their functions. They must, in terms of section 
92(3) act in accordance with the Constitution. 



8.1 .1 .4 Section 96 provides that: 



"(1) Members of the Cabinet and Deputy Ministers must act in accordance 

with a code of ethics prescribed by national legislation. 
(2) Members of the Cabinet and Deputy Ministers may not 

(a) undertake any other paid work; 

(b) act in a way that is inconsistent with their office, or expose 
themselves to any situation involving the risk of a conflict between their 
official responsibilities and private interests; or 

(c) use their position or any information entrusted to them, to enrich 
themselves or improperly benefit any other person. " 



8.1.2. The Executive Members' Ethics Act 



8.1 .2.1 Section 2 of this Act provides for the publishing by the President of a code of 
ethics, as contemplated by section 96 of the Constitution. 



8.1 .2.2 The Public Protector must, by virtue of the provisions of sections 3 and 4 
investigate complaints against a Cabinet member (which includes the 
President) or a Deputy Minister when it is lodged by a member of the 
National Assembly. 



351 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




8.1 .2.3 A report on the investigation against a Cabinet member must, in terms of 



section 3, be submitted to the President, who has to submit a copy thereof 
and any comments thereon to the National Assembly within 14 days, 
together with a report on any action taken or to be taken in regard thereto. 



8.1.3. The Executive Ethics Code 

8.1.3.1 This Code was published in terms of section 2 of the Executive Members' 
Ethics Act. 

8.1 .3.2 Paragraph 2 requires of Cabinet members inter alia to: 



(a) perform their duties and exercise their powers diligently and honestly; 

(b) act in good faith and in the best interest of good governance; 

(c) act in all respects in a manner that is consistent with the integrity of their 
office or the government. 



8.1 .3.3 Paragraph 2.3 provides, inter alia, that members may not act in a way that is 
inconsistent with their position. 

8.1 .3.4 When considering appropriate international bench marks I came across the 



Code of Ethics for US Government Service, which constitutes a transversal 
Code of Ethics for all public office bearers and employees in the United 
States of America (USA). The Code provides that : 

" Any person in Government service should: 

1. Put loyalty to the highest moral principles and to country above loyalty to 
Government persons, party, or department. 

2. Uphold the Constitution, laws, and legal regulations of the United States 
and of all governments therein and never be a party to their evasion. 



352 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



3. Give a full day's labor for a full clay's pay; giving to the performance of his 
duties his earnest effort and best thought. 

4. Seek to find and employ more efficient and economical ways of getting 
tasks accomplished. 

5. Never discriminate unfairly by the dispensing of special favors or privileges 
to anyone, whether for remuneration or not; and never accept for himself or 
his family, favors or benefits under circumstances which might be construed 
by reasonable persons as influencing the performance of his governmental 
duties. 

6. Make no private promises of any kind binding upon the duties of office, 
since a Government employee has no private word which can be binding on 
public duty. 

7. Engage in no business with the Government, either directly or indirectly 
which is inconsistent with the conscientious performance of his governmental 
duties. 

8. Never use any information coming to him confidentially in the performance 
of governmental duties as a means for making private profit. 

9. Expose corruption wherever discovered. 

10. Uphold these principles, ever conscious that public office is a public 
trust." 

8.1 .3.5 While our Constitution is brief on the specific provisions regarding ethics, if 
we take the provisions of section 195 on principles of public service and 
section 237 of the Constitution requires that constitutional obligations be 
performed diligently and without delay. This import of our constitutional 
architecture on the ethical standards expected of public office bearers and I 
believe, officials cannot be far from the 10 ethical standards expected of all 



353 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




persons entrusted with public power and control over public resources in the 



8.1 .3.6 At a workshop on ethics, hosted by the Joint Chairpersons of the 



Parliamentary Joint Committee on Ethics and Members Interests, it was 
agreed that a universal code of ethics for all entrusted with public power and 
control over public resources should be developed and implemented 
throughout the public sector and that there were gaps in the Parliamentary 
Codes of Ethics, the Executive Code of Ethics and other sector codes, which 
should also be addressed. 



Implementation of Security Measures at the Private Residence of the 
President 



8.2.1. The Application of the Ministerial Handbook as Approved by the Cabinet on 7 
February 2007 

8.2.1.1 The Ministerial Handbook ("the Handbook") regulates the privileges to which 
members of the Executive are entitled, by virtue of the offices that they 
occupy. 

8.2.1.2 A "member" is, for the purposes of the application of the provisions of the 



Handbook defined as a Minister, Deputy Minister, Premier, Member of the 
Executive Council (MEC) and a Presiding Officer/Deputy Presiding Officer in 
Parliament or in the Provincial Legislature, except in cases where specific 
categories of the above members are mentioned as national or provincial 
members. 



8.2.1.3 The President is therefore not a "member" of the Executive for the purposes 
of the general application of the provisions of the Handbook. 



USA. 



8.2. 



The Legal and Policy Framework Regulating the Installation and 



354 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




8.2.1 .4 Chapter 4 that deals with residences only applies to "members". 

8.2.1 .5 Annexure E to the Handbook consists of the Policy on Security Measures at 
the Private Residences of Public Office Bearers, which was approved by the 
Cabinet on 1 1 June 2003. 

8.2.1.6 This Policy provides that that the Minister of Public Works may approve a 



state contribution of a non-recoverable maximum amount of R100 000 in 
respect of security measures taken at the private residence of a public office 
bearer. If the cost exceeds R100 000, the difference shall be paid by the 
public office bearer. 



8.2.1.7 It should be noted in this regard that the Remuneration of Public Office 



Bearers Act, 1998 excludes the President specifically from the definition of 
"office bearer". This is also evident from the fact that the salary, allowances 
and benefits of the President are provided for separately in this Act. 



8.2.1 .8 It is furthermore clear from the provisions of Annexure E that the initiative for 



security measures has to be that of the Public Office Bearer, who has to be 
satisfied with the cost estimation and is responsible for contracting with 
service providers. The involvement of the DPW is limited to assisting with 
determining the scope and costs of the measures to be taken and providing a 
financial contribution of not more than R100 000. 



8.2.1 .9 Annexure E therefore clearly does not apply to the project referred to in this 
report. 



355 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




8.2.2. 
8.2.2.1 

8.2.2.2 
8.2.2.3 

8.2.2.4 
8.2.2.5 
8.2.2.6 
8.2.2.7 
8.2.2.8 



The Cabinet Policy: Security Measures at the Private Residences of the 
President, Deputy President and former Presidents and Deputy Presidents, 
approved on 20 August 2003 

This Cabinet Policy provides that at the request of the President or the 
Presidency , the SAPS together with the National Intelligence Agency (NIA) 
(now the State Security Agency) evaluate the security situation of private 
properties that are owned and regularly used by the President, and in 
exceptional circumstances, his immediate family. 

The evaluation is based on a threat analysis conducted by the NIA. 

Based on the evaluation the SAPS and the NIA have to formulate a proposal 
on appropriate security measures (staff and structures) that should be put in 
place by the State. These measures have to be submitted to the Inter- 
Departmental Security Coordinating Committee, for technical assessment. 

The DPW then has to prepare cost estimates of the proposed structural 
security measures and submit it to the SAPS. 

Thereafter, the SAPS have to advise the Minister of Police on the proposed 
safety measures, including the cost thereof. 

Whatever measures are accordingly approved by the Minister of Police shall 
be communicated to the President for his or her consent. 

The SAPS then has to submit the measures, as approved by the President to 
the Minister of Public Works for approval of the structural components. 

The security measures agreed to in the above process have to be 
implemented as follows: 



356 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




(a) 
(b) 

8.2.2.9 

8.2.3. 
8.2.3.1 

8.2.3.2 

8.2.3.3 
8.2.3.4 



SAPS personnel and related costs have to be provided and funded by the 
SAPS; 

structural additions and amendments have to be provided, maintained and 
funded by the DPW. 

This Policy further provides that the security situation at the private residence 
of the President shall from time to time be revisited by the SAPS based on 
the findings of a threat analysis done by the NIA. The SAPS has to report its 
findings to the Minister of Police. This may at any time lead to the upgrading, 
downgrading or termination of security measures. 

The National Key Points Act, 1 980 

Section 2 of this Act provides that if it appears to the Minister of Police at any 
time that any place is so important that its loss, damage, disruption or 
immobilization may prejudice the Republic, or whenever he/she considers it 
necessary or expedient for the safety of the Republic or in the public interest, 
he/she may declare that place a National Key Point. 

When in the opinion of the Minister it will contribute to the safeguarding of 
two or more National Key Points if certain steps in respect of their security 
are taken jointly by their owners, he may, in terms of section 2A(1), declare, 
those Key Points a National Key Points Complex. 

The owner of the affected place has to be provided with a written notice of 
the declaration. 

Section 3 provides further that on receipt of the notice, the owner , after 
consultation with the Minister of Police, has to take steps at his/her own 
expense and to the satisfaction of the Minister in respect of the security of the 
place. 



357 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH flfEICfl 



8.2.3.5 Should the owner fail to take such steps, the Minister may by written notice in 
terms of section 3(2) order him/her to take within a specified time in the 
notice and at his or own expense take such steps in respect of the security of 
the Key Point as may be specified in the notice. If the owner without 
reasonable cause refuses or fails to comply with the notice, it amounts to a 
criminal offence . 

8.2.3.6 If the owner refuses or fails to take the steps specified in the said notice 
within the period specified, the Minister may take or cause to be taken the 
steps and may recover the cost thereof to such extent that the Minister may 
determine. 

8.2.3.7 Section 3A affords the Minister of Police with the power to take over the 
duties of the owner to secure the place declared as a National Key Point. 
He/she may do so at any time and will then be acting on behalf of and with 
the consent of the owner to take the steps or cause it to be taken, which are 
or may become necessary to secure the National Key Point. The owner shall 
in such a case be liable for the cost of the steps taken to the extent 
determined by the Minister. 

8.2.3.8 A Special Account for the Safeguarding of National Key Points is established 
in terms of section 3B of this Act. It provides that money appropriated by 
Parliament is paid into the account, as well as money recovered from the 
owner of a National Key Point. 

8.2.3.9 The moneys in the account are to be utilised, inter alia, to render assistance 
to the owner of a National Key Point in respect of the steps that need to be 
taken to secure the place. 

8.2.3.10 The Minister of Police has to designate a person in the service of the State to 
be the accounting officer of the account. 



358 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



8.2.3.11 The account is to have its own bank account and has to be audited by the 
Auditor-General. 

8.2.4. The South African Defence Review 

8.2.4.1 In May 1996, Parliament approved the White Paper on National Defence for 
the Republic of South Africa that constituted the Defence Policy for the new 
democratic state. 

8.2.4.2 The White Paper provides for a Defence Review, the aim of which was to 
elaborate on the Defence Policy Framework. 

8.2.4.3 The South African Defence Review was issued in 1998. Chapter 7 of the 
Defence Review provides for the Non-Military tasks to be performed by the 
South African National Defence Force (SANDF). 

8.2.4.4 Paragraph 9 of this Chapter states that the SANDF provides VIP air transport 
for the President, the Deputy President, the Minister and Deputy Minister of 
Defence and, where capacity allows, for other Cabinet Ministers and 
Premiers. 

8.2.4.5 Paragraph 22 provides that: 

"The SAMHS (South African Military Health Service) also provides medical 
care to the President, the Deputy President, the Minister and Deputy Minister 
of Defence and, at the request of the Department of Foreign Affairs, foreign 
VIPs visiting South Africa." 

8.3. The Relevant Provisions Relating to the Protection of Information 
Pertaining to the Security Measures Implemented at the Private 
Residence of the President 

359 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



8.3.1. The Cabinet Policy: Security Measures at the Private Residences of the 
President, Deputy President and former Presidents and Deputy Presidents, 
approved on 20 August 2003 



8.3.1.1 The Cabinet Policy does not contain any reference to the protection of 
information that relate to the security measures implemented at the 
President's private residence. 



8.3.2. The National Key Points Act, 1980 



8.3.2.1 Section 1 0(2) of this Act provides in this regard that: 



"Any person who furnishes in any manner whatsoever any information 
relating to the security measures , applicable at or in respect of any National 
Key Point or in respect of any incident that occurred there, without being 
legally obliged or entitled to do so , or without the disclosure or publication of 
the said information being empowered by or on the authority of the Minister, 
except as may be strictly necessary for the performance of his functions in 
regard to his employment in connection with, or his ownership of, or as may 
be necessary to protect, the place concerned, shall be guilty of an offence 
and on conviction liable to a fine not exceeding R10 000 or to imprisonment 
for a period not exceeding three years or both such fine and such 
imprisonment, (emphasis added). 



8.3.3. The Protection of Information Act, 1982 



8.3.3.1 The relevant provision that applies to the information referred to in this report 
is section 4 of this Act. 



8.3.3.2 It provides that any person who discloses information that is in his or her 
possession or under his/her control or at his/her disposal on account of 



360 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



holding an office under the Government, that he/she knows or should 
reasonably know, the security or other interests of the Republic demands to 
be kept secret, to anyone other than: 



(a) someone lawfully entitled to it; or 



(b) someone to whom he/she has a duty to disclose it in the interests of the 
Republic shall be guilty of an offence. 

8.3.4. The Minimum Information Security Standards 

8.3.4.1 The Minimum Information Security Standards (MISS) is the National 
Information Security Policy, approved by the Cabinet on 4 December 1996. 

8.3.4.2 The Preface to this Policy states that it was compiled as an official 
government policy document on information security, which must be 
maintained by all institutions that handle sensitive or classified material. 

8.3.4.3 Chapter 1 of the Policy provides that government institutions should compile 
its own rules of procedure in respect of the protection of information, based 
on the minimum standard set by the Policy. In so doing, it is expected of all 
institutions to strive for reconciliation between the requirements of sound 
administration and effective security. 

8.3.4.4 The classification of official matters is referred to in Chapter 2. Paragraph 2 
of this Chapter provides that the head of an institution is responsible for the 
classification of a document. Paragraph 1 .2 of Chapter 4 states in this regard 
that: 



"The responsibility for the gradings and regradings of document 
classifications rests with the institution where the documents have their 



361 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




SOUTH flfEIOl 



origin. This function rests with the author or head of the institution or his (or 
her) delegate(s)." 



8.3.4.5 The head of an institution is defined by paragraph 21 of Chapter 2 as: 



"The person who is serving as the head of the institution, whether defined by 
law or otherwise, including the official acting in his place". 



8.3.4.6 The classification can, in terms of paragraph 3.1 , be as follows: 



(a) Restricted; 

(b) Confidential; 



(c) Secret; 



(d) Top Secret. 



8.3.4.7 The following note appears under paragraph 3.4 of Chapter 2 of the Policy: 



"Security measures are not intended and should not be applied to cover up 
maladministration, corruption, criminal actions, etc, or to protect 
individuals/officials involved in such cases." 



8.3.4.8 The definition of the classification of "Top Secret", which is relevant to the 
matters referred to in this report, is, in terms of paragraph 3.4.4. of Chapter 2 
of the Policy, as follows: 

"TOP SECRET is the classification given to information that can be used by 
malicious/opposing/hostile elements to neutralise the objectives and 
functions of institutions and/or state. " 

362 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




8.3.4.9 The test to be applied to determine whether information should be classified 
as TOP SECRET is whether the compromise thereof: 



(a) "can disrupt the effective execution of information or operational 
planning and/or plans; 

(b) can seriously damage operational relations between institutions; 

(c) can lead to the discontinuation of diplomatic relations between states; 
and 

(d) can result in the declaration of war." 



8.3.4.10 The following explanation of the classification is provided: 



"TOP SECRET is used when the compromise of information results in: 

The functions of a state and/or institution being brought to a halt by 
disciplinary measures, sanctions, boycotts or mass action; 
The severing of relations between states; and 
a declaration of war. " (emphasis added) 



8.3.4.1 1 "Compromise" is defined in paragraph 7 of Chapter 2 as: 



"The unauthorised disclosure/exposure or loss of sensitive or classified 
information, or exposure of sensitive operations, people or places, whether 
by design or through negligence." (emphasis added) 



363 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




8.4. 



The Legal and Policy Framework Regulating the Procurement of Goods 
and Services by the DPW 



8.4.1. Legal framework 

8.4.1.1 Section 217 of the Constitution is the basis upon which all procurement 



practices within the public sector are developed. The Constitution demands 
that when an organ of state contracts for goods and services it must do so in 
accordance with a system which is fair, equitable, transparent competitive 
and cost effective. 



8.4.1.2 In terms of section 195, the public administration must be governed by the 
democratic values and principles enshrined in the Constitution, including the 
promotion of the efficient, economic and effective use of public resources. 

8.4.1.3 The key instrument regulating procurement is the Public Finance 
Management Act, 1999 (PFMA) the purpose of which is set out in the 
preamble to the Act, that reads as follows: 



"To regulate financial management in the national government and provincial 
governments; to ensure that all revenue, expenditure, assets and liabilities of 
those governments are managed efficiently and effectively; to provide for the 
responsibilities of persons entrusted with financial management in those 
governments; and to provide for matters connected therewith. " 



8.4.1.4 In terms of section 76(4)(c) of the PFMA, the National Treasury may make 



regulations or issue instructions applicable to all institutions to which the 
PFMA applies concerning, inter alia, the determination of a framework for an 
appropriate procurement and provisioning system which is in keeping with 
the dictates of Section 217(1) of the Constitution. 



364 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEIOl 



8.4.1.5 The DPW business processes require a client Department to confirm 
availability of funding prior to the procurement process being embarked upon. 
The DPW, upon receiving a request to satisfy a need, embarks upon a 
process of estimating the costs to the client Department. This document 
allows the client Department to estimate the costs it would possibly incur and 
allows the Department to assess its budget and to plan for future budgets. 



8.4.1.6 The Supply Chain Management (SCM) framework is set out in Regulation 
16A of the Treasury Regulations, which are applicable to all departments in 
national and provincial governments. 



8.4.1.7 The Treasury Regulations set out the areas that form the SCM framework 
and this is to be found in Regulation 16A.3.2 which reads as follows: 



"A supply chain management system referred to in paragraph 16A.3. 1 must - 

(a) be fair, equitable, transparent, competitive and cost effective; 

(b) be consistent with the Preferential Procurement Policy Framework Act, 
2000 (Act No. 5 of 2000); 

(c) be consistent with the Broad Based Black Economic Empowerment Act, 
2003 (Act No. 53 of 2003); and 

(d) provide for at least the following: - 

(i) demand management; 

(ii) acquisition management; 
(Hi) logistics management; 

(iv) disposal management; 

(v) risk management; and 

(vi) regular assessment of supply chain performance." 



8.4.1.8 Regulation 11(a) of the Regulations issued in terms of the Preferential 
Procurement Policy Framework Act, 2000, provides that an organ of state 
must, prior to making an invitation for tenders properly plan for and as far as 



365 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH flfEIOl 



possible, accurately estimate the costs of the provision of services or goods 
for which an invitation for tenders is to be made. 



8.4.2. Supply Chain Management Guidelines 



8.4.2.1 In February 2004, the National Treasury issued a document entitled "Supply 
Chain Management: A Guide for Accounting Officers/Authorities" (SCM 
Guide). The purpose of the SCM Guide was to give guidance to accounting 
officers in fulfilling their roles within the SCM framework. 



8.4.2.2 Paragraph 3 of the SCM Guide sets out guidelines in regard to demand 
management and reads as follows: 

"Demand management 

3. 1 Introduction 

3.1.1 Demand management is the first phase of SCM. The objective is to 
ensure that the resources required to fulfil the needs identified in the 
strategic plan of the institution are delivered at the correct time, price 
and place and that the quantity and quality will satisfy those needs. 
As part of this element of SCM, a total needs assessment should be 
undertaken. This analysis should be included as part of the strategic 
planning process of the institution and hence will incorporate the 
future needs. 

3. 1.2 It is vital for managers to understand and utilise sound techniques to 
assist them in their planning, implementation and control activities. 
As part of the strategic plan of the institution, resources 
required for the fulfilment of its obligations should be clearly 
analysed . This includes a detailed analysis of the goods, works and 
services required, such as how much can be accomplished, how 
quickly and with what materials, equipment, etc." (emphasis added) 



366 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




8.4.2.3 This Guide is applicable to all accounting officers and contains the following 



principles: 

(a) The identification of a need is the initiating trigger to a procurement 
process. 

(b) The fulfilment of the need should form part of the strategic objectives of 
the department and a needs analysis should therefore be part of the 
strategic planning process. 

(c) Sound techniques should be utilised in conducting the needs analysis. 

(d) The need should be linked to the budget. 



8.4.2.4 Paragraph 1 .3.2.2 of the SCM Guide states that Demand Management is the 



beginning of the supply chain where: 

(a) a needs assessment is done to ensure that goods or services are 
acquired in order to deliver the agreed service; 

(b) specifications are precisely determined; 

(c) requirements are linked to the budget; and 

(d) the supplying industry has been analysed. 



8.4.2.5 Planning therefore plays an integral part in supply chain management. 

8.4.3. The Government Immovable Asset Management Act, 2007 (GIAMA) 

8.4.3.1 The purpose of this Act is to provide a framework for the management of 



immovable assets held by a national or provincial department and to provide 



367 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



minimum standards in respect of immovable asset management. Section 5 of 
the Act sets out the principles of asset management and reads as follows: 

"(1) The following are principles of immovable asset management: 

(a) an immovable asset must be used efficiently and becomes surplus to a 
user if it does not support its service delivery objectives at an efficient 
level and if it cannot be upgraded to that level; 

(b) to minimise the demand for immovable assets, alternative service 
delivery methods that do not require immovable assets must be 
identified and considered; 

(c) in relation to an acquisition, it must be considered whether— 

(i) a non-immovable asset solution is viable; 

(ii) an immovable asset currently used by the state is adequate to 
meet a change in its service delivery objectives; and 

(Hi) the cost of the immovable asset as well as operational and 
maintenance cost throughout its life cycle justifies its acquisition in 
relation to the cost of the service; 

(d) immovable assets that are currently used must be kept operational to 
function in a manner that supports efficient service delivery; 

(e) When an immovable asset is acquired or disposed of best value for 
money must be realised. . ." (emphasis added) 



8.4.3.2 The effect of GIAMA is, inter alia, to enforce optimal use of immovable 
property. GIAMA, through section 21, creates a criminal offence should an 
accounting officer wilfully or negligently contravene or fail to comply with any 
provision of this Act. 



8.4.3.3 



This Act further provides that the DPW must annually prepare a custodian 
asset management plan (C-AMP). A comprehensive C-AMP will include an 

368 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



acquisition plan, refurbishment plan, maintenance & repairs, and disposal 
plan. In the interim, the needs for built environment, professional services, 
construction, building and contracting services, land, buildings and facilities 
will have to be estimated based on the annual budget and the business plan 
of the units involved in the acquisition of construction related services. 



8.4.4. The Requirements in Respect of the DPW Budget 

8.4.4.1 The DPW business processes require of a client department, such as the 
SAPS and the DOD, to confirm availability of funding prior to the procurement 
process being embarked upon. Although the DPW is involved in the actual 
acquisition and procurement of property and goods and services relating 
thereto, the costs are to be borne by the client department. 

8.4.4.2 The DPW, upon receiving a request to satisfy a need, embarks upon a 
process of estimating the costs to the client department. This allows the client 
department to assess its budget and to plan for the budgeting of the 
expected expenditure. 

8.4.4.3 As stated earlier, the National Treasury guidelines expect a need to be linked 
to a budget and strategic objectives. Each department is expected to have a 
strategic plan in place that identifies the aims of the department and provides 
a budget towards achieving the said aims. 

8.4.4.4 Regulation 5.1 of the Treasury Regulations makes it mandatory for the 
accounting officer of an institution to prepare a strategic plan for the 
forthcoming Medium Term Expenditure Framework (MTEF) cycle. 

8.4.4.5 In terms of Regulation 5.2.2 the strategic plan must, inter alia, include details 
of proposed acquisitions of fixed or movable capital assets, planned capital 
investments and rehabilitation and maintenance of physical assets. 



369 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEIOl 



8.4.4.6 The PFMA, together with the Treasury Regulations and guidelines, ensure 
that proper planning is in place, a need is identified, analysed, and included 
in the strategic planning and therefore budgeted for. 

8.4.4.7 The Medium Term Expenditure Frame Work (MTEF) issued by the National 
Treasury in 2007, which covers the period under review in this Report, 
emphasises this point and the following is contained in the document - 

"The link between strategic planning, budgeting and spending plans is 
important in compiling a credible budget, as inadequate planning could lead 
to budgets which do not give effect to strategic priorities". 



8.4.4.8 Section 38(2) of the PFMA reinforces this principle of proper planning. This 
section reads as follows: 



"An accounting officer may not commit a department, trading entity or 
constitutional institution to any liability for which money has not been 
appropriated." 



8.4.4.9 Expenditure must be in accordance with the vote of the department and the 
main divisions within the vote. This requirement is encapsulated in section 39 
of the PFMA. Read with section 38(2), the principle of proper planning is 
once again highlighted. 



8.4.4.10 The PFMA, however, recognises situations where a need is not linked to a 
budget. In these instances four options are available to a department to fund 
such needs. 



8.4.4.11 The first option deals with a situation where no funding has been 
appropriated, but due to an emergency, funds are required for the purposes 
of procurement. 



370 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




8.4.4.12 Section 16 of the PFMA allows the Minister of Finance to authorise the use of 
funds from the National Revenue Fund to defray expenditure provided that: 



(a) the expenditure is of an exceptional nature; 

(b) expenditure is not currently provided for; and 

(c) the expenditure cannot be postponed to a future appropriation cycle 
without serious prejudice to the public interest. 



8.4.4.13 The second option is in the form of section 43 of the PFMA which allows an 



accounting officer to utilise a saving in an amount appropriated under a main 
division within a vote towards the defrayment of excess expenditure under 
another main division within the same vote. This virement of funds is, 
however, limited to 8% of the amount appropriated under that main division 
and a report concerning the utilisation of the savings must be presented to 
the Executive Authority (Minister) and the relevant treasury. 



8.4.4.14 The third option open to departments is to request further funds from National 
Treasury. This is, however, limited in its application and would only be 
applicable to situations where: 



8.4.4.15 The fourth option is to re-prioritise expenditure within a main division of a 
vote to accommodate the need. 

8.4.5. The Prescripts Relating to Urgency 



(a) a department inherited new functions; or 



(b) where due to policy decisions new needs arise. 



371 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC f>e«oi 

SOUTH flfl 



8.4.5.1 The PFMA and Treasury Regulations require that the default position in 
regard to procurement is that a competitive bid procedure be embarked 
upon. 

8.4.5.2 However, the legislation recognises that in certain cases it is impractical to 
invite competitive bids and as such it is permissible to procure goods or 
services by other means, provided that reasons for the deviation are 
recorded and approved by the accounting officer (Regulation 16A6.4). 

8.4.5.3 The National Treasury issued Practice Note 8 of 2007/08 wherein, inter alia, 
urgent, emergency or sole supplier cases were further regulated. Paragraph 
3.4.3 thereof provides as follows: 

"Should it be impractical to invite competitive bids for specific procurement 
,e.g. in urgent or emergency cases or in case of a sole supplier, the 
accounting officer / authority may procure the required goods or services by 
other means, such as price quotations or negotiations in accordance with 
Treasury Regulation 16A6.4. The reasons for deviating from inviting 
competitive bids should be recorded and approved by the accounting officer/ 
authority or his/her delegate. Accounting officers/authorities are required to 
report within ten (10) working days to the relevant treasury and the Auditor- 
General all cases where goods and services above the value of R1 million 
(VAT inclusive) were procured in terms of Treasury Regulation 16A6.4. The 
report must include the description of the goods or services, the name/s of 
the supplier/s, the amount/s involved and the reasons for dispensing with the 
prescribed competitive bidding process."(emphasis added) 

8.4.5.4 The SCM Guide at paragraph 4.7.5.1 notes that in urgent and emergency 
cases, an institution may dispense with the competitive bidding process, but 
must act in a manner that is in the best interest of the State. 



372 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




8.4.5.5 The SCM Guide defines an "emergency case" as - 



"A case where immediate action is necessary in order to avoid a dangerous 
or risky situation or misery." (emphasis added) 



8.4.5.6 An "urgent case" is defined as "a case where early delivery is of critical 



importance and the invitation of competitive bids is either impossible or 
impractical". This definition is, however, subject to the qualification that "A 
lack of proper planning should not be constituted as an urgent case. " 
(emphasis added) 



8.4.5.7 The following principles can be gleaned from this definition of urgency: 



(a) The early delivery is the key requirement which would decide the 
success or failure of the project; 

(b) The time period available for the acquisition makes it impractical or 
impossible to pursue a competitive bid process; 

(c) The urgency was not foreseeable or the result of dilatory conduct; and 

(d) For a situation to be classified as urgent all three the above 
requirements must be met. 



8.4.6. The Responsibilities of Accounting Officers in Respect of SCM 

8.4.6.1 Section 38(1)(a)(iii) of the PFMA prescribes that the accounting officer of a 



department must ensure and maintain an appropriate procurement and 
provisioning system which is fair, equitable, transparent, competitive and cost 
effective. 



373 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH flfEICfl 



8.4.6.2 In terms of section 38(1 )(c)(ii) of the PFMA, an accounting officer must take 
effective and appropriate steps to prevent unauthorised, irregular and 
fruitless and wasteful expenditure. It is expected of the accounting officer to 
take effective and appropriate disciplinary steps against any official in the 
service of the department who makes or permits an unauthorised, irregular 
and fruitless and wasteful expenditure. Irregular, unauthorised or fruitless and 
wasteful expenditure is regarded as an act of financial misconduct in terms of 
section 38(1 )(h)(iii) of the PFMA. 

8.4.6.3 An accounting officer is, in terms of section 86(1) of the PFMA guilty of an 
offence and liable on conviction to a fine or to imprisonment for a period not 
exceeding five years, if he or she wilfully or in a grossly negligent way fails to 
comply with a provision of, inter alia, section 38, referred to above. 

8.4.7. Assignment of Powers and Duties by Accounting Officers 

8.4.7.1 In terms of section 44 of the PFMA, the accounting officer for a department 
may in writing delegate any of the powers entrusted or delegated to him/her 
to an official in that department. 

8.4.7.2 However, in terms of section 44(2) (d) of the PFMA, a delegation to an official 
does not divest the accounting officer of the responsibility concerning the 
exercise of the delegated power or the performance of the assigned duty. 

8.4.8. The Responsibilities of Other Officials 

8.4.8.1 Section 45 of the PFMA provides that an official in a department must ensure 
that the system of financial management and internal control established for 
that department is carried out within the area of responsibility of that official. 

8.4.8.2 Officials are also responsible for the effective, efficient, economical and 
transparent use of financial and other resources within that official's area of 



374 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




8.4.9. 
8.4.9.1 

8.4.10. 
8.4.10.1 

8.4.10.2 



8.4.10.3 



responsibility. They must take effective and appropriate steps to prevent, 
within his/her area of responsibility, any unauthorised, irregular and fruitless 
and wasteful expenditure. 

The Powers of the National Treasury 

Section 6(2) of the PFMA provides that the National Treasury must intervene 
by taking appropriate steps to address the serious material breach of the Act 
by a department and may do anything further that is necessary to fulfil its 
responsibilities effectively. 

The SCM Policy of the DPW 

The relevant SCM Policy (the Policy) of the DPW was approved by the 
Director-General on 29 April 2008 and came into operation on 1 May 2008. 

Paragraph 14 of the Policy provides that its purpose is to formalize the 
DPW's SCM Policy within the context of the Treasury Regulations and that it 
consists of the following three main components: 

(a) Directives, providing specific direction on supply chain management 
and key decision points; 

(b) Delegations, assigning specific responsibilities to DPW role players, in 
terms of section 38 of the PFMA; and 

(c) Business processes, aligning the DPW's day-to-day procedures with the 
overall requirements of the policy, directives and delegations. 

The primary objective of the Policy, in terms of its paragraph 1 5, is to create 
an environment that enables the DPW to manage the supply of goods, 
services and works in a manner that is fair, equitable, transparent, 



375 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



competitive and cost effective. One of its focus areas in this regard is 
demand management "to link SCM practices to the strategic planning and 
budgeting processes and to improve strategies and planning for acquisition, 
maintenance and disposal." Another is "introducing the concept of value for 
money to balance socio-economic and black economic empowerment 
objectives with the cost of the product and services, through appropriate 
scoring models. " 



8.4.10.4 Paragraph 18 provides for special measures to accommodate empowerment 
initiatives as far as the construction industry is concerned. Potentially 
emerging contractors will, in terms of paragraph 25 be invited to tender for 
work in a category that is one higher than that in which they are graded by 
the CIDB, provided that they are part of the DPW's contractor development 
programmes. 



8.4.10.5 The purpose of demand management is described in paragraph 37 of the 
Policy as: 



"...to ensure that resources to fulfill the needs identified in the strategic plan 
are delivered at the correct price, time, place, quantity and quality to satisfy 
the needs." 



8.4.1 0.6 Paragraph 38 states that following in this regard: 

"Proper demand management practices will allow the SCM unit to prepare 
itself and the supplier base to meet the need for services by DPW. 
Introducing demand management will require: 

a. that a needs assessment is conducted prior to the beginning of the 
MTEF period; 

b. specifications are precisely determined; and 

c. the supplier industry has been analysed. " 



376 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



8.4.10.7 The needs assessment process must, according to paragraph 41, "be 
embedded in the business planning and budgeting processes as part of the 
annual budgeting and business plan cycle." As far as immovable assets are 
concerned, it is provided that: 

"In terms of the Government Immovable Asset Management Act, (GIAMA), 
DPW must annually prepare a custodian asset management plan. " 



8.4.10.8 The DPW must, in terms of paragraph 47 of the Policy, have a register of 
suppliers. This register is regarded as a key instrument to ensure that the 
DPW has sufficient appropriately qualified suppliers to provide the 
department with goods or to perform required services. The stated objectives 
of the Supplier Register are, inter alia, to 



"assess the profile of suppliers available in the market; 



maintain an approved list of suppliers to aid the quotation method of 
acquisition; 

reduce the administrative and bidding/quotation costs for both the 
Department and the supplier. " 

8.4.10.9 The accounting officer of the DPW must, in terms of paragraph 60 of the 
Policy, ensure that appropriate delegations are in place for acquisitions in line 
with the Treasury Regulations and prescripts. 



8.4.10.10 The Chief Director: Supply Chain Management of the DPW issued a 
"DIRECTIVE: ACQUISITION AND DISPOSAL MANAGEMENT" in terms of 
the Policy, on 19 February 2010. The following acquisition procedures to 
acquire goods and services provided for under paragraph 18 of the Directive 
are of significance to the project referred to in this report: 



377 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH flffclOl 



idard application for goods and servii 
lND for engineering and construction 




Open 
Procedure 



All bids above the value threshold must be solicited 
through the Open Procedure. 

Vendors may submit bid offers in response to an 
invitation by the Department to do so. 

The Open Procedure must be used for ad hoc contracts 
above the value threshold, to award term contracts and 
to establish a panel of preferred service providers. 



Above R500 000 



The Negotiated Procedure is the least desirable of all 
acquisition procedures and Bid Adjudication 
Committees may approve this procedure as a last 
resort 



Bids or quotations are solicited from a single vendor. 
The negotiated procedure may be used in the following 
circumstances only: 



Negotiated 
Procedure 



If the goods or services must be acquired as a matter of 
urgency or emergency and a competitive bidding 
process or other acquisition procedures are impractical, 
provided that the circumstances giving rise to the 
urgency were neither foreseeable by the users nor the 
result of dilatory conduct on their part; 

Owing to a catastrophic event there is an urgent need 

for the goods, works or services, making it impractical 

to use other methods of procurement because of the 

time involved in using those methods; 

If the market was tested and no responsive bids were 

obtained; 

If there is no competition and only one vendor exists. 



Any value 



The reason for using the negotiated procedure must be 
motivated in the sourcing strategy for approval by the 
BAC. 



378 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




SOUTH flfBKfl 



PROCEDURE 


STANDARD APPLICATION FOR GOODS AND SERVICES 
AND FOR ENGINEERING AND CONSTRUCTION 




Nominated 
Procedure 


The Nominated Procedure is not a desirable 
acquisition procedure and the relevant BAC may 
approve this procedure as a last resort 

At least three vendors are nominated from the supplier 
register or panel of vendors to provide a written or 
verbal quote. 

This procedure must be motivated to the BAC. 

The Nominated Procedure may be used: 

• In emergency cases; or 

• Where there are time constraints in carrying out the 
service; 

• For the supplying of the goods or where the services 
required are of a specialized nature 





Figure 16: Acquisition Procedures in terms of DPW policy 



8.4.10.11 Paragraph 23 of the Directive relates to Ad hoc contracts and provides as 
follows: 



"Ad hoc contracts will be utilized as follows: 

a. Goods or services that are required infrequently, or on a once off basis, 
or where there are no term contractors or panels in place for the 
required goods or services, will be acquired on an ad hoc basis, either 
through the open bid procedure or the quotation procedure; 

b. Vendors will enter into a contract with the Department to render 
services on a once off basis; 

c. Ad hoc contracts will be entered into for a contract that has a definite 
scope of work, timeframe and price (as submitted by the vendor)." 



8.4.10.12 Variation orders are provided for in paragraphs 29 to 33 of the Directive. 

According to these provisions contract variations refer to any change in the 
scope of work, specifications or time which was not provided for in the 
original contract. Variation orders must be recorded in writing. Project 

379 



Secure In Comfort A Report of the March 2014 

Public Protector 

PUBLIC f>e«oi 

SOUTH flfl 



managers are required to confirm the availability of funds before obtaining 
approval of any variation order. 

8.4.10.13 "Emergency and/or urgent acquisitions" are provided for as follows in 
paragraphs 44 to 50 of the Directive: 

"44. A lack of proper planning does not constitute an urgent or emergency 
case. 

45. Under the following circumstances, the Department may dispense with 
the invitation of bids and may obtain the required goods, works or 
services by means of quotations or in any other manner that is 
determined to be in the best interest of the State: 

a. urgent circumstances; or 

b. emergency circumstances. 

46. Goods or services may be acquired in an urgent or emergency situation 
using the following standard acquisition procedures: 

a. Nominated Procedure; 

b. Quotation Procedure; 

c. Negotiated Procedure. 

47. All urgent and emergency acquisitions for goods and services will be 
approved verbally by the relevant Regional Manager and in the case of 
Head Office the Chief Director: SCM. 

48. For works related acquisitions the Project Manager will record the 
reasons and justification for the urgent and/or emergency related 
acquisitions. 



380 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




49. On completion of the emergency or urgent acquisition, a fully motivated 
report must immediately be forwarded to the BAC for merit assessment 
and ratification. 

50. Negligence on the part of officials in obtaining the necessary approvals 
will be dealt with in terms of the Department's internal disciplinary 
proceedings. " 



8.4.10.14 The functioning of the BAC is provided for in paragraph 216 of the Directive 
in terms of which it conducts, inter alia, the following specific tasks in the 
acquisition process: 



(a) Approval of sourcing strategy. In this regard it is expected of the BAC to 
consider the strategy that will ensure that the most favourable 
acquisition process is followed; 

(b) Assessment and award of bids recommended by the BEC; 

(c) Consideration of variation orders; 

(d) Approval of urgent and emergency acquisitions; and 

(e) Awarding of contacts; 

(f) Approval of variation orders. Paragraph 223 provides in this respect 



"The BAC must ensure that the variation order does not exceed the 
scope of work to the extent where the variation order could be 
perceived as a new contract, or which could have the potential to have 
prejudiced other vendors by not being included in the original scope of 
work. " 



that: 



381 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flffclOl 



8.4.10.15 In terms of paragraph 190 of the Directive, the BAC operates under 
delegations as approved by the Accounting Officer of the DPW. 



8.4.10.16 Annexure C to the Directive deals specifically with the acquisition of 
professional service providers in the built environment. It provides for only 
two acquisition procedures, namely quotations in respect of projects with a 
percentage or time based fee value not exceeding R500 000, and Open 
Tender. 



8.4.10.17 It must be noted that in terms of the DPW's SCM Circular of 2009/10, issued 
on 25 May 2009, a Special National Bid Adjudication Committee (SNBAC) 
was appointed for acquisitions exceeding R20 million. 



8.4.11. The Role of the DPW Regional Offices in the SCM process in Respect of the 
Procurement of Goods and Services 



8.4.11.1 It was established through the course of the investigation that under normal 
circumstances the client department submits a needs analysis and funding 
confirmation to the Key Accounts Management (KAM) division located at the 
Head Office of the DPW. 

8.4.11.2 The KAM division then fully assesses the client's need, including the nature 
and extent of the goods and services required. 

8.4.1 1 .3 When satisfied that the relevant requirements are met the KAM division then 
issues a Procurement Instruction (PI) to the DPW Regional Office in whose 
area the goods and services are to be procured. 

8.4.11.4 The PI requires of the Regional Office to follow the SCM principles, 
procedures and processes in the procurement of the goods and services to 
the satisfaction of the client department, in terms of the approved norms and 
cost. 



382 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



8.4.11.5 If the cost exceeds R20 million a recommendation relating to an appropriate 
procurement strategy must be submitted to the (Special National Bid 
Adjudication Committee (SNBAC) for approval. 

8.4.11.6 Once approved by the SNBAC, the procurement strategy must be 
implemented by the Regional Office. 

8.4.11.7 The Regional Office then becomes responsible for the initiation of the 
procurement process in compliance with the approved procurement strategy. 

8.4.11.8 The Regional Office is required to provide regular feedback to the KAM 
division of the progress made throughout the procurement process. 

8.4.12. The Delegations to the Project Manager and Other Officials of the DPW 

8.4.12.1 On 3 October 2005, the Director-General of the DPW issued delegations to 
officials of the Department, in terms of the provisions of the PFMA, in a 
document entitled "DELEGATION OF POWERS, DUTIES AND FUNCTIONS 
WITH REGARD TO THE MANAGEMENT OF SITE CLEARANCE- 
,BUILDING-,LEASING-OR ENGINEERING PROJECTS, VESTED IN THE 
DIRECTOR-GENERAL BY VIRTUE OF HIS ROLE AS D I ECTOR - 
GENERAL/ACCOUNTING OFFICER OF THE DEPARTMENT OF PUBLIC 
WORKS." 

8.4.12.2 Mr Rindel indicated during the investigation that the delegations referred to in 
this document still applied at the time of its implementation. 

8.4.12.3 The Introduction to the delegation document states that delegations apply to 
posts and therefore to any person formally appointed to that post. It is further 
required of the officials affected by the delegations to be conversant with the 
relevant legal and policy frameworks that apply to their functions. The 



383 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



document further provides that the delegations empowered managers to take 
decisions for which they would be held accountable and that: 



"Although duties have been delegated to the official, the Accounting Officer is 
still held accountable together with the person who has been delegated." 



8.4.1 2.4 A Project Manager is defined by the delegation document as: 



"An official appointed in terms of these delegations to manage a site 
clearance-, building, leasing-or engineering project on behalf of the Director- 
General and shall deem to include all professional staff members of the Chief 
Directorate: Professional Services tasked with projects, related to the built 
environment, aimed at compiling policy documents, norms, standards, pro- 
forma documentation, manuals and all other related assignments, including 
the management of Consultant appointments to achieve the desired end 
products(s)." (emphasis added) 



8.4.12.5 In terms of paragraph 1.6 of the delegation document, the approval to 
improve privately owned land can be granted at the level of a Deputy 
Director-General. However, it has to be based on an accepted feasibility 
study and recommendation by the relevant Chief Director: Key Account 
Management and the Chief Director: Professional Services. 



8.4.12.6 The acceptance of a Procurement Instruction was delegated to a number of 
officials at Director Level on condition that the Procurement Instruction must 
be complete in all respects, including funds allocation, preliminary 
programme, cash flow/budget particulars and registration on the WCS. 

8.4.12.7 Paragraph 4.1 delegated the approval and amendment of sketch plans in the 
case of a building project to the Directors: Projects and Maintenance, 
Professional Services, Project Management Support, Special Projects and 
the Transaction Manager. The approval was subject to the recommendation 



384 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



of the Project Manager and the following general notes and conditions 
applied: 



"1. Sketch plans and/or preliminary design reports of all projects consisting 
of: 

(a) new work; 

(b) upgrading or alterations to existing buildings/installations/ 
engineering infrastructure or 

(c) repair and renovation/maintenance in excess of an estimated 
value larger than R5 000 000 

must be subjected to the scrutiny and comment of the Scrutiny Com at 
Regional Level for projects with an estimated value of less than R10M 
and to the Scrutiny Com at Head Office level for projects with an 
estimated value of more than R10M. 



2. If serious or far reaching comments were passed by the Scrutiny Com, 
and the Professional Team was required to re-submit an 
amended/revised design, such amended/revised design must first be 
completed before final approval stages, referred to below, can be 
considered. PM (Project Manager) to consider a further round at the 
Scrutiny Com. 

3. The final approval power (delegated power as above) must only be 
executed subject to the comments by the Scrutiny Com, design 
documents being in compliance with the prescribed space norms and 
cost limits, funds being available and the Client Department having 
expressed its satisfaction and granted written approval on the 
drawings/report. 



385 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




4. Approvals given against advise (sic) of Professional Services/Scrutiny 
Committee will be at the risk of the approving authority in terms of this 
delegated power. 

5. The amendments must not be of such extensive nature that it 
constitutes a new project or new design and may not exceed 5% of the 
project estimate. PM to supply full motivation as to the necessity for the 
amendment. Amendments may not violate space norms and cost limit 
set for the project. If the 5% margin stated herein is exceeded, the 
comments of the Scrutiny Com are to be obtained again. " 



8.4.12.8 The Scrutiny Committee referred to above is defined by the delegation 



document as: 

"A Committee at Head Office or Regional Office level, comprising of one 
member of each of the built environment professional sections in the Unit: 
Professional Services, chaired by the member of Architectural Services in the 
case of a building project or a member of the relevant Engineering profession 
in the case of an engineering project. The D/TP Services (Director: Town 
Planning Services) to form part of the said Committee to verify if the 
proposed development is in line with Site Development Plans and/or 
development conditions as negotiated during site creation. " 



8.5.1. Section 237 of the Constitution which provides that "all constitutional 



obligations must be performed diligently and without delay" is considered 
relevant in guiding the use of limited state resources. Principles of Public 
Administration referred to in section 195 was also considered relevant. 
Section 195(1 )(b) provides for "efficient, economic and effective use of 
resources to be promoted. " . 



8.5. 



Other rules and policies 



386 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




8.5.2. 
9. 

9.1. 

9.1.1. 

9.1.1.1 

9.1.1.2 

9.1.1.3 



As one of the principles of public administration, the Batho Pele White Paper 
Transforming the Public Service Delivery was also considered. Key in this 
policy paper is the principle of putting, first in the context of transforming the 
Public Service, towards one that is people centred. 

ANALYSIS AND CONCLUSION 

The Legal Authority For The State To Provide Adequate Security At The 
Private Residence Of The President And The Compliance With The 
Prescribed Processes 

The Cabinet Policy: Security Measures at the Private residences of the 
President, Deputy President and former Presidents and Deputy Presidents 

The Ministerial Handbook does not apply to the provisioning of security 
measures by the state in respect of the private residence of the President. 

The President and Deputy President have a special security regime created 
by the Cabinet Policy: Security Measures at the Private residences of the 
President, Deputy President and former Presidents and Deputy Presidents, 
dated 20 August 2003. 

The key requirements prescribed by the Cabinet Policy which have to be 
complied with before the DPW commences with the installation of security 
measures at a President's private residence are set out in the table below: 



387 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH flfEICfl 




• A REQUEST BY THE PRESIDENT OR PRESIDENCY 



• JOINT SECURITY EVALUATION OF PRIVATE RESIDENCE BY SAPS 
ANDNIA 



• JOINT PROPOSAL ON SECURITY MEASURES SUBMITTED TO 
INTER-DEPARTMENTAL SECURITY COORDINATING COMMITTEE 
FOR TECHNICAL ASSESSMENT 



DPW PREPARE COST ESTIMATES OF PROPOSED STRUCTURAL 
SECURITY MEASURES AND SUBMIT TO SAPS 



• SAPS ADVISE MINISTER OF POLICE ON PROPOSED SECURITY 
MEASURES AND THE COST 



MINISTER OF POLICE COMMUNICATES APPROVED MEASURES 
TO THE PRESIDENT FOR HIS/HER CONSENT 



• SAPS SUBMITS MEASURES AS APPROVED BY THE PRESIDENT TO 
THE MINISTER OF PUBLIC WORKS FOR APPROVAL OF 
STRUCTURAL COMPONENTS 



• SECURITY MEASURES AGREED TO IMPLEMENTED 



Figure 1 7: Key Requirements as prescribed by the Cabinet Policy 



9.1.1.4 It should be noted that the Cabinet Policy provides that the security 
measures agreed to have to be implemented as follows: 

388 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



(a) SAPS personnel and related costs have to be provided and funded by 
the SAPS; 

(b) Structural additions and amendments have to be provided, maintained 
and funded by the DPW. 

9.1.1.5 None of these requirements of the Cabinet Policy were complied with in 
respect of the Nkandla Project, but for the two security evaluations that were 
conducted by the SAPS. However, there was no indication in the evidence of 
Brigadier Adendorff that the evaluations were conducted jointly with NIA 
(SSA) or that it was submitted to the Inter Departmental Security 
Coordinating Committee for technical assessment. 

9.1.1.6 Brigadier Adendorff stated that she was not aware of the existence of the 
Policy, and therefore the Minister of Police was never advised accordingly. 
Mr Rindel was also not aware that the Nkandla Project was based on the 
Policy. 

9.1.1.7 From the investigation it was evident that the SAPS officials involved just 
accepted that they had to present security evaluations to the DPW and be 
involved in the Nkandla project, without having a clear understanding of the 
relevant and applicable regulatory prescripts and requirements. They took no 
interest in the extent and outrageous escalation of the cost of the Nkandla 
Project, as they regarded it as DPW's problem despite the fact that large 
parts thereof related to their areas of responsibility, as contemplated by 
section 45 of the PFMA. 

9.1.1.8 The Minister of Police probably did not inform the President and requested 
his consent, as he was required to have done in terms of the Policy, because 
he was not advised accordingly by the SAPS. 



389 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH flfEICfl 



9.1.1.9 The Policy further provided that the security measures that relate to the 
personnel of the SAPS had to be funded by it. However, in this case all the 
costs were carried by the DPW. 



9.1 .1.10 I could find no indication that the DPW's accounting officer or the officials to 
whom he delegated responsibility for the implementation of the Nkandla 
Project ever enquired into the legal and policy framework in respect of the 
provision of security measures at the President's private residence. The 
Policy was already adopted by the Cabinet in 2003, i.e. 6 years before Mr 
Zuma became the President, and therefore clearly applied in respect of the 
security measures that were installed at the private residences of former 
Presidents Mandela and Mbeki. It is therefore highly unlikely that senior 
officials involved in those projects were not aware of it. 



9.1.1.11 Some of the officials involved in the Nkandla Project were mistakenly under 
the impression that the provisions of the Ministerial Handbook applied in this 
case. 



9.1 .1 .12 The failure by the DPW and the SAPS to ensure compliance with the Policy 
was probably also the result of the absence of a DPW policy framework 
regulating the installation of security measures at the private residences of 
the President, Deputy President and former Presidents and Deputy 
Presidents. 



9.1 .1.13 The result of the failure on the part of the DPW and the SAPS to comply with 
the provisions of the Policy was that neither the Minister of Police nor the 
President was accordingly advised of the proposed measures and the cost 
thereof. It further resulted in the DPW funding the total bill in the absence of 
an authorizing instrument, which was irregular. 



9.1.1.14 The non-compliance of the SAPS and DPW with the Cabinet Policy was 
improper and constitutes maladministration. 



390 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




9.1 .2. The National Key Points Act 

9.1.2.1 The President's private residence was declared a National Key Point by the 



Minister of Police, in terms of section 2(1) the National Key Points Act, 1980, 
on 8 April 2010. In the Declaration Certificate the Minister of Police directed 
the President to pay for all security upgrades at his homestead, which now 
constitutes a National Key Point. 



9.1 .2.2 The Minister of Police personally signed the Declaration Certificate. I 
therefore have to accept that he was aware of the provisions of the National 
Key Points Act at the time. 

9.1 .2.3 The President's private residence was only declared a National Key Point 1 1 



months after he was appointed. By that time the Nkandla Project was already 
underway. It was not explained during the investigation why this was not 
done when the project commenced in May 2009 and was regarded as 
urgent. 



9.1 .2.4 As indicated above, the Cabinet Policy was not complied with and therefore 



did not constitute legal authority for the expenditure incurred by the DPW in 
respect of the Nkandla Project. The declaration of the President's private 
residence as a National Key Point on 8 April 2010 therefore had the result 
that as from that date, he was required to secure his private residence at his 
own cost. His failure to do so without reasonable cause would have 
constituted a criminal offence. 



9.1 .2.5 It is common cause that the President did not implement any security 
measures in respect of his private residence, as was required of him in terms 
of section 3 of this Act. 



391 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH flfEICfl 



9.1 .2.6 There is no evidence that the Minister of Police issued a notice in terms of 
section 3(2) of this Act ordering the President to within a specified period and 
at his own expense takes steps to secure the premises. 



9.1 .2.7 The Minister of Police could, in terms of section 3A of the National Key Points 
Act, only have taken over the duties of the President to secure his residence 
as a National Key Point, on his behalf and with his consent. In such a case, 
the President was liable for the cost of the steps taken, to the extent 
determined by the Minister. 



9.1 .2.8 I requested the Minister of Police on several occasions during the 
investigation to submit the relevant documents and/or correspondence 
indicating that the President was informed of the actions taken by the 
Minister as far as securing his private residence was concerned, that he 
consented to it, that a decision was taken accordingly and that he was 
informed of his liability for the costs involved. 

9.1.2.9 No such documents and/or correspondence could be provided and I could 
find no evidence or indication that the Minister invoked the provisions of 
section 3A of the National Key Points Act at any time. 

9.1 .2.10 When I raised my views on the evidence pointing at non-compliance with the 
provisions of the Cabinet Policy of 2003 and the National Key Points Act with 
the Minister of Police during the investigation, he contended that: 

"There is no provisions in the NKP (National Key Points) Act which requires 
the President as the owner of the Key Point to pay for the security measures 
that are implemented at the Key Point if the security measures (security 
upgrades) are implemented to provide for his own security as a President 
and not the security of the Key Point. The only instance the President as the 
owner of the Key Point would be required to pay for the security measures 



392 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



implemented at the Key Point is when such security measures are 
implemented in order to protect the Key Point and not the President. 

9.1.2.11 I found the reasoning of the Minister difficult to follow as the purpose of the 
National Key Point Act is the safeguarding of a "place" and not a person. 



9.1 .2.1 2 The Minister correctly contended that: 



" What is patently clear from the reading of Sections 2 and 3 of the NKP Act is 
that the security that is required to be implemented by the owner of the Key 
Point at his cost or expense is the security of the Key Point and not the 
security or safety of the owner. " 



9.1.2.13 This in my view clearly means that once the Minister had decided that the 
"place" i.e. the President's private residence had to be declared a National 
Key Point, the focus was on safeguarding it and not the President. It was the 
Minister himself that informed the President in the Declaration Certificate that 
he had to take the safeguarding measures at his private residence at his own 
cost. The anomaly in this regard is that the President's private residence was 
obviously only regarded as a National Key Point, due to the fact he it is his 
home. If anyone else was living there, it would not have been so declared. It 
is therefore clearly different from an airport or military installation that would 
remain a National Key Point, irrespective of its occupants. 



9.1 .2.14 The Minister maintained that the security measures were implemented by the 
DPW at the President's private residence in terms of the Cabinet Policy of 
2003. He stated further that: 



It is illogical to suggest that the State's obligation to implement security 
measures ceased to exist the moment his private residence was declared a 
Key Point. The State's obligation to implement security measures at the 
President's private residence continued beyond its declaration as a Key Point 

393 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



on 8 April 2010 because the Cabinet Policy of 2003 enjoins the State to 
provide for the President's safety at his private residence by implementing 
security upgrades at his private residence. For the above reasons there 
would have been no legal basis for me as the Minister to have required the 
President to pay for the security upgrades post 8 April 2010 as required by 
Section 3(1) of the NKP Act for the simple reason that Section 3(1) of the 
NKP Act does not apply to the security upgrades that were initiated and 
implemented in (sic) the President's private residence. " 

9.1 .2.15 The difficulty I have with the Minister's view is that the Cabinet Policy was not 
complied with. The measures implemented up to 7 April 2010 were therefore 
not based on compliance with the relevant instrument. The Minister's 
submissions further fail to accept that it was he who ordered the President to 
pay under the National Key Points Act. 



9.1.2.16 In his submissions in this regard, the President stated that the security 
measures implemented at his private residence should not be "measured 
against the prescripts of the National Key Points Act. " 



9.1 .2.17 The President contended in this regard that: 



"A national key point does not out of necessity imply that security features 
must be present; 

The regulatory framework of the National Key Points Act relates to the 
security of the place ; 

security features are assessed and evaluated with specific regard being had 
to the person , in this instance my position as President of the Republic of 
South Africa; 

security measures may be implemented without the declaration of a National 
Key Point and vice versa; 



394 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




any discussion regarding a contribution by me to the costs of the key point in 
terms of section 3 relate to the security of the place and not its construction. " 



9.1.2.18 As already indicated, I agree with the contention that the purpose of the 
National Key Points Act is the safeguarding of a place and not a person. 

9.1.2.19 During their presentation on his submissions, the President's legal team 



submitted that a place can be safeguarded without security measures and 
that the security of a place such as the President's private residence does 
not have to involve construction. I found this argument difficult to accept as I 
could not envisage the safeguarding of a private residence without any 
security measure, even if it only a palisade fence, that would not involve 
construction. 



9.1 .2.20 The legal position in my view is therefore that the National Key Points Act 



was not complied with. The other authorising instrument, being the Cabinet 
Policy of 2003 was not fully complied with as the prescribed procedures were 
not adhered to and the boundaries thereof exceeded. 



9.1 .2.21 The expenditure incurred by the DPW in respect of the Nkandla Project was 
accordingly irregular. 

9.1.2.22 The failure by the Acting Directors-General of the DPW, to ensure that the 



expenditure incurred by the DPW in respect of the Nkandla Project was 
based on a valid authorizing instrument constituted a violation of the 
provisions of section 38 of the PFMA, was improper and amounts to 
maladministration. 



395 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC f>eo>tectop? 

SOUTH flfEICfl 



9.1 .3. The South African Defence Review 

9.1.3.1 The South African Defence Review was issued in 1998, by virtue of the 
White Paper on National Defence for the Republic of South Africa, which 
constitutes the National Defence Policy. 

9.1 .3.2 Chapter 7 of the Defence Review provided for the non-military tasks to be 
performed by the South African National Defence Force (SANDF). 

9.1 .3.3 In terms of paragraph 9 of this Chapter, the SANDF provides VIP air 
transport for the President, the Deputy President, the Minister and Deputy 
Minister of Defence and, where capacity allows, for other Cabinet Ministers 
and Premiers. 

9.1 .3.4 Paragraph 22 provides that: 

"The SAMHS (South African Military Health Service) also provides medical 
care to the President, the Deputy President, the Minister and Deputy Minister 
of Defence and, at the request of the Department of Foreign Affairs, foreign 
VIPs visiting South Africa." 

9.1 .3.5 It has already been indicated that no specific documents were provided that 
expressly authorize the building of a clinic. Another regulatory instrument 
cited was the Military Doctrines authorising SAMHS to provide medical 
assistance, including specialised health facilities to government departments 
on request. It did not seem to make sense that the President's private 
household would be classified under government departments. Lt Gen 
Ramlakan conceded that much of the ground traversed in Nkandla had no 
previous trail from its own activities in relation to predecessors. A mobile 
clinic given to former President Mandela in the last years of his life was the 
closest precedent. Then there was an airport said to have been built a stone 
throw away from former President Botha's house in George, which turned out 



396 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




to be a public airport built 23 km from private residence at Wilderness. In fact, 
this provided precedence of the approach that keeps the people first while 
meeting the unprecedented needs of an important dignitary such as the first 
citizen. 



other items constructed during the project and the excessive 
expenditure incurred 



9.2.1. As I have indicated above, it was alleged and/or suggested by some of the 



complainants that the Nkandla Project went beyond addressing the security 
elements that are necessary for the protection of the President and that it 
constituted an improper improvement and extension of his private residence. 



9.2.2. It is not disputed that the security at the President's private residence had to 
be improved when he took office in May 2009. 

9.2.3. The SAPS, DOD and DPW were responsible for the implementation of the 
Nkandla Project and the SAPS and the DOD had to carry most of the cost, as 
the client departments. 

9.2.4. In the absence of a clear DPW policy on the implementation of security 



measures at the private residence of the President, the details and extent of 
the Nkandla Project were to be informed by the requirements itemised in the 
security evaluations. The DOD part needed to be based on precedent and 
where none existed a request for a higher authorisation from a higher 
authority, such as Cabinet, should have been considered. 



9.2.5. It must be understood that the legal and policy framework regulating security 
measures at the President's private residence do not allow for discretionary 
decisions regarding additional measures that could be taken. As far as such 



9.2. 



The relevance to security of the measures installed and buildings and 



397 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



SOUTH flfEICfl 



discretion was to be exercised, it should in any event have been exercised 
reasonably. 



9.2.6. There is a clear mismatch between some of the "big" items in the list and the 
lists in the Minimum Physical Security Standards instrument, and the list 
prepared by the security experts. The table below shows this discrepancy. 



398 



Secure In Comfort 



A Report of the 
Public Protector 



March 



MEASURES AUTHORISED BY PRESCRIPTS 












PRESCRIPTS BUT 
ECOMMENDED BY SECU 
VALUATIONS OR INCIDEf 






EASURES NEITHER AUTHORISED BY 
tECRIPTS NOR RECOMMENDED BY 
SECURITY EVALUATIONS OR 
INCIDENTAL THERETO 














Safe haven Secure room on the surface that could not be reached 
or surveyed from outside the residence. Should consist of 
enforced brick walls and ceiling, bullet resistant windows and a 
bullet resistant door 




Safe haven facility underground with 
air-conditioning and lifts 


CCTV Security System 






Intruder alarm system 






Solid walls and bullet resistant glass in certain rooms 


Bullet Resistant Glazing installed 
in all the areas regarded as 
sensitive 


Bullet resistant glass installed in the 
President's houses and all buildings that 
he regularly use 


Security doors in certain rooms 






Burglar proofing of certain rooms 


All windows to be fitted with 
burglar proofing secured to the 
walls 




A new secured and security equipped guard hut to be built at the 
new main gate 


2 Additional guards huts 




Brick and Mortar Perimeter fence 

External and internal perimeter fence around the entire 
homestead 


High security parameter fence 





399 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



MEASURES AUTHORISED BY PRESCRIPTS 


MEASU ltc?J 1 o T U c T R H M T R ' SED BY MEASURES NEITHER AUTHORISED BY 
PRE^CRIPT^ RUT 

nr^^r-^rr, „w f rn ,„,™ PRECRIPTS NOR RECOMMENDED BY 

ZTr l SECURITY EVALUATIONS OR 
EVALUATIONS OR INCIDENTAL INCIDENTAL THERETO 


Fire-fighting equipment in certain rooms Fire detection system 
linked to the Control Room and proper fire-fighting equipment in 

iij.1 i *ii* r ■ i I-. >i ■ 

all the buildings of the President 


Fire extinguishers and fire 
hydrants 


A fire-pool converted into a swimming 
pool 


Illumination of the residential area 






Security gate at the main entrance 






Security control room 








Secure garage parking 




Living quarters for SAPS staff with parking facilities 




20 thatched roof buildings with a 
laundry facility, paved roads, 
landscaping constituting a small 
residential village 


A new borehole to be sunk to improve the water supply to the 
premises, alternatively, a mini sewer treatment plant to be built 


Steel water reservoir and mini 
sewer treatment plant 





400 



Secure In Comfort 



A Report of the 
Public Protector 



March 



MEASURES AUTHORISED BY PRESCRIPTS 












PRESCRIPTS BUT 
ECOMMENDED BY SECU 
VALUATIONS OR INCIDEf 






EASURES NEITHER AUTHORISED BY 
tECRIPTS NOR RECOMMENDED BY 
SECURITY EVALUATIONS OR 










Turk chnn inQiHp thp rpQirlpnti^il arpa tn hp rplnr^ttprl 

1 ULI\ Jl 1U[J 1 1 1 O 1 U C L 1 IC 1 CjIUCI 1 Ud 1 d 1 Cd LU UC 1 ClUtaLCU 


Tuck shop relocated 




Standby generator for uninterrupted power supply to security 

bybLclllb 


Standby generator for 
uninterrupted power supply to 
security systems 




Health care facility 




■ I 1 ! 1 !. 1 • • • ■ ■ r ■ 

Military clinic consisting of a permanent 
structure furnished with specialized 
equipment and facilities for the 
exclusive use of the President, his family 
and staff. 


Helicopter landing pads 






Temporary accommodation for SAPS and DOD staff 
Park Homes 










Construction of a new kraal and 
installation of culvert with remote 
controlled gate 






Amphitheater and area for marquee 
tent 



401 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



scum mi men 





MEASURES NOT AUTHORISED BY 
PRESCRIPTS BUT 
RECOMMENDED BY SECURITY 
EVALUATIONS OR INCIDENTAL 




| 


MEASURES AUTHORISED BY PRESCRIPTS 




IASURES NEITHER AUTHORISED BY 
iECRIPTS NOR RECOMMENDED BY 
SECURITY EVALUATIONS OR 
INCIDENTAL THERETO 














Relocation of 4 households 


Patrol roads between fences 




Elaborate paved roads, terraces and 
walkways 






Visitors Lounge 




Landscaping necessary to 


Other landscaping 




rehabilitate land and address 








storm water 







Figure 18: Breakdown of Authorised, Unauthorised and Non-Security Related Measures Implemented in the Nkandla Project 



402 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




9.2.7. The Minister of Police suggested during the investigation that one would 



require the opinion of a security expert to determine whether the measures 
that were implemented by the DPW went beyond what was required for the 
security of the President. 



9.2.8. There is no evidence indicating that Mr Makhanya had any experience in the 



design of security related projects. The argument presented that being an 
architect qualifies him to design security installations has the same 
implication as arguing that just because I am a lawyer I am an expert at any 
area of the law. That cannot be logical. 



9.2.9. Regarding how I was to determine legitimate installations in the name of 



security I agree with the concession made by the President's legal team in its 
submissions that the determination of what constituted security provisions for 
the President had to be made on the list contained in the two SAPS Security 
Evaluation Reports. There is no evidence that any of the security measures 
that are not referred to in these reports and that were installed in addition 
thereto were based a proper security evaluation. The evidence, as alluded to 
earlier, shows on-going casual discussions and measures implemented on 
an impromptu idea, with most of these ideas coming from Mr Makhanya. 



9.2.1 0. The excessive expenditure incurred by the state was the result of a failure on 



the part of the SAPS and DPW officials responsible for the implementation of 
the Nkandla Project to guard against expenditure that was not authorised or 
necessary for the security of the President and, to focus on what was 
reasonably affordable. Whatever the discretionary powers that were 
exercised in this regard, such powers were clearly not applied within reason. 
I noted that the escalation in the estimated cost of the Nkandla Project from 
approximately R27 million to approximately R225 million was also the result 
of additions that were not recommended or requested by security experts. 



403 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




9.2.1 1 . I also noted that the National Key Points Act, which one of the instruments is 



relied upon in terms of which the Nkandla Project was implemented, provides 
for security measures to be taken at the expense of the owner of the National 
Key Point, in this case the President. This, in my view, is indicative of the fact 
that the Legislature regarded the measures that have to be taken to be 
reasonable and affordable to the owner of the National Key Point. This 
principle was clearly not applied by the DPW, SAPS and DOD in the 
implementation of the Nkandla Project. 



9.2.12. One of the other reasons for the excessive expenditure, which resulted in a 



misappropriation of public funds, was that Mr Malebye, the Acting Director- 
General of the DPW delegated, against the law, unconditional and unlimited 
authority for the procurement of goods and services to the Regional Office in 
respect of the Nkandla Project. 



9.2.13. Mr Makhanya also indicated that the Project Team did not have the luxury to 
plan in advance but that planning took place while the works were being 
implemented. 

9.2.14. The extent of the difference between the expenditure incurred by the state in 



respect of the security measures installed at the private residences of former 
Presidents Botha, De Klerk, Mandela and Mbeki and incurred at President 
Zuma's private residence is an indication that the enabling policy framework 
anticipated something more modest. This is so even if we take into account 
the location and remoteness of the area of Nkandla, as is indicated in the 
table below: 



404 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



R 250,000,000 



R 241 000 000.00 



R 200,000,000 



R 150,000,000 



R 100,000,000 



R 50,000,000 



R0 




R 173 338.32 

(R20 101.67) 



R 236 484.78 

(R42 196.19) 



R 32 000 000.00 R 12 483 938.17 

(R 8 113 703.24) 

& m 



Botha De Klerk Mandela Mbeki 

□ (Actual Value) □ Estimated 2013 Value 



Zuma 



Figure 19: Comparative Expenditure on Security Related Upgrades 



9.2.1 5. Lt Gen Ramlakan referred to the fact that the DOD had placed a field hospital 
at former President Mandela's rural home, the replacement costs of which 
amounts to more than R17 million. However, this is a mobile facility that can 
in the future be utilized elsewhere and is not a permanent fixture, as is the 
case of the military clinic that was constructed at the Presidents private 
residence at a cost of R1 1 million. 



9.2.16. The table below indicates the measures that were installed by the state as 
part of the Nkandla Project that constitutes an improvement of the 
President's private residence in comparison with the measures that constitute 
state facilities: 



405 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 



JCjLIC F>EO>TE<:.TOk 
SOUTH flft'lOl 



MEASURES INSTALLED THAT FORM PART 
OF OR ARE DIRECTLY LINKED TO THE 
PRESIDENTS PRIVATE RESIDENCE AND 



iTiVli jHMl^kirilll jili!riiljill*«li 1 m I >J 4*J mil] 



SIDENTS PRIVATE RESIDENCE AND FORM PART OF 
STATE FACILITIE 



Security systems installed in all the 
Presidents houses and other buildings 



Military Clinic 



Security fence and patrol roads around the 
Presidents private residence 



Security fence and patrol roads outside of the President's 
private residence and around buildings and facilities of 
the state 



Visitors' Centre 



Security Control Room 



Swimming Pool 



Helipads 



Amphitheatre 



Crew Pavilion 



Grassed area for Marquee Tent 



Staff accommodation and parking facilities 



Paved areas around the swimming pool, 
Visitors Centre and amphitheatre and paved 
walkways 



Park Homes 



Safe Haven 



Guard house and entrance gate at main entrance 



New houses for relocated households 



Landscaping of the terrain occupied by the state 



Emergency electricity facilities 



SAPS Garage 



New kraal and culvert 



Transformer & LV Room and refuse area 



New Tuck Shop 



Steel water reservoir and mini sewer 
treatment plant 



lumination around the residence 



Fire detection systems 



Bullet resistant glazing 



Security doors in certain rooms of buildings 
of the President 



Burglar proofing of all buildings of the 
President 



Landscaping of the terrain of the President's 
residence 



Air conditioning of President's houses 



Figure 20: Comparison between Private Residence and State Facilities Upgrades 

9.2.17. There is no question that the President's private residence was substantially 
increased due to some of the measures taken by the state. Clearly, items 
such as the Visitors Centre, swimming pool and terrace, amphitheatre, 
elaborate paved roads, terraces and walkways and the building of the kraal, 



406 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




with an aesthetically pleasing structure, a culvert with a remote controlled 
gate and chicken run, added substantial value to the property. 



9.2.18. The excessive nature in which the Nkandla Project was implemented went a 



long way to beautify the President's private residence and to add comfort to 
its infrastructure, which was not the objective of security measures that had 
to be implemented for his protection. 



9.2.19. If one takes into account the condition and extent of the President's private 



residence when the Nkandla Project started and compares it with its current 
stature, it is obvious that the state has made a major contribution to the 
President's estate at the expense of the taxpayer. 



9.2.20. The relocation of neighbours households, at the substantial cost to the state 
of approximately R8 million has no legal basis apart from the issue of legality, 
no sensible and affordable alternative was considered. 

9.2.21 . Regarding the outside installations, it is clear that there is a legal and policy 



lacuna or gap. The first gap relates to whether these installations can be 
implemented at or near a private person's household when the person at the 
time is a president or another qualifying dignitary. The law advanced does 
not seem to support Lt Gen Ramlakan. The second gap refers to what 
exactly can be implemented as privileges for a public office bearer. Should 
such bulk facilities be directed at a deserving dignitary and his or her family 
or placed in the community for collective benefit, in a manner that gives 
convenient access to the deserving dignitary? The third gap is related to 
whose onus is it? Is it the DOD or the DPW, and if so, for whose account? 



407 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 ^^^^ 

PUBLIC F>EO>TECTOE? 
SOUTH flfPIOl 



9.3. The Allegation That The President's Family Improperly Benefitted From 
The Project 

9.3.1. On the original allegation that the President's brothers may have benefitted, 
there is no evidence. Had this happened, the law is clear that this would have 
been unlawful. 



9.3.2. There is no question that his family benefitted from these as they now form 
part of the President's estate. 

9.3.3. The question that arises is whether or not the family has and will continue to 
unduly benefit from the luxurious items not recommended in the security 
evaluation. 



9.4. Compliance of the Public Office Bearers and the Officials with the 
Regulatory Framework Regulating the Procurement of Goods and 
Services In Respect of the Nkandla Project 

9.4.1. The evidence obtained from officials of the DPW approached during the 
investigation confirmed that the practical application of the prescribed 
regulatory framework in respect of the implementation of a new project would 
be as follows: 



9.4.1 .1 Any new project is generated based on a needs assessment prepared by the 
client department, as approved by its accounting officer and presented to the 
DPW head office. 



9.4.1.2 The request for the implementation of the project is registered as a 
programme and managed in accordance with the following principles: 



408 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




(a) Scope management-the client department's request and needs are 
clearly identified, documented and approved. This includes any 
standard norms, policies and standards that are applicable; 

(b) Finance and time management- the project cost is determined and 
budgeted for over the Medium Term Expenditure Framework cycle; 

(c) Procurement and management-once the scope of the project has been 
finalized and funds allocated, the prescribed procurement processes 
are implemented. The procurement plan must be in line with the 
relevant regulatory framework; 

(d) Communication Management-the project manager is the centre point of 
communication between the DPW, the client department and the 
professional team; and 

(e) Quality management. 



9.4.2. It is not in dispute that the SAPS, the DOD and the DPW did not implement 
and apply a proper demand management process in respect of the 
implementation of the project, as was expected of the respective 
departments in terms of the PFMA, the Treasury Regulations and the DPW 
Supply Chain Management (SCM) Policy. 

9.4.3. The original scoping of the Nkandla Project conducted by the Regional Office 
was inadequate, which resulted in a misconception of the actual cost 
involved. 

9.4.4. The explanation provided to me during the investigation that it was not 
possible to plan in advance due to the urgency of the Nkandla Project, 



409 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




cannot be accepted, if one takes into account that the appointment of 
contractors for Phase 1 of the project was only approved in March 2010, i.e. 
1 months after the project commenced. 



9.4.5. No reasonable explanation was presented as to why a comprehensive needs 



assessment could not have been drafted, costed and submitted by the client 
departments to the DPW in order for everyone involved to participate in 
decisions in respect of what measures were really necessary and reasonably 
affordable. 



9.4.6. It was also not clear why the DPW accepted that it was responsible for the 
cost of the Nkandla Project despite the fact that the requirements in respect 
of it came from the SAPS and the DOD as the client departments. 

9.4.7. The designs of the Nkandla Project became more expensive and in certain 



cases elaborate as time passed, which made it difficult for the DPW (that 
mistakenly accepted responsibility for all the cost) to budget for its 
implementation. 



9.4.8. The sensitivities, importance, scale and cost of the Nkandla project clearly 



warranted regular meetings between high level officials of the departments 
involved, including the accounting officers, to discuss the extent of the 
project, the expenditure involved, the value for money for the state and the 
progress made, on a regular basis. This did not happen and everything was 
basically left in the hands of the consultants and the DPW office bearers and 
officials involved. 



9.4.9. I could find no indication in the evidence that the officials of the DOD and 
SAPS involved in the project reported to their respective accounting officers 
on the involvement of their departments and its liability in terms of the 



410 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




expenditure. The National Commissioner of Police and the Chief of the 
SANDF were clearly left in the dark due to the fact that the officials looked at 
the DPW to foot the bill of their requirements. The accounting officers of the 
SANDF and the SAPS were therefore not placed in a position where they 
could perform their functions and take responsibility for the involvement of 
their departments, in terms of section 38 of the PFMA. 



9.4.10. The failure of the SAPS, DOD and DPW to implement a sensible and 



affordable demand management process in respect of the Nkandla Project 
was not in accordance with proper supply chain management practices that 
could have linked it to strategic planning and budgeting processes, as is 
envisaged and required by the PFMA, the Treasury Regulations and the 
DPW SCM Policy. It was therefore improper and constitutes 
maladministration. 



9.4.1 1 . As I have indicated above, the DPW does not have any policy that regulates 



the implementation of security measures at the private residences of 
Presidents, Deputy Presidents, former Presidents and former Deputy 
Presidents, as authorized by the relevant Cabinet Policy. The absence of any 
guidelines in this regard left the officials involved with little direction and their 
inability to manage the process properly was further compounded by the 
involvement of the Minister and Deputy Minister, which was extraordinary. 



9.4.1 2. It was expected of the DPW, the SAPS and the DOD, by the provisions of the 



PFMA, the Treasury Regulations and Guidelines of the National Treasury to 
budget properly and in advance for the Nkandla Project, which budgeting had 
to be linked to the demand management process. The DPW erroneously 
accepted responsibility for the cost of the project right from its inception. 



411 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




9.4.14. 



9.4.15. 



9.4.16. 



9.4.17. 



9.4.18. 



Although the DPW probably could not have budgeted in advance for the 
project prior to May 2009, as Mr Zuma's election as the President was not a 
certainty, it was well aware of the need to secure the President's private 
residence by August 2009. 

However, the DPW still failed to include it during the 2010/2011 budget. It 
also underestimated the extent of the expenditure in respect of the 
201 1/2012 and 2012/2013 budgets, clearly as a result of not implementing a 
proper demand management process, which resulted in the budgeted 
amounts allocated to other necessary capital works programmes of the DPW 
being negatively affected. 

The evidence of Ms Motsisi, the former Chief Financial Officer of the DPW, 
also indicates that the DPW had a tendency at the time of the implementation 
of the Nkandla Project to over commit its Prestige Budget, which then had to 
be corrected by shifting funds from other necessary projects. 

The acceptance by the DPW of the responsibility for the cost of the Nkandla 
Project and its failure to budget properly was contrary to what is required by 
the PFMA and the Treasury Regulations. It was therefore improper and 
constitutes maladministration. 

Treasury Regulation 16A6.4 provides for a deviation from the default position 
of inviting competitive bids in cases where it is impractical to do so. 

Under such circumstances it would be permissible to procure goods or 
services by other means, provided that the reasons are recorded and 
approved by the accounting officer. 



412 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




9.4.20. 



9.4.21. 



9.4.22. 



9.4.23. 



9.4.24. 



The typical circumstances covered by the directives and guidelines issued by 
the National Treasury are urgent or emergency cases and where the service 
or product can only be provided by a sole supplier. 

In all cases where goods and services above the value of R1 million were 
procured in terms of Regulation 16A6.4, it had to be reported to the National 
Treasury and the Auditor-General. 

The DPW records show that at the time when the Nkandla Project 
commenced, the DPW's internal directives provided that procurement of 
goods and services amounting to more than R20 million per procurement, 
had to be submitted to and recommended by the Special National Bid 
Adjudication Committee (SNBAC). 

However, in the case of this project, procurement strategies were submitted 
to and approved by the Regional Bid Adjudication Committee (RBAC), in 
terms of a delegation issued by the then Acting Director-General, Mr 
Malebye, authorizing it to do so in amounts above R20 million. 

The only motivation in the evidence obtained during the investigation for the 
decision to delegate unlimited authority to the RBAC, was that the Nkandla 
Project had to be fast tracked due to the fact that it related to the security of 
the President and that submission of requests for the approval of 
procurement strategies to the SNBAC would only have caused delays. 

Although this decision of the Acting Director-General was within his powers 
and authority in terms of section 38 of the PFMA, it does not seem to have 
taken into account the fact that the SNBAC was established at the National 
Office of the DPW, consisting of senior and experienced staff to ensure 
proper compliance with the relevant Supply Chain Management Policy and 



413 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




prescripts, responsible procurement strategies and value for money, in cases 
where the expenditure of public funds was to go as high as R20 million. 



9.4.25. I could find no indication in the evidence that any measures or strategies to 
expedite submissions to the SNBAC in the case of the Nkandla Project, as a 
special arrangement, was investigated or considered. 

9.4.26. It is not clear to me how the RBAC suddenly became better qualified to 
consider procurement strategies and procurement of goods and services of 
more than R20 million in the case of the Nkandla Project, when other such 
projects, still had to be submitted to the SNBAC. 

9.4.27. Mr Malebye's decision in my view failed to comply with the standard of care 
required of an accounting officer in terms of section 38 of the PFMA was 
therefore improper and constitutes maladministration. 

9.4.28. Regarding the appointment of Mr Makhanya, as Principle Agent and overall 



architect, the first issue is whether or not it was proper to do so without going 
on tender. On the basis of the original quotes, which were under R500 000, 
only three quotes were needed. Once the project scope became wider, it 
needed to go on tender, the alternative being "allowed deviations". His 
appointment did not satisfy the requirements of the legal framework. 



9.4.29. The next issue is that of conflict of interest. Conflict of interest arises when a 



person is placed in a position of serving two masters. The President's legal 
team disagreed in their submissions with my view that Mr Makhanya had a 
conflict of interest as far as his involvement in the Nkandla Project was 
concerned. According to them, there is nothing wrong with an architect acting 
on behalf of a private client (who also happens to be the head of state) and 



414 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




as the Principal Agent and architect for the state in designing works for the 
same premises. It was not clear to me how they envisaged Mr Makhanya 
was supposed to have dealt with a situation where the interests of the state 
clashed with that of his private client. 



9.4.30. Mr Makhanya, in my view, allowed himself to be placed in a precarious 



position as a professional consultant. He had to look after the personal 
interests of the President in respect of his private construction works and also 
after those of the state in respect of the implementation of the project. The 
fact that he was appointed by the President, had direct access to him and 
reported to him on the project from time to time, naturally had an impact on 
the officials involved who would have been reluctant to confront him as the 
Principal Agent, on his designs. The evidence indicated that he was directing 
the Project Manager what to do, instead of the opposite. 



9.4.31. There is no indication in the evidence that the DPW considered Mr 



Makhanya's qualifications and appropriate experience to design a security 
project of this magnitude . He should, in my respectful view, not have been 
involved in the Nkandla Project. Instead, he should have been consulted 
where there were overlaps between the project and the President's private 
works. 



9.4.32. No other convincing or acceptable reason pointing at the requirements of 



Treasury Regulation 16A6.4 could be provided to me during the investigation 
for the deviation from the competitive process required by section 217 of the 
Constitution, in this case. 



9.4.33. Under the circumstances, the failure to comply with the prescribed 
competitive bidding process as far as the procurement of the services of the 



415 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




consultants referred to above is concerned, was improper and amounts to 
maladministration. 



9.4.34. The DPW Directive on Acquisition and Disposal Management provides that 



the nominated procurement strategy is undesirable and may only be 
approved as a last resort. It may be used in emergency cases, where there 
are time constraints in carrying out the service or for the supplying of goods 
or where the services required are of a specialized nature. 



9.4.35. It is not in dispute that there was no emergency when the appointment of the 



private Project Manager (Ramcon) was considered, that required a deviation 
from an open competitive bidding process. The only urgency indicated at the 
time was that due to the President's complaints, the Ministry of Public Works 
had determined a target date for completion that had to be complied with. 



9.4.36. The records of the DPW, including the Minutes of Progress Meetings, 



indicate that at the time when it was decided to appoint a private Project 
Manager there were serious delays in the Nkandla Project and that the DPW 
Project Manager was struggling. The time constraints were therefore self- 
imposed and the result of inordinate delays in the project on the part of the 
DPW, which was clearly, as confirmed by the evidence, the result of a lack of 
proper planning and management. 



9.4.37. The decision to deviate from an open and competitive bidding process to 



appoint a private Project Manager by means of a nominated procurement 
strategy did not comply with the requirements of section 217 of the 
Constitution, the PFMA, the Treasury Regulations and the SCM Policy and 
prescripts of the DPW. It was therefore improper and amounts to 
maladministration. 



416 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




9.4.38. I could find no indication that the situation at the time when it was decided to 



approve a nominated procurement strategy in respect of the appointment of a 
contractor for the so called "emergency works", constituted an emergency or 
urgency that was not caused by inordinate delays and a lack of planning on 
the part of DPW itself. The Nkandla Project was already 10 months old by 
then and no attempt had been made to appoint contractors to implement 
works that were described as "emergency. 



9.4.39. The DPW records furthermore do not indicate that an informed decision was 



taken by the RBAC that it was impractical to utilize an open and competitive 
bidding processes, even if it was shortened. The argument presented by Mr 
Rindel that the screening of contractors would take up to four months to 
complete was only based on previous experience. 



9.4.40. There is no indication in the evidence and information that I obtained during 



the investigation that the DPW approached NIA (SSA) to assist it in 
expediting the screening process, should an open tender process be 
followed, especially as the Nkandla Project related to the private residence of 
the President. It is also not clear to me why the details of the scope of works 
could not have been provided to qualifying interested contractors after the 
screening process had been completed. 



9.4.41 . The decision of the RBAC to approve the nominated procurement strategy 



which resulted in the appointment of Bonelena was not in accordance with 
the requirements of competitive bidding, as contemplated by section 217 of 
the Constitution, the PFMA, Treasury Regulations and the DPW SCM Policy 
and directives. It was improper and constitutes maladministration. 



9.4.42. The DPW Directive on Acquisition and Disposal Management regards the 
negotiated procurement strategy as the least desirable, provides that it can 



417 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




only be approved by the Bid Adjudication Committee as a last resort and that 
it may only be used, inter alia, in urgent or emergency cases when the 
competitive bidding process is impractical, provided that the circumstances 
giving rise to the urgency were neither foreseeable by the DPW nor the result 
of the dilatory conduct on its part. 



9.4.43. I found no indication during the investigation that the motivation for the 



deviation considered by the RBAC in respect of the appointment of 
Moneymine 310 CC (Moneymine) in Phase 1 of the project included any 
reference to emergency or urgency. 



9.4.44. The evidence further does not indicate that the suggestion by Mr Rindel in 



respect of the impact of the appointment of another contractor on the 
guarantees provided to the President by Moneymine, was properly 
interrogated and informed. No reasonable explanation was presented to me 
why the issue of integration with the private works and the providing of 
guarantees could not have been negotiated and agreed upon between 
Moneymine and another contractor. 



9.4.45. I cannot reasonably conclude that the circumstances 10 months after the 



Nkandla Project commenced, could have been such that a competitive 
bidding process was impractical and that the negotiated procurement 
process followed to appoint Moneymine was the last resort available to the 
DPW. 



9.4.46. The decision by the RBAC to approve the negotiated procurement strategy 



was probably influenced by the fact that Moneymine had been appointed by 
the President for his private construction works. It was not in compliance with 
the requirements of competitive bidding, as contemplated by section 217 of 



418 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




the Constitution, the Treasury Regulations and the DPW SCM Policy and 
prescripts, was therefore improper and constitutes maladministration. 



9.4.47. No reference was made to emergency, urgency or whether it was at all 



impractical to employ an open and competitive bidding process to procure 
the services of contractors for the implementation of Phase 2 of the project, 
costing millions of rand. 



9.4.48. The RBAC's decision to approve negotiated procurement strategies in 
respect of Bonelena and Moneymine for Phase 2 was clearly influenced by 
what was regarded as instructions from the Deputy Minister. 

9.4.49. I could find no reasonable indication from the evidence of the officials and the 



records of the DPW why the negotiated procurement strategy was regarded 
as the last resort. The decision of the RBAC in this regard did not consider 
the prescribed requirements for deviation and was not in compliance with the 
provisions of section 217 of the Constitution, the Treasury Regulations and 
the DPW SCM Policy and directives. It was therefore improper and 
constitutes maladministration. 



9.4.50. By the time that the order for bullet resistant glass was issued, Mr Zuma had 



been the President for 1 year and 10 months. It therefore cannot be argued 
that an immediate emergency or urgency arose, that was not prevalent at the 
time of his appointment, which could have justified a deviation from a 
competitive bidding process for a procurement of more than R3 million. 



9.4.51 . If there was an emergency, it was in any event the result of poor planning 



and management of the project on the part of the DPW. There is also no 
indication in the evidence that it was impractical to have utilized a more 
competitive procurement process. 



419 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




9.4.52. A direct order was placed and the procurement prescripts violated by the 
officials involved because of instructions given by the Minister, who was 
under pressure from the President. 

9.4.53. If the installation of the bullet resistant glass had been properly planned, the 



impact on ventilation would have been obvious. This could then have been 
addressed by means of a more competitive procurement process. The DPW 
was solely responsible for the urgency that arose and the resultant deviation 
from the prescribed procurement process. 



9.4.54. I am of the view that the deviations from the default procurement process, i.e. 



open and competitive bidding in the procurement of bullet resistant glass 
from SA BRG Glass and the air conditioning units, were not in compliance 
with the standard prescribed by section 217 of the Constitution, the PFMA, 
Treasury Regulations and the DPW SCM Policy and prescripts. It violated the 
constitutional imperative of competition, was therefore improper and amounts 
to maladministration. 



9.4.55. The failure by the DPW to record the reasons and decisions relating to the 



procurement of lifts of more than R2 million without following an open bidding 
process was a violation of the provisions of the Treasury Regulations and 
constitutes maladministration. 



9.4.56. From the evidence there is also no clear indication as to why a deviation from 



a competitive bidding process was justified as far as the procurement of the 
lifts for the safe haven was concerned. The decision of the RBAC to approve 
a nominated procurement strategy therefore has to be regarded as having 
violated the standard prescribed by section 217 of the Constitution, the 



420 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




PFMA, Treasury Regulations and the DPW SCM Policy and directives. It was 
therefore improper and constitutes maladministration. 



9.4.57. The DPW was requested on numerous occasions during the investigation to 



submit copies of the notifications to the National Treasury of all the deviations 
of more than R1 million, but no such evidence was provided. I therefore have 
to accept that the DPW failed to comply with the directive to report such 
deviations to the National Treasury, which is improper and amounts to 
maladministration. 



9.4.58. The delegations issued by the Director-General of the DPW on 3 October 



2005 provided that a reference to a "Project Manager" included all the 
professional staff members of the Chief Directorate: Professional Services, 
tasked with projects relating to the built environment. 



9.4.59. The obvious purpose of this requirement was to ensure that the Project 



Manager is provided with and has access to professional advice during the 
implementation of a project in order to achieve the desired result and 
product. 



9.4.60. The side-lining of the professional team during the implementation of the 



Nkandla Project was not in line with the delegations of the Director-General 
that established the position and authority of the Project Manager, which was 
subject to their involvement in the project. It was therefore improper and 
constitutes maladministration. 



9.4.61 . In terms of the said delegations, the sketch plans and/or preliminary designs 



of the Nkandla Project had to be subjected to a Scrutiny Committee at the 
DPW Head Office. The final approval of these plans and designs could only 
have been executed subject to comments by the Scrutiny Committee. 



421 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




9.4.62. I could find no evidence that any of the sketch plans or the designs of the 
Nkandla Project was ever submitted to a Scrutiny Committee, either at the 
Regional or Head Office. 

9.4.63. The approval of the plans and designs and amendments thereto therefore did 
not follow the prescribed process of evaluation and scrutiny, as per the 
authority delegated by the accounting officer in terms of the PFMA. 

9.4.64. The failure of the DPW to comply with the requirements of the delegations in 
this regard was improper and constitutes maladministration. 

9.4.65. The DPW conceded during the investigation that it failed to comply with the 



provisions of GIAMA in respect of the assets that it required as a result of the 
implementation of the Nkandla Project. This failure was improper and 
constitutes maladministration. 



9.4.66. The manner in which the Nkandla Project was administered and 



implemented gave me the impression of a toxic concoction of a lack of 
leadership, a lack of control and focused self-interest. The fear factor among 
officials was (and in some cases still is) prevalent due to the fact that the 
project related to the President's house and that the Minister and Deputy 
Minister were directly involved. 



9.5.1. It is common cause that the President was briefed by officials of the SAPS 



and DOD when the Nkandla Project started on the measures that had to be 
installed in his private dwellings. He has not denied that he was informed 
from time to time on certain aspects of the project by Mr Makhanya and 



9.5. 



The President's Alleged Ethical Violations 



422 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




Deputy Minister Bogopane-Zulu and reports were occasionally forwarded for 
his attention. 



9.5.2. The President was also provided with a detailed progress report on 5 
November 201 1 by the former Minister of Public Works. 

9.5.3. The President was therefore aware of what the Nkandla Project entailed. He 
obviously also observed the scale and extent of the project when he visited 
his private residence during the period of implementation. 

9.5.4. The fact that he complained on more than one occasion of the lack of 



progress made with the project and the impact that it had on his private life 
and that of his family clearly shows that he was aware of the measures taken 
and the status of its implementation. 



9.5.5. We have also ascertained some direct involvement related to his request that 
the design of the bullet resistant windows be changed and a kraal be built. 

9.5.6. There is no evidence that the President raised his concern or disapproval on 
the scale of the project that was being implemented at his private residence 
or the cost thereof with the Ministers or officials involved. 

9.5.7. The mere magnitude of the Nkandla Project, the many buildings constructed, 



including underground facilities and substantial landscaping interventions, the 
swimming pool and terrace, amphitheater, kraal and culvert, Visitors Centre, 
elaborate paving and the space created for a marquee tent, would, in my 
view, have prompted any reasonable person in the position of the President 
to seriously question the need for certain items and the expense to the fiscus 
of funds that could have been used somewhere else where there are service 
delivery needs, poverty and unemployment. 



423 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




9.5.8. Regarding his ethical conduct I considered it proper to ask him the same 



questions that I had to ask of the former Minister of Cooperative Governance 
and Traditional Affairs, the late Mr S Shiceka, and the Minister of Police, Mr 
N Mthethwa, when I investigated allegations of unethical conduct against 
them. These included did he raise any concerns about obvious extravagant 
and expensive measures that were being implemented by the state at his 
private residence? 



9.5.9. In the case of my investigation into extravagant expenditure by the Minister of 



Police on hotel accommodation (Report no 7 of 2011/12), I found that the 
Minister, when he became aware of the extent of the expenditure, took steps 
to contain it and to prevent a recurrence thereof. 



9.5.10. The standards of ethical conduct set by the provisions of section 96 of the 



Constitution and the Executive Ethics Code require of a person in the 
position of the President to have been concerned about the obvious 
elaborate scale of the project that was being implemented at his private 
residence and the cost thereof to the state. 



9.5.11. As the ultimate upholder of the values of the Constitution and custodian of 



public funds, it was, in my respectful opinion, expected of him to have 
interrogated the need for measures, such as the underground safe haven, 
the relocation of households, the construction of a Visitors Centre, swimming 
pool, amphitheatre etc. which were both extensive and in some instances 
had no obvious relation to his protection and the security of the premises. 



9.5.1 2. The evidence in connection with the changes that were made in the design of 
the bullet resistant windows after he complained about it and the building of 
the kraal, is indicative thereof that any other concerns that he would have 



424 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




raised would have been taken seriously. A substantial amount of public 
money would have been saved, had the President raised his concerns in 
time. By failing to do so, the President allowed or caused extensive and 
excessive upgrades that go beyond necessary security measures to be made 
to his private residence, at state expense. 



9.5.13. Another question regarding ethical conduct by the President related to him 



reportedly telling Parliament and the nation that no building was constructed 
for him by government. The evidence shows that these structures were 
constructed for him at state expense. The structures on the homestead part 
of the fence include the Visitors' Centre, cattle kraal with chicken run, 
swimming pool and amphitheatre. Misleading Parliament is prohibited by the 
Executive Ethics Code. My decision on his conduct is in the findings. 



9.5.14. The pertinent question related to the fact that the President may have misled 



Parliament and accordingly violated the Executive Ethics Code when he 
announced that the renovations at his private residence were financed 
through a bank mortgage bond. I deal with this in the findings. 



9.6.1. The Construction Of Buildings And Other Structures On Land That Belongs 
To The Ingonyama Trust 

9.6.1.1 In terms of the provisions of the KwaZulu-Natal Ingonyama Trust Act, 1994, 



the Kwazulu-Natal Ingonyama Trust Board required the written consent of the 
relevant traditional authority or community, before it could enter into a lease 
agreement with the DPW. 



9.6. 



Other Observations 



425 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




9.6.1.2 According to the evidence the requisite legal process to regularise building 
on trust land was no concluded. 

9.6.1.3 The DPW proceeded with the construction of buildings and other structures 



on the land immediately adjacent to the land occupied by the President's 
private residence, despite the fact that no lease agreement had been 
concluded with the KwaZulu-Natal Ingonyama Trust Board. 



9.6.1.4 In other words, the DPW does not have legal tenure of the land and the 
construction of the buildings.. 

9.6.1 .5 The implementation of the Nkandla Project leaves one with the impression of 



excessive and unconscionable "Rolls Royce" security constituting an island in 
a sea of poverty and paucity of public infrastructure. This cannot be accepted 
as conscionable in any state and certainly not in a state where section 195 
and 237 of the Constitution promise to put people first and where the Batho 
Pele White Paper undertakes to transform the state from the insular 
apartheid state to one that is people centred and puts people first 



9.6.2. The submission of the final report 

9.6.2.1 The issue of the competent authority to receive the report is one of the 



controversies that bedevilled the report. As indicated, the matter arises on 
account of the President being the competent authority to act on my findings 
under the EMEA, while in the current case he is the alleged wrongdoer. 



9.6.2.2 Dr Lubisi informed me that the relevant amendments to the Executive 



Members' Ethics Act, as requested in my 2010 report, are still in process and 
will not be completed by the time that my final report on the investigation is 
issued. 



426 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




10. 



FINDINGS 



I make the following findings: 



10.1. Was there any legal authority for the installation and implementation of 



security measures and the construction of buildings and other items at 
the President's private residence and was such authority violated or 
exceeded? 



10.1 .1 . The authority for implementing security measures at the private residence of 



the President is primarily conferred by the Cabinet Policy of 2003. In view of 
the Declaration of the residence as a National Key Point during the 
implementation of the security measures, the National Key Points Act, 
constitutes part of the legal framework conferring authority to upgrade 
security at a private residence. However, the implementation of the security 
measures failed to comply with the parameters set out in the laws in question 
for the proper exercise of such authority. 



10.1 .2. The key violation in this regard is the failure to follow the processes outlined 



in the Cabinet Policy and the deviation from the 16 security measures that 
were recommended in the Second Security Evaluation by SAPS. This 
constitutes improper conduct and maladministration. 



1 0.1 .3. With the National Key Points Act having been inexplicably dragged in halfway 



through the implementation of the Nkandla Project, its provisions had to be 
complied with. This did not happen. Neither was there compliance with the 
contents of the declaration of the Nkandla Residence as a National Key 
Point, as signed by the Minister of Police on 08 April 2010. 



427 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




10.1.4. 



10.2. 



10.2.1. 



10.2.2. 



In relation to installations at the request of the Surgeon General on behalf of 
the DOD and SAMHS, there appears to be no instrument specifically 
authorizing the construction of brick and mortar installations at or for a private 
household. The installations were justified on generic military doctrines aimed 
at installations built in pursuit of public services and the general power given 
to the SAMHS to provide health services to the President Deputy President, 
Minister and Deputy Minister of Defence and, at the request of the Minister of 
International relations, foreign dignitaries. 

Was the conduct of relevant authorities in respect of the procurement 
of goods services relating to the Nkandla Project improper and in 
violation of relevant prescripts? 

The organs of state involved in the Nkandla Project failed dismally to follow 
Supply Chain Management prescripts, such as section 217 of the 
Constitution, PFMA, Treasury Regulations the DPW Supply Chain 
Management policy, key omissions including: the absence of demand 
management; improper delegations; failure to procure services and goods 
costing above R500 000 through a competitive tender process; failure to 
conduct due diligence leading to the engagement of service providers such 
as the Principal Agent without the necessary qualifications or capacity for 
security measures; failure to ensure security clearance for service providers, 
and allowing "scope creep" leading to exponential scope and cost 
escalations. 

In addition, the DPW failed to comply with the provisions of GIAMA, which 
specifically require a proper asset management plan in respect of the 
immovable assets of the state. 



428 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 ^^^^ 

PUfctK PROIEOOI? 
SOUTH flfPICfl 



10.2.3. The conduct of all organs of state involved in managing the Nkandla Project, 
particularly officials from the DPW, who unduly failed to comply with Supply 
Chain Management prescripts was unlawful and constitutes improper 
conduct and maladministration. The DOD and SAPS officials failed to comply 
with Treasury Regulation 16A.3.2 imposing the responsibility for demand 
management on client departments, which include ensuring cost effective 
measures and budgeting, appropriately for such. 

10.3. Did the measures taken by the DPW at the President's private 
residence, go beyond what was required for his security? 



10.3.1. A number of the measures, including buildings and other items constructed 
and installed by the DPW at the President's private residence went beyond 
what was reasonably required for his security. Some of these measures can 
be legitimately classified as unlawful and the acts involved constitute 
improper conduct and maladministration. 



10.3.2. Measures that should never have been implemented as they are neither 
provided for in the regulatory instruments, particularly the Cabinet Policy of 
2003, the Minimum Physical Security Standards and the SAPS Security 
Evaluation Reports, nor reasonable, as the most cost effective to meet 
incidental security needs, include the construction inside the President's 
residence of Visitors' Centre, an expensive cattle kraal with a culvert and 
chicken run, a swimming pool, an amphitheatre, marquee area, some of the 
extensive paving and the relocation of neighbours who used to form part of 
the original homestead, at an enormous cost to the state. The relocation was 
unlawful as it did not comply with section 237 of the Constitution. The 



429 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




implementation of these installations involved unlawful action and constitutes 
improper conduct and maladministration. 



10.3.3. Measures that are not expressly provided for, but could have been 



discretionally implemented in a manner that benefits the broader community, 
include helipads and a private clinic, whose role could have been fulfilled by 
a mobile clinic and/or beefed up capacity at the local medical facilities. The 
measures also include the construction, within the state occupied land, of 
permanent, expensive but one roomed SAPS staff quarters, which could 
have been located at a centralized police station. The failure to explore more 
economic and community inclusive options to accommodate the discretional 
security related needs, constitutes improper conduct and maladministration. 



10.4. Was the expenditure incurred by the state in this regard excessive or 
amount to opulence at a grand scale, as alleged? 

10.4.1. The expenditure incurred by the state in respect of the measures taken, 



including buildings and other items constructed or installed by the DPW at 
the request of the SAPS and DOD, many of which went beyond what was 
reasonably required for the President's security, was unconscionable, 
excessive, and caused a misappropriation of public funds. The failure to 
spend state funds prudently is a contravention of section 195 (1)(b) of the 
Constitution and section of the Public Finance Management Act. The acts 
and omissions involved are, accordingly, unlawful and constitute improper 
conduct and maladministration. 



10.4.2. The first Complainant's allegation that the expenditure constitutes opulence 
at a grand scale is substantiated. The acts and omissions that allowed the 



430 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

excessive expenditure due to non-security items and failure to arrest the wild 
cost escalation, especially after the story broke in the media in December 
2009, constitute improper conduct and maladministration. 

10.5. Did the President's family and/or relatives improperly benefit from 
installations implemented by the state at his private residence? 

10.5.1. The allegation that President Zuma's brother improperly benefitted from the 
measures implemented is not substantiated. I could find no evidence 
supporting the allegations that the President's brothers benefitted from the 
procurement of electrical items for the implementation of the Nkandla Project. 

10.5.2. The allegation that the excessive expenditure added substantial value to the 
President's private property at the expense of the state is substantiated. The 
excessive and improper manner in which the Nkandla Project was 
implemented resulted in substantial value being unduly added to the 
President's private property. The acts and omissions that allowed this to 
happen constitute unlawful and conduct improper conduct and 
maladministration. 

1 0.5.3. The original allegation that President Zuma's immediate family members also 
improperly benefitted from the measures implemented is substantiated. 
President Zuma improperly benefited from the measures implemented in the 
name of security which include non-security comforts such as the Visitors' 
Centre, such as the swimming pool, amphitheatre, cattle kraal with culvert 
and chicken run. The private medical clinic at the family's doorstep will also 
benefit the family forever. The acts and omissions that allowed this to happen 
constitute unlawful and improper conduct and maladministration. 



431 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




10.5.4. I do not find the relocation of the tuck shop as a benefit as the business was 
moved at the instance of the state to a building that might even be 
inconvenient to the owner. 

10.5.5. The conduct of the DPW leading to the failure to resolve the issue of items 



earmarked for the owner's cost transparently, including the failure to report 
back on the swimming pool question after the 1 1 May 201 1 meeting and the 
disappearance of the letter proposing an apportionment of costs, constitutes 
improper conduct and maladministration 



10.6. Was there any maladministration by public office bearers, officials and 
other actors involved in the project? 

10.6.1. Public Office Bearers: 

10.6.1.1 All the Ministers of Public Works provided incorrect information on the legal 
authority for and the extent of the works at the President's private residence. 

10.6.1.2 The Minister of Police failed to properly apply his mind when signing the 



Declaration of President Zuma's private residence as a National Key Point 
directing the President to implement security measures at own cost or to 
properly modify the Declaration. This failure constitutes improper conduct 
and maladministration. 



10.6.1.3 The former Minister of Public Works, Mr G Doidge and the Minister of Police 
could have provided better executive leadership, especially with regard to 



432 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




speedily accessing the extent and cost of the Nkandla Project, particularly 
when the media broke the story in 2009 and taking decisive measures to 
curb excessive expenditure. Their failure in this regard constitutes improper 
conduct and maladministration 



10.6.2. Officials of the DPW: 

10.6.2.1 The DPW officials failed to acquaint themselves with the authorizing 
instruments relating to the implementation of the Nkandla Project. They failed 
to apply their minds and adhere to the supply chain management policy 
framework in respect of the procurement of goods and services for the 
Nkandla Project. These failures constitute improper conduct and 
maladministration. 

1 0.6.2.2 Messrs Malebye and Vukela, the Acting Directors-General of the DPW failed 



as the accounting officers of the Department at the material times to comply 
with and/or ensure compliance with the provisions of sections 1 95(1 )(b) and 
217 of the Constitution, the PFMA, Treasury Regulations and prescripts and 
the DPW Supply Chain Management Policy in respect of the Nkandla Project 
was improper and constitutes maladministration. 



10.6.2.3 Ms G Pasely, the Chief Quantity Surveyor showed exemplary conduct by 
raising her concerns about the excessive escalation in the cost of the Project. 
It is unfortunate that her concerns in this regard were not taken seriously. 

10.6.3. Officials of the SAPS: 

10.6.3.1 The SAPS officials failed to acquaint themselves with the authorizing 
instruments relating to the implementation of the Nkandla Project. They failed 



433 



Secure In Comfort A Report of the March 2014 

Public Protector 

SOUTH flfPICfl 

to apply their minds and adhere to the supply chain management policy 
framework in respect of the procurement of goods and services for the 
Nkandla Project. These failures constitute improper conduct and 
maladministration. 



10.6.3.2 Brigadier Adendorff, the Head of Security Advisory Service failed to comply 
with and or ensure compliance with the provisions of sections 1 95(1 )(b) and 
217 of the Constitution, the PFMA, Treasury Regulations and prescripts in 
respect of the area of her responsibility relating to the Nkandla Project was 
improper and constitutes maladministration 



10.6.4. Officials of the POD 



10.6.4.1 The DOD officials failed to acquaint themselves with the authorizing 
instruments relating to the implementation of the Nkandla Project. They failed 
to apply their minds and adhere to the supply chain management policy 
framework in respect of the procurement of goods and services for the 
Nkandla Project. These failures constitute improper conduct and 
maladministration. 



10.6.4.2 Lt Gen Ramlakan, the former Surgeon-General, failed to comply with and or 
ensure compliance with the provisions of sections 1 95(1 )(b) and 217 of the 
Constitution, the PFMA, Treasury Regulations and prescripts in respect of his 
area of responsibility relating to the Nkandla Project was improper and 
constitutes maladministration. 



434 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




10.6.5. The Contractors 



10.6.5.1 Mr Makhanya's assumption of multiple and conflicting roles as Principal 



Agent, the President's architect and procurer of some of the subcontractors 
which placed him in a position where the advice he gave was tainted by 
conflict of interest and not in the public interest, which led to uncontrolled 
scope creep, cost escalation and poor performance by some of the 
contractors. 



10.7. Was there any political interference in the implementation of this 
project? 

10.7.1.1 The former Minister of Public Works, Mr G Doidge, and Deputy Minister 



Bogopane-Zulu were at some stage involved in the implementation of the 
Nkandla Project. Their involvement, albeit for a short period of time, appears 
to have created an atmosphere that was perceived as political interference or 
pressure, although the evidence does not show any such intent on their part. 



10.7.1.2 The Task Team Report also indicated that officials were uneasy with the 
operational involvement of politicians in the Nkandla Project. 

10.7.1.3 Their involvement at trench level, including the Deputy Minister making 



suggestions on how to meet perceived security need, was ill advised 
although well intended in the light of failures in meeting the project timelines. 
While I would discourage such acts in similar future circumstances, I am 
unable to find their attempts at problem solving as constituting improper 
conduct or maladministration. 



435 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




10.8. Were funds transferred from other much needed DPW projects to fund 
this project? 

10.8.1.1 Funds were reallocated from the Inner City Regeneration and the Dolomite 



Risk Management Programmes of the DPW. Due to a lack of proper demand 
management and planning service delivery programmes of the DPW were 
negatively affected. This was in violation of section 237 of the Constitution 
and the Batho Pele White Paper and accordingly constitutes improper 
conduct and maladministration. 



1 0.9. Is the President liable for some of the cost incurred? 



10.9.1 .1 If a strict legal approach were to be adopted and the National Key Points Act 



was complied with, President Zuma would be held to the provisions of the 
Declaration of the Minister of Police issued on 08 April 2010, which informs 
him of the decision to declare his private Nkandla residence a National Key 
Points and directs him to secure the National Key Point at his own cost. 



10.9.1.2 However, that approach would not meet the dictates of fairness as the 



Presidents, Deputy Presidents, former Presidents and former Deputy 
Presidents are entitled, under the Cabinet Policy of 2003, to reasonable 
security upgrades, at their request or that of their office at state expense 
under the. Even on the understanding that some of the measures were 
unauthorized and transcended security measures as envisaged in the 
regulatory instruments and security evaluation findings, the questionable 
measures implemented exceed the financial means of an ordinary person. It 
is further clear from all communication by President Zuma that he was never 
familiarized with the provisions of the National Key Points Act and, 



436 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




specifically, the import of the declaration. The declaration itself was 
apparently delivered to his office in April 201 1 , a year after it was made and 
more than two years after the security installations had commenced. 



10.9.1.3 The DPW mismanaged the process initiated with a view to determining the 



cost to be paid by President Zuma in respect of security measures installed 
at and in support of his private residence at Nkandla and which was initially 
estimated at more than R10 million, leading to a situation where to date, 
there is no clarity on that matter. This constitutes improper conduct and 
maladministration. 



10.9.1.4 It is my considered view that as the President tacitly accepted the 



implementation of all measures at his residence and has unduly benefited 
from the enormous capital investment from the non-security installations at 
his private residence, a reasonable part of the expenditure towards the 
installations that were not identified as security measures in the list compiled 
by security experts in pursuit of the security evaluation, should be borne by 
him and his family. 



1 0.9.1 .5 It is also my considered view that the amount in question should be based on 



the cost of the installation of some or all the items that can't be conscionably 
accepted as security measures. These include the Visitors' Centre, cattle 
kraal and chicken run, swimming pool and amphitheatre. The President and 
his legal advisers, did not dispute this in their response to the Provisional 
Report. The President did not dispute during the investigation that he told me 
on 1 1 August 2013 that he requested the building of a larger kraal, and that 
he was willing to reimburse the state for the cost thereof. 



437 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




10.10. Were there ethical violations on the part of the President in respect of 
the project? 

10.10.1.1 President Zuma told Parliament that his family had built its own houses and 



the state had not built any for it or benefited them. This was not true. It is 
common cause that in the name of security, government built for the 
President and his family at his private residence a Visitors' Centre, cattle 
kraal and chicken run, swimming pool and amphitheatre among others. The 
President and his family clearly benefitted from this. 



10.10.1.2 I have accepted the evidence that he addressed Parliament in good faith and 



was not thinking about the Visitors' Centre, but his family dwellings when he 
made the statement. While his conduct could accordingly be legitimately 
construed as misleading Parliament, it appears to have been a bona fide 
mistake and I am accordingly unable to find that his conduct was in violation 
of paragraph 2 of the Executive Ethics Code. His statement is also consistent 
with those made by the Ministers of Public Works throughout the public 
outcry over the Nkandla expenditure. I am accordingly unable to find that his 
conduct was in violation of paragraph 2 of the Executive Ethics Code. 



10.10.1.3 Regarding President Zuma's conduct in respect of the use of state funds in 



the Nkandla Project, on the only evidence currently available, the President 
failed to apply his mind to the contents of the Declaration of his private 
residence as a National Key Points and specifically failed to implement 
security measures at own cost as directed by it or to approach the Minister of 
Police for a variation of the Declaration. 



438 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




10.10.1.4 It is my considered view that the President, as the head of South Africa 



Incorporated, was wearing two hats, that of the ultimate guardian of the 
resources of the people of South Africa and that of being a beneficiary of 
public privileges of some of the guardians of public power and state 
resources, but failed to discharge his responsibilities in terms of the latter. I 
believe the President should have ideally asked questions regarding the 
scale, cost and affordability of the Nkandla Project. He may have also 
benchmarked with some of his colleagues. He also may have asked whose 
idea were some of these measures and viewed them with circumspection, 
given Mr Makhanya's non-security background and the potential of 
misguided belief that his main role was to please the President as his client 
and benefactor. 



10.10.1.5 It is also not unreasonable to expect that when news broke in December 



2009 of alleged exorbitant amounts, at the time R65 million on questioned 
security installations at his private residence, the dictates of sections 96 and 
237 of the Constitution and the Executive Ethics Code required of President 
Zuma to take reasonable steps to order an immediate inquiry into the 
situation and immediate correction of any irregularities and excesses. 



10.10.1.6 His failure to act in protection of state resources constitutes a violation of 



paragraph 2 of the Executive Ethics Code and accordingly, amounts to 
conduct that is inconsistent with his office as a member of Cabinet, as 
contemplated by section 96 of the Constitution. 



10.10.1.7 Regarding the allegation that the President may have misled Parliament and 



accordingly violated the Executive Ethics Code when he announced that the 
renovations at his private residence were financed through a bank mortgage 
bond, I am unable to make a finding. Although having established through 



439 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




the Register of Financial Interests that the President has declared a 
mortgage bond in respect of his private residence at Nkandla since 2009, I 
am not able to establish if costs relating to his private renovations were 
separated from those of the state in the light of using the same contractors 
around the same time and the evidence of one invoice that had conflated the 
costs although with no proof of payment. 



10.11. Other Findings of Maladministration 



10.11.1.1 The occupation by the state of the land adjacent to that occupied by the 



President, and where security and other measures were constructed and 
installed by the DPW is unlawful and improper as it violates the provisions 
and requirements of the KwaZulu-Natal Ingonyama Trust Act, 1994 that 
requires a proper lease agreement. It also constitutes maladministration. 



1 0.1 1 .1 .2 The conduct of some of the role players unduly delayed the investigation. 



1 0.1 2. Systemic Deficiencies Observed During the Investigation 



10.12.1.1 The anomalies in the Nkandla Project point to the existence of systemic 



policy gaps and administrative deficiencies in the regulatory framework used 
as authority for implementing security measures at the private residences of 
ones of Presidents, Deputy Presidents, former Presidents and former Deputy 
Presidents, key among these being the absence of a cap and an integrated 
instrument such as the Ministerial Handbook, where all permissible measures 
can be found. 



440 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




10.12.1.2 In view of the fact that the Cabinet Policy of 2003 applies equally to all 



Presidents, Deputy Presidents, former Presidents and former Deputy 
Presidents, there is real risk of a repeat of the Nkandla excesses in respect 
of any of the four covered categories of public office bearers in the future. As 
the policy applies to all residences of incumbents in any of the four 
categories, the risk of unbridled expenditure in the future is very real and 
needs immediate curbing. 



10.12.1.3 DOD deficiencies, including no instruments for according and regulating the 



exercise of discretion and concentration of power on a single individual with 
no accountability arrangements, emphasized the need for a proper policy 
regime regulating security measures at the private residences of the 
President, Deputy President, Minister and Deputy Minister of Defence. 



10.12.1.4 Need for a clear demarcation of the roles of the SAPS, DPW and DOD in 
respect of such projects. 



1 0.1 3. The Impact of the Nkandla Project 



10.13.1.1 A number of the items installed by the DPW, such as the safe haven, 



swimming pool, paved roads and walkways as well as water and electricity 
supply, will require lifetime maintenance at cost to the state. Some 
maintenance costs may transcend the President's lifetime. 



1 0.1 3.1 .2 The military clinic also requires maintenance, supplies and permanent human 
resources as long as it exists, which may be beyond the President's lifetime. 



441 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




10.13.1.3 The future of the buildings constructed at the request of the SAPS also need 
to be determined. 



11.1. The President is to: 



11.1.1. Take steps, with the assistance of the National Treasury and the SAPS, to 



determine the reasonable cost of the measures implemented by the DPW at 
his private residence that do not relate to security, and which include Visitors' 
Centre, the amphitheatre, the cattle kraal and chicken run, the swimming 
pool. 



1 1 .1 .2. Pay a reasonable percentage of the cost of the measures as determined with 
the assistance of National Treasury, also considering the DPW 
apportionment document. 

11.1.3. Reprimand the Ministers involved for the appalling manner in which the 
Nkandla Project was handled and state funds were abused. 

1 1 .1 .4. Report to the National Assembly on his comments and actions on this report 
within 14 days. 



11. 



REMEDIAL ACTION 



Remedial action to be taken in terms of section 182(1)(c) of the 
constitution is the following: 



442 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




11.2. 

11.2.1. 

11.2.2. 

11.2.3. 

11.2.4. 

11.3. 
11.3.1. 



The Secretary to the Cabinet to take urgent steps to: 

Update the Cabinet Policy of 2003 to provide for a more detailed regime; 

Assist Cabinet to set clear standards on the security measures that can be 
taken, the reasonable cost that can be incurred by the state and the 
conditions subject to which current and former Presidents and Deputy 
Presidents would qualify for such measures; 

Take periodic measures to familiarize all members of the Cabinet with the 
parameters for enjoying executive benefits and the responsibilities they have 
to ensure that officials do not give them benefits transcending what they are 
entitled to under the law or policies; and 

The Department of Defence creates Standard Operating Procedures 
regulating the implementation of the benefits extended to Presidents, Deputy 
Presidents, the Minister and Deputy Minister of Defence and foreign 
dignitaries (at the request of the Minister of International Relations), which is 
aligned with the principles of equality, proportionality, reasonableness and 
justifiability, within 6 months from the issuing of this report. 

The Minister of Police to: 

Take urgent steps to expedite the review of the National Key Points Act to 
clarify its applicability to presidential security privileges and align it with the 
Constitution and post-apartheid developments; and 



443 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 ^^^^ 

PUfctK PROIEOOI? 
SOUTH flfPICfl 



1 1 .3.2. Ensure that no further security measures are installed at the President's 
private residence at Nkandla, except those determined to be absolutely 
necessary for the functionality of already installed measures. 

11.3.3. The Nkandla Project does not set a precedent for measures implemented in 
respect of any future President, Former President, Deputy President and 
Former Deputy President 

1 1 .4. The National Commissioner of the SAPS to: 

11.4.1. Identify officials that were and may still be involved in the Nkandla Project 
and implement measures to identify why prescripts were not complied with 
and on the basis thereof decide if disciplinary action should be taken; and 

11.4.2. Assist the Minister of Police in familiarizing himself with the contents of and 
his responsibilities under the National Key Points Act and the Cabinet Policy 
of 2003 and ensure that in future officials assisting Ministers to take action 
under any law include, in each relevant submission, a copy of the legal 
instrument in question and an outline of all steps required of the Minister. 

1 1 .5. The Director-General of the DPW to take urgent steps to: 

11.5.1. Identify officials that were and may still be involved in the Nkandla Project 
and implement measures to identify why prescripts were not complied with 
and on the basis thereof decide if disciplinary action should be taken; 



444 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




1 1 .5.2. With the assistance of the National Treasury, obtain advice from an 



independent and reputable security consultant on the security measures that 
were necessary for the protection of the President and estimated legitimate 
costs thereof. On the basis of this information, the DPW to determine the 
extent of the over expenditure on the Nkandla project and to obtain legal 
advice on the recovery thereof; 



1 1 .5.3. With the assistance of the National Treasury, determine the extent to which 



the SAPS and the DOD should be held liable for the expenditure incurred in 
the implementation of the Nkandla Project and to recover the amounts 
accordingly; 



11.5.4. Take urgent steps to enter into a lease agreement with the KwaZulu-Natal 
Ingonyama Trust Board in respect of the property occupied by the state 
adjacent to the President's private residence; 

1 1 .5.5. Take urgent steps to relocate the park homes to another organ of state that 
requires temporary accommodation; 

1 1 .5.6. Review the delegation of authority to Regional Offices of the Department; 

11.5.7. Ensure that all DPW staff involved in supply chain management is properly 
trained on deviations from the normal prescribed procurement processes; 

1 1 .5.8. Ensure that all DPW staff involved in the implementation and execution of 
projects are properly trained and capacitated to manage projects assigned to 
them; 



445 



Secure In Comfort 



A Report of the 
Public Protector 



March 2014 




1 1 .5.9. Comply with the provisions of GIAMA in respect of the assets acquired as a 
result of the Nkandla Project; and 

11.5.10. Develop a policy for the implementation of security measures at the private 
residences of the President, Deputy President and former Presidents and 
Deputy Presidents. 

1 1 .6. The Secretary for Defence, to take urgent steps to: 

11.6.1. Consolidate prescripts relating to the medical, transport and evacuation of 
Presidents, Deputy Presidents, former Presidents and former Deputy 
Presidents; 

1 1 .6.2. Determine the role played by DOD Officials, and in particular the SAMHS, in 
the Nkandla Project to ascertain if it was in line with their remit and if legal 
authority boundaries and procedures were complied with; and 

1 1 .6.3. Ensure certainty and accountability in respect of the future implementation of 
measures relating to 1 1 .6.1 above. 

12. MONITORING 

12.1. In order to monitor and ensure the implementation of my recommendations 



indicated above, the following steps must be taken: 



446 



Secure In Comfort A Report of the March 2014 

Public Protector 



12.2. When the President submits this report and his intentions regarding the 
findings and remedial action, within 14 days of its receipt, the Director 
General in the Presidency should notify my office and Cabinet. 

1 2.3. Accounting Officers of all organs of state required to take remedial action, are 
to provide implementation plans to my office not later than 01 May 2014. 

12.4. Status reports on implementation to be submitted by the affected accounting 
officers within three months and final reports on action taken to be submitted 
within 6 months of the issuing of this report. 

1 2.5. Public Office bearers in affected organs of state are to ensure compliance. 



"Let it never be said by future generations that indifference, cynicism or selfishness 
made us fail to live up to the ideals of humanism which the Nobel Peace Prize 
encapsulates." President of South Africa, Nelson Rholihlahla Mandela 




ADV. T N. MADONSELA 
PUBLIC PROTECTOR 
REPUBLIC OF SOUTH AFRICA 

19 March 2014 

Assisted by the Branch: Good Governance and Integrity, Public Protector SA 



447